{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 10, 2014 All Power Reactor Licensees on the Enclosed List
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 All Power Reactor Licensees on the Enclosed List September 10, 2014


==SUBJECT:==
==SUBJECT:==
Line 25: Line 25:
Regarding NTTF Recommendations 2.1 and 2.3, Mr. Robert Kuntz and Mr. Nicholas DiFrancesco are assigned as the lead project managers for flooding and seismic, respectively.
Regarding NTTF Recommendations 2.1 and 2.3, Mr. Robert Kuntz and Mr. Nicholas DiFrancesco are assigned as the lead project managers for flooding and seismic, respectively.
Mr. Kuntz may be reached at (301) 415-3733 and Mr. DiFrancesco may be reached at (301) 415-1115. Please use these project managers as your primary points of contact and include them on your distribution list to receive correspondence related to NTTF Recommendations 2.1 and 2.3.
Mr. Kuntz may be reached at (301) 415-3733 and Mr. DiFrancesco may be reached at (301) 415-1115. Please use these project managers as your primary points of contact and include them on your distribution list to receive correspondence related to NTTF Recommendations 2.1 and 2.3.
If you have any questions regarding this letter, please contact the project manager assigned for your plant on the enclosed list.
If you have any questions regarding this letter, please contact the project manager assigned for your plant on the enclosed list.
Sincerely,
Sincerely,  
                                              '
' a k Davis, Director a an Lessons-Learned Division ice of Nuclear Reactor Regulation  
a k Davis, Director a an Lessons-Learned Division ice of Nuclear Reactor Regulation


==Enclosures:==
==Enclosures:==
: 1. Project Manager Assignments
: 1. Project Manager Assignments
: 2. Addressee List cc w/encl: Distribution via Listserv
: 2. Addressee List cc w/encl: Distribution via Listserv  
 
Assignment of NRC Project Managers Relating to NRC Orders EA-12-049, EA-12-051, EA-13-109 and Near-Term Task Force Recommendation 9.3 Plant Name                    Project Manager          Contact Information Arkansas Nuclear One, Units 1                                  301-415-2833 Peter Bamford and 2                                                      Peter. Bamford@nrc.gov Beaver Valley Power Station,                                    301-415-3204 John Hughey Units 1 and 2                                              John.Hughey@nrc.gov Braidwood Station, Units 1 and                                  301-415-3204 John Hughey 2                                                          John.Hughey@nrc.gov Browns Ferry Nuclear Plant, Tony Brown          Tony.Brown@nrc.gov Units 1, 2 and 3 Brunswick Steam Electric                                        301-415-2833 Peter Bamford Plant, Units 1 and 2                                      Peter. Bamford_@nrc. gov Byron Station, Units 1 and 2                                    301-415-3204 John Hughey John.Hughey@nrc.gov Callaway Plant, Unit 1                                          301-415-2833 Peter Bamford Peter. Bamford@nrc.gov Calvert Cliffs Nuclear Power                                    301-415-5888 Jason Paige Plant, Units 1 and 2                                        Jason. Paige@nrc.gov Catawba Nuclear Station,                                        301-415-2833 Peter Bamford Units 1 and 2                                              Peter. Bamford@nrc.gov Clinton Power Station, Unit                                    301-415-2901 John Boska No.1                                                        John. Boska@nrc.gov Columbia Generating Station                                    301-415-1544 Stephen Monarque Stephen. Monarque@nrc.gov Comanche Peak Nuclear                                          301-415-1544 Stephen Monarque Power Plant, Units 1 and 2                              Stephen.Monarque@nrc.gov Cooper Nuclear Station                                          301-415-3204 John Hughey John. Hughey@nrc.gov Davis-Besse Nuclear Power                                      301-415-3204 John Hughey Station, Unit 1                                            John.Hughey@nrc.gov Diablo Canyon Nuclear Power Tony Brown          Tony. Brown@nrc.gov Plant, Unit Nos. 1 and 2 Donald C. Cook Nuclear Plant,                                  301-415-2901 John Boska Units 1 and 2                                              John. Boska@nrc.gov Dresden Nuclear Power                                          301-415-2901 John Boska Station, Units 2 and 3                                      John. Boska@nrc.gov Duane Arnold Energy Center                                      301-415-5888 Jason Paige Jason. Paige@nrc.gov Edwin I. Hatch Nuclear Plant,                                  301-415-5888 Jason Paige Units 1 and 2                                              Jason.Paige@nrc.gov Enclosure 1
 
Plant Name                      Project Manager      Contact Information Fermi, Unit 2                                                301-415-1544 Stephen Monarque Ste_Qhen. Mona~ue@nrc.gov Fort Calhoun Station, Unit 1            Tony Brown      Tony. Brown@nrc.gov Grand Gulf Nuclear Station,                                  301-415-2901 John Boska Unit 1                                                  John. Boska@nrc.:.9_ov H.B. Robinson Steam Electric                                301-415-5888 Jason Paige Plant, Unit No. 2                                        Jason. Pa_ig_e@nrc.:.9_ov Hope Creek Generating                                        301-415-2901 John Boska Station                                                  John.Boska@nrc.:.9_ov Indian Point Nuclear                                        301-415-2901 John Boska Generating, Unit Nos. 2 and 3                            John. Boska@nrc:9_ov James A. FitzPatrick Nuclear                                301-415-2833 Peter Bamford Power Plant                                            Peter. Bamford_@nrc.gov Joseph M. Farley Nuclear                                    301-415-1544 Stephen Monarque Plant Units 1 and 2                                  Stephen. Monarque@nrc.gov Lasalle County Station, Units                                301-415-2901 John Boska 1 and 2                                                  John. Boska@nrc:9_ov Limerick Generating Station,                                301-415-3204 John Hughey Units 1 and 2                                          John. Hughey@nrc.gov McGuire Nuclear Station, Units                              301-415-2901 John Boska 1 and 2                                                  John. Boska@nrc.gov Millstone Power Station, Units Tony Brown      Tony. Brown@nrc.gov 2 and 3 Monticello Nuclear Generating                                301-415-2833 Peter Bamford Plant, Unit 1                                          Peter. Bamford@nrc.gov Nine Mile Point Nuclear                                      301-415-5888 Jason Paige Station, Units 1 and 2                                  Jason.Paige@nrc.gov North Anna Power Station, Tony Brown      Tony.Brown@nrc.gov Units 1 and 2 Oconee Nuclear Station, Units                                301-415-2901 John Boska 1, 2, and 3                                              John.Boska_@nrc.gov Oyster Creek Nuclear                                        301-415-3204 John Hughey Generating Station                                      John. Hugh~nrc.gov Palisades Nuclear Plant                                      301-415-3204 John Hughey John. Hughey@nrc.gov Palo Verde Nuclear 301-415-2901 Generating Station, Units 1, 2,        John Boska John. Boska@nrc.gov and 3 Peach Bottom Atomic Power                                    301-415-2833 Peter Bamford Station, Units 2 and 3                                Peter. Bamford_@nrc.gov Perry Nuclear Power Plant,                                  301-415-2833 Peter Bamford Unit 1                                                Peter. Bamford@nrc.gov Pilgrim Nuclear Power Station                                301-415-1544 Stephen Monarque Stephen. Monarque@nrc:9_ov


Plant Name                     Project Manager     Contact Information Point Beach Nuclear Plant,                                   301-415-5888 Jason Paige Units 1 and 2                                           Jason. Paige@nrc.gov Prairie Island Nuclear 301-415-2833 Generating Plant, Units 1 and         Peter Bamford Peter. Bamford@nrc.gov 2
Assignment of NRC Project Managers Relating to NRC Orders EA-12-049, EA-12-051, EA-13-109 and Near-Term Task Force Recommendation 9.3 Plant Name Project Manager Contact Information Arkansas Nuclear One, Units 1 Peter Bamford 301-415-2833 and 2 Peter. Bamford@nrc.gov Beaver Valley Power Station, John Hughey 301-415-3204 Units 1 and 2 John.Hughey@nrc.gov Braidwood Station, Units 1 and John Hughey 301-415-3204 2
Quad Cities Nuclear Power                                    301-415-2901 John Boska Station, Units 1 and 2                                   John. Boska@nrc.g_ov R. E. Ginna Nuclear Power                                   301-415-2901 John Boska Plant                                                    John. Boska@nrc.g_ov River Bend Station                                           301-415-3204 John Hughey John. HLJg_he_y@_nrc.gov Salem Nuclear Generating                                     301-415-2901 John Boska Station, Units 1 and 2                                   John. Boska@nrc.gov Seabrook, Unit 1                                             301-415-5888 Jason Paige Jason. Paige@nrc.g_ov Sequoyah Nuclear Plant, Units Tony Brown       Tony. Brown@nrc.gov 1 and 2 Shearon Harris Nuclear Power                                301-415-1544 Stephen Monarque Plant, Unit 1                                       Ste_2_hen. Monarqu~@nrc.gov South Texas Project, Units 1 Tony Brown       Tony.Brown@nrc.gov and 2 St. Lucie Plant, Units 1 and 2                             301-415-5888 Jason Paige Jason. Paig_e@nrc.gov Surry Power Station, Unit Nos.
John.Hughey@nrc.gov Browns Ferry Nuclear Plant, Tony Brown Tony.Brown@nrc.gov Units 1, 2 and 3 Brunswick Steam Electric Peter Bamford 301-415-2833 Plant, Units 1 and 2 Peter. Bamford_@ nrc. gov Byron Station, Units 1 and 2 John Hughey 301-415-3204 John.Hughey@nrc.gov Callaway Plant, Unit 1 Peter Bamford 301-415-2833 Peter. Bamford@nrc.gov Calvert Cliffs Nuclear Power Jason Paige 301-415-5888 Plant, Units 1 and 2 Jason. Paige@nrc.gov Catawba Nuclear Station, Peter Bamford 301-415-2833 Units 1 and 2 Peter. Bamford@nrc.gov Clinton Power Station, Unit John Boska 301-415-2901 No.1 John. Boska@nrc.gov Columbia Generating Station Stephen Monarque 301-415-1544 Stephen. Monarque@nrc.gov Comanche Peak Nuclear Stephen Monarque 301-415-1544 Power Plant, Units 1 and 2 Stephen.Monarque@nrc.gov Cooper Nuclear Station John Hughey 301-415-3204 John. Hughey@nrc.gov Davis-Besse Nuclear Power John Hughey 301-415-3204 Station, Unit 1 John.Hughey@nrc.gov Diablo Canyon Nuclear Power Tony Brown Tony. Brown@nrc.gov Plant, Unit Nos. 1 and 2 Donald C. Cook Nuclear Plant, John Boska 301-415-2901 Units 1 and 2 John. Boska@nrc.gov Dresden Nuclear Power John Boska 301-415-2901 Station, Units 2 and 3 John. Boska@nrc.gov Duane Arnold Energy Center Jason Paige 301-415-5888 Jason. Paige@nrc.gov Edwin I. Hatch Nuclear Plant, Jason Paige 301-415-5888 Units 1 and 2 Jason.Paige@nrc.gov Plant Name Project Manager Contact Information 301-415-1544 Fermi, Unit 2 Stephen Monarque Ste_Qhen. Mona~ue@nrc.gov Fort Calhoun Station, Unit 1 Tony Brown Tony. Brown@nrc.gov 301-415-2901 Grand Gulf Nuclear Station, John Boska John. Boska@nrc.:.9_ov Unit 1 301-415-5888 H.B. Robinson Steam Electric Jason Paige Jason. Pa_ig_e@nrc.:.9_ov Plant, Unit No. 2 301-415-2901 Hope Creek Generating John Boska John.Boska@nrc.:.9_ov Station 301-415-2901 Indian Point Nuclear John Boska John. Boska@nrc:9_ov Generating, Unit Nos. 2 and 3 301-415-2833 James A. FitzPatrick Nuclear Peter Bamford Peter. Bamford_@nrc.gov Power Plant 301-415-1544 Joseph M. Farley Nuclear Stephen Monarque Stephen. Monarque@nrc.gov Plant Units 1 and 2 301-415-2901 Lasalle County Station, Units John Boska John. Boska@nrc:9_ov 1 and 2 301-415-3204 Limerick Generating Station, John Hughey John. Hughey@nrc.gov Units 1 and 2 301-415-2901 McGuire Nuclear Station, Units John Boska John. Boska@nrc.gov 1 and 2 Tony. Brown@nrc.gov Millstone Power Station, Units Tony Brown 2 and 3 301-415-2833 Monticello Nuclear Generating Peter Bamford Peter. Bamford@nrc.gov Plant, Unit 1 301-415-5888 Nine Mile Point Nuclear Jason Paige Jason.Paige@nrc.gov Station, Units 1 and 2 Tony.Brown@nrc.gov North Anna Power Station, Tony Brown Units 1 and 2 301-415-2901 Oconee Nuclear Station, Units John Boska John.Boska_@nrc.gov 1, 2, and 3 301-415-3204 Oyster Creek Nuclear John Hughey John. Hugh~nrc.gov Generating Station 301-415-3204 Palisades Nuclear Plant John Hughey John. Hughey@nrc.gov Palo Verde Nuclear 301-415-2901 Generating Station, Units 1, 2, John Boska John. Boska@nrc.gov and 3 301-415-2833 Peach Bottom Atomic Power Peter Bamford Peter. Bamford_@nrc.gov Station, Units 2 and 3 301-415-2833 Perry Nuclear Power Plant, Peter Bamford Peter. Bamford@nrc.gov Unit 1 301-415-1544 Pilgrim Nuclear Power Station Stephen Monarque Stephen. Monarque@nrc:9_ov Plant Name Project Manager Contact Information 301-415-5888 Point Beach Nuclear Plant, Jason Paige Jason. Paige@nrc.gov Units 1 and 2 301-415-2833 Prairie Island Nuclear Generating Plant, Units 1 and Peter Bamford Peter. Bamford@nrc.gov 2
Tony Brown       Tony.Brown@nrc.gov 1 and 2 Susquehanna Steam Electric                                  301-415-3204 John Hughey Station, Units 1 and 2                                  John. Hughey@nrc.gov Three Mile Island Nuclear                                  301-415-3204 John Hughey Station, Unit 1                                        John. HLJg_hey@nrc.g_ov Turkey Point Plant, Units 3                                 301-415-5888 Jason Paige and 4                                                  Jason. Paige_@nrc.gov Vermont Yankee Nuclear                                      301-415-5888 Jason Paige Power Station                                           Jason. Paig_e@nrc.gov Virgil c. Summer Nuclear Tony Brown       Tony. Brown@nrc.gov Station, Unit 1 Vogtle Electric Generating                                  301-415-1544 Stephen Monarque Plant, Units 1 and 2                                Stephen. Monarque@nrc.gov Waterford Steam Electric                                    301-415-2833 Peter Bamford Station, Unit 3                                        Peter. Bamford@nrc.gov Watts Bar Nuclear Plant, Units                             301-415-5888 Jason Paige 1 and 2                                                Jason. Paige@nrc.gov Wolf Creek Generating                                      301-415-1544 Stephen Monarque Station, Unit 1                                    Stephen. Monarq ue@nrc.g_ov
301-415-2901 Quad Cities Nuclear Power John Boska John. Boska@nrc.g_ov Station, Units 1 and 2 301-415-2901 R. E. Ginna Nuclear Power John Boska John. Boska@nrc.g_ov Plant 301-415-3204 River Bend Station John Hughey John. HLJg_he_y@_nrc.gov 301-415-2901 Salem Nuclear Generating John Boska John. Boska@nrc.gov Station, Units 1 and 2 301-415-5888 Seabrook, Unit 1 Jason Paige Jason. Paige@nrc.g_ov Sequoyah Nuclear Plant, Units Tony Brown Tony. Brown@nrc.gov 1 and 2 301-415-1544 Shearon Harris Nuclear Power Stephen Monarque Ste_2_hen. Monarqu~@nrc.gov Plant, Unit 1 Tony.Brown@nrc.gov South Texas Project, Units 1 Tony Brown and 2 301-415-5888 St. Lucie Plant, Units 1 and 2 Jason Paige Jason. Paig_e@nrc.gov Surry Power Station, Unit Nos.
Tony Brown Tony.Brown@nrc.gov 1 and 2 301-415-3204 Susquehanna Steam Electric John Hughey John. Hughey@nrc.gov Station, Units 1 and 2 301-415-3204 Three Mile Island Nuclear John Hughey John. HLJg_hey@nrc.g_ov Station, Unit 1 301-415-5888 Turkey Point Plant, Units 3 Jason Paige Jason. Paige_@nrc.gov and 4 301-415-5888 Vermont Yankee Nuclear Jason Paige Jason. Paig_e@nrc.gov Power Station Tony. Brown@nrc.gov Virgil c. Summer Nuclear Tony Brown Station, Unit 1 301-415-1544 Vogtle Electric Generating Stephen Monarque Stephen. Monarque@nrc.gov Plant, Units 1 and 2 301-415-2833 Waterford Steam Electric Peter Bamford Peter. Bamford@nrc.gov Station, Unit 3 301-415-5888 Watts Bar Nuclear Plant, Units Jason Paige Jason. Paige@nrc.gov 1 and 2 301-415-1544 Wolf Creek Generating Stephen Monarque Stephen. Monarq ue@nrc.g_ov Station, Unit 1


List of Addressees Arkansas Nuclear One                               Brunswick Steam Electric Plant Entergy Operations, Inc.                          Duke Energy Progress, Inc.
Arkansas Nuclear One Entergy Operations, Inc.
Docket Nos. 50-313 and 50-368                     Docket Nos. 50-325 and 50-324 License Nos. DPR-51 and NPF-6                     License Nos. DPR-71 and DPR-62 Vice President, Operations                         Mr. George T. Hamrick Arkansas Nuclear One                               Vice President Entergy Operations, Inc.                           Brunswick Steam Electric Plant 1448 S.R. 333                                     P. 0. Box 10429 Russellville, AR 72802                             Southport, NC 28461-0429 Beaver Valley Power Station                        Byron Station FirstEnergy Nuclear Operating Co.                 Exelon Generation Co., LLC Docket Nos. 50-334 and 50-412                     Docket Nos. STN 50-454 and STN 50-455 License Nos. DPR-66 and NPF-73                     License Nos. NPF-37 and NPF-66 Mr. Eric A. Larson                                 Mr. Michael J. Pacilio Site Vice President                               President and Chief Nuclear Officer Beaver Valley Power Station                       Exelon Nuclear P.O. Box 4, Route 168                             4300 Winfield Road Shippingport, PA 15077                             Warrenville, IL 60555 Braidwood Station                                 Callaway Plant Exelon Generation Co., LLC                         Union Electric Company Docket Nos. STN 50-456 and STN 50-457             Docket No. 50-483 License Nos. NPF-72 and NPF-77                     License No. NPF-30 Mr. Michael J. Pacilio                             Mr. Fadi Diya President and Chief Nuclear Officer               Senior Vice President and Exelon Nuclear                                     Chief Nuclear Officer 4300 Winfield Road                                 Ameren Missouri Warrenville, IL 60555                             Callaway Plant P.O. 620 Browns Ferry Nuclear Plant                         Fulton, MO 65251 Tennessee Valley Authority Docket Nos. 50-259, 50-260 and 50-296             Calvert Cliffs Nuclear Power Plant License Nos. DPR-33, DPR-52 and DPR-68             Calvert Cliffs Nuclear Power Plant, LLC Docket Nos. 50-317 and 50-318 Mr. Joseph W. Shea                                License Nos. DPR-53 and DPR-69 Vice President, Nuclear Licensing Tennessee Valley Authority                        Mr. George H. Gellrich 1101 Market Street, LP 3D-C                        Vice President Chattanooga, TN 37402-2801                        Calvert Cliffs Nuclear Power Plant, LLC Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702 Enclosure 2
List of Addressees Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802 Beaver Valley Power Station FirstEnergy Nuclear Operating Co.
Docket Nos. 50-334 and 50-412 License Nos. DPR-66 and NPF-73 Mr. Eric A. Larson Site Vice President Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Braidwood Station Exelon Generation Co., LLC Docket Nos. STN 50-456 and STN 50-457 License Nos. NPF-72 and NPF-77 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Browns Ferry Nuclear Plant Tennessee Valley Authority Docket Nos. 50-259, 50-260 and 50-296 License Nos. DPR-33, DPR-52 and DPR-68 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801 Brunswick Steam Electric Plant Duke Energy Progress, Inc.
Docket Nos. 50-325 and 50-324 License Nos. DPR-71 and DPR-62 Mr. George T. Hamrick Vice President Brunswick Steam Electric Plant P. 0. Box 10429 Southport, NC 28461-0429 Byron Station Exelon Generation Co., LLC Docket Nos. STN 50-454 and STN 50-455 License Nos. NPF-37 and NPF-66 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Callaway Plant Union Electric Company Docket No. 50-483 License No. NPF-30 Mr. Fadi Diya Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Plant P.O. 620 Fulton, MO 65251 Calvert Cliffs Nuclear Power Plant Calvert Cliffs Nuclear Power Plant, LLC Docket Nos. 50-317 and 50-318 License Nos. DPR-53 and DPR-69 Mr. George H. Gellrich Vice President Calvert Cliffs Nuclear Power Plant, LLC Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702  


Catawba Nuclear Station                  Cooper Nuclear Station Duke Energy Carolinas, LLC               Nebraska Public Power District Docket Nos. 50-413 and 50-414           Docket No. 50-298 License Nos. NPF-35 and NPF-52           License No. DPR-46 Mr. Kelvin Henderson                     Mr. Oscar A. Limpias Site Vice President                     Vice President -Nuclear and Chief Nuclear Duke Energy Carolinas, LLC               Officer Catawba Nuclear Station                 Nebraska Public Power District 4800 Concord Road                       72676 648A Avenue York, SC 29745                          P.O. Box 98 Brownville, NE 68321 Clinton Power Station Exelon Generation Co., LLC               Davis-Besse Nuclear Power Station Docket No. 50-461                       FirstEnergy Nuclear Operating Company License No. NPF-62                       Docket No. 50-346 License No. NPF-3 Mr. Michael J. Pacilio President and Chief Nuclear Officer     Mr. Raymond A. Lieb Exelon Nuclear                           Site Vice President 4300 Winfield Rd.                       FirstEnergy Nuclear Operating Company Warrenville, IL 60555                   c/o Davis-Besse NPS 5501 N. State Route 2 Columbia Generating Station             Oak Harbor, OH 43449-9760 Energy Northwest Docket No. 50-397                       Diablo Canyon Nuclear Power Plant License No. NPF-21                       Pacific Gas and Electric Company Docket Nos. 50-275 and 50-323 Mr. Mark E. Reddemann                   License Nos. DPR-80 and DPR-82 Chief Executive Officer Energy Northwest                         Mr. Edward D. Halpin MD 1023                                 Senior Vice President and Chief P.O. Box 968                             Nuclear Officer Richland, WA 99352                       Pacific Gas and Electric Company P.O. Box 56 Comanche Peak Nuclear Power Plant       Mail Code 104/6 Luminant Generation Company LLC         Avila Beach, CA 93424 Docket Nos. 50-445 and 50-446 License Nos. NPF-87 and NPF-89 Mr. Rafael Flores Senior Vice President and Chief Nuclear Officer Attn: Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043
Catawba Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-413 and 50-414 License Nos. NPF-35 and NPF-52 Mr. Kelvin Henderson Site Vice President Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road York, SC 297 45 Clinton Power Station Exelon Generation Co., LLC Docket No. 50-461 License No. NPF-62 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Rd.
Warrenville, IL 60555 Columbia Generating Station Energy Northwest Docket No. 50-397 License No. NPF-21 Mr. Mark E. Reddemann Chief Executive Officer Energy Northwest MD 1023 P.O. Box 968 Richland, WA 99352 Comanche Peak Nuclear Power Plant Luminant Generation Company LLC Docket Nos. 50-445 and 50-446 License Nos. NPF-87 and NPF-89 Mr. Rafael Flores Senior Vice President and Chief Nuclear Officer Attn: Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043 Cooper Nuclear Station Nebraska Public Power District Docket No. 50-298 License No. DPR-46 Mr. Oscar A. Limpias Vice President -Nuclear and Chief Nuclear Officer Nebraska Public Power District 72676 648A Avenue P.O. Box 98 Brownville, NE 68321 Davis-Besse Nuclear Power Station FirstEnergy Nuclear Operating Company Docket No. 50-346 License No. NPF-3 Mr. Raymond A. Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 N. State Route 2 Oak Harbor, OH 43449-9760 Diablo Canyon Nuclear Power Plant Pacific Gas and Electric Company Docket Nos. 50-275 and 50-323 License Nos. DPR-80 and DPR-82 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company P.O. Box 56 Mail Code 1 04/6 Avila Beach, CA 93424


Donald C. Cook Nuclear Plant               Fermi Indiana Michigan Power Company            DTE Electric Company Docket Nos. 50-315 and 50-316             Docket No. 50-341 License Nos. DPR-58 and DPR-7 4           License No. NPF-43 Mr. Lawrence J. Weber                     Joseph H. Plona, Senior Vice President Senior Vice President and Chief             and Chief Nuclear Officer Nuclear Officer                         DTE Electric Company Indiana Michigan Power Company           Fermi 2-210 NOC Nuclear Generation Group                 6400 North Dixie Highway One Cook Place                           Newport, Ml 48166 Bridgman, Ml 49106 Fort Calhoun Station Dresden Nuclear Power Station             Omaha Public Power District Exelon Generation Co., LLC               Docket No. 50-285 Docket Nos. 50-237 and 50-249            License No.DPR-40 License Nos. DPR-19 and DPR-25 Mr. Louis Cortopassi Mr. Michael J. Pacilio                    Vice President and Chief Nuclear Officer President and Chief Nuclear Officer       Omaha Public Power District Exelon Nuclear                            Fort Calhoun Station 4300 Winfield Road                        Mail Stop FC-2-4 Warrenville, IL 60555                    9610 Power Lane Blair, NE 68008 Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC          Grand Gulf Nuclear Station Docket No. 50-331                        Entergy Operations, Inc.
Donald C. Cook Nuclear Plant Indiana Michigan Power Company Docket Nos. 50-315 and 50-316 License Nos. DPR-58 and DPR-7 4 Mr. Lawrence J. Weber Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, Ml 49106 Dresden Nuclear Power Station Exelon Generation Co., LLC Docket Nos. 50-237 and 50-249 License Nos. DPR-19 and DPR-25 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC Docket No. 50-331 License No. DPR-49 Mr. Rich Anderson Site Vice President NextEra Energy Duane Arnold Energy Center 3277 DAEC Road Palo, lA 52324-9785 Edwin I. Hatch Nuclear Plant Southern Nuclear Operating Co. Inc.
License No. DPR-49                        Docket No. 50-416 License No. NPF-29 Mr. Rich Anderson Site Vice President                      Vice President, Operations NextEra Energy                            Entergy Operations, Inc.
Docket Nos. 50-321 and 50-366 License Nos. DPR-57 and NPF-5 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Co., Inc.
Duane Arnold Energy Center                Grand Gulf Nuclear Station 3277 DAEC Road                            P.O. Box 756 Palo, lA 52324-9785                      Port Gibson, MS 39150 Edwin I. Hatch Nuclear Plant              H.B Robinson Steam Electric Plant Southern Nuclear Operating Co. Inc.      Duke Energy Progress, Inc.
P.O. Box 1295/BIN B038 Birmingham, AL 35201-1295 Fermi DTE Electric Company Docket No. 50-341 License No. NPF-43 Joseph H. Plona, Senior Vice President and Chief Nuclear Officer DTE Electric Company Fermi 2-210 NOC 6400 North Dixie Highway Newport, Ml 48166 Fort Calhoun Station Omaha Public Power District Docket No. 50-285 License No.DPR-40 Mr. Louis Cortopassi Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station Mail Stop FC-2-4 9610 Power Lane Blair, NE 68008 Grand Gulf Nuclear Station Entergy Operations, Inc.
Docket Nos. 50-321 and 50-366            Docket No. 50-261 License Nos. DPR-57 and NPF-5            License No. DPR-23 Mr. C. R. Pierce                          Mr. William R. Gideon, Vice President Regulatory Affairs Director              H. B. Robinson Steam Electric Plant Southern Nuclear Operating Co., Inc.      3581 West Entrance Road P.O. Box 1295/BIN B038                    Hartsville, SC 29550 Birmingham, AL 35201-1295
Docket No. 50-416 License No. NPF-29 Vice President, Operations Entergy Operations, Inc.
Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150 H.B Robinson Steam Electric Plant Duke Energy Progress, Inc.
Docket No. 50-261 License No. DPR-23 Mr. William R. Gideon, Vice President H. B. Robinson Steam Electric Plant 3581 West Entrance Road Hartsville, SC 29550  


Hope Creek Generating Station                  LaSalle County Station PSEG Nuclear LLC                              Exelon Generation Co., LLC Docket No. 50-354                             Docket Nos. 50-373 and 50-374 License No. NPF-57                             License Nos. NPF-11 and NPF-18 Mr. Thomas Joyce                             Mr. Michael J. Pacilio President and Chief Nuclear Officer            President and Chief Nuclear Officer PSEG Nuclear LLC - N09                       Exelon Nuclear P. 0. Box 236                                 4300 Winfield Road Hancocks Bridge, NJ 08038                     Warrenville, IL 60555 Indian Point Nuclear Generating Units         Limerick Generating Station Entergy Nuclear Operations, Inc.             Exelon Generation Co., LLC Docket Nos. 50-247 and 50-286                 Docket Nos. 50-352 and 50-353 License Nos. DPR-26 and DPR-64               License Nos. NPF-39 and NPF-85 Vice President, Operations                   Mr. Michael J. Pacilio Entergy Nuclear Operations, Inc.             President and Chief Nuclear Officer Indian Point Energy Center                   Exelon Nuclear 450 Broadway, GSB                             4300 Winfield Road P.O. Box 249                                 Warrenville, IL 60555 Buchanan, NY 10511-0249 McGuire Nuclear Station James A. FitzPatrick Nuclear Power Plant     Duke Energy Carolinas, LLC Entergy Nuclear Operations, Inc.             Docket Nos. 50-369 and 50-370 Docket No. 50-333                             License Nos. NPF-9 and NPF-17 License No. DPR-59 Mr. Steven D. Capps Vice President, Operations                   Vice President - McGuire Site Entergy Nuclear Operations, Inc.             Duke Energy Carolinas, LLC James A. FitzPatrick Nuclear Power Plant     McGuire Nuclear Station P.O. Box 110                                 12700 Hagers Ferry Road Lycoming, NY 13093                           Huntersville, NC 28078-8985 Joseph M. Farley Nuclear Plant               Millstone Power Station Southern Nuclear Operating Company           Dominion Nuclear Connecticut, Inc.
Hope Creek Generating Station PSEG Nuclear LLC Docket No. 50-354 License No. NPF-57 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P. 0. Box 236 Hancocks Bridge, NJ 08038 Indian Point Nuclear Generating Units Entergy Nuclear Operations, Inc.
Docket Nos. 50-348 and 50-364                Docket Nos. 50-336 and 50-423 License Nos. NPF-2 and NPF-8                  License Nos. DPR-65 and NPF-49 Mr. C.R. Pierce                              Mr. David A. Heacock Regulatory Affairs Director                  President and Chief Nuclear Officer Southern Nuclear Operating Company            Virginia Electric & Power Company P.O. Box 1295/Bin 038                        lnnsbrook Technical Center Birmingham, AL 35201-1295                    5000 Dominion Boulevard Glen Allen, VA 23060-6711
Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64 Vice President, Operations Entergy Nuclear Operations, Inc.
Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 James A. FitzPatrick Nuclear Power Plant Entergy Nuclear Operations, Inc.
Docket No. 50-333 License No. DPR-59 Vice President, Operations Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company Docket Nos. 50-348 and 50-364 License Nos. NPF-2 and NPF-8 Mr. C.R. Pierce Regulatory Affairs Director Southern Nuclear Operating Company P.O. Box 1295/Bin 038 Birmingham, AL 35201-1295 LaSalle County Station Exelon Generation Co., LLC Docket Nos. 50-373 and 50-37 4 License Nos. NPF-11 and NPF-18 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Limerick Generating Station Exelon Generation Co., LLC Docket Nos. 50-352 and 50-353 License Nos. NPF-39 and NPF-85 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 McGuire Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-369 and 50-370 License Nos. NPF-9 and NPF-17 Mr. Steven D. Capps Vice President - McGuire Site Duke Energy Carolinas, LLC McGuire Nuclear Station 12700 Hagers Ferry Road Huntersville, NC 28078-8985 Millstone Power Station Dominion Nuclear Connecticut, Inc.
Docket Nos. 50-336 and 50-423 License Nos. DPR-65 and NPF-49 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric & Power Company lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711  


Monticello Nuclear Generating Plant       Oyster Creek Nuclear Generating Station Northern States Power Company             Exelon Generation Co., LLC Docket No. 50-263                         Docket No. 50-219 License No. DPR-22                         License No. DPR-16 Mrs. Karen D. Fili                         Mr. Michael J. Pacilio Site Vice President                       President and Chief Nuclear Officer Northern States Power Company             Exelon Nuclear Monticello Nuclear Generating Plant       4300 Winfield Road 2807 West County Road 75                   Warrenville, IL 60555 Monticello, MN 55362-9637 Palisades Nuclear Plant Nine Mile Point Nuclear Station           Entergy Nuclear Operations, Inc.
Monticello Nuclear Generating Plant Northern States Power Company Docket No. 50-263 License No. DPR-22 Mrs. Karen D. Fili Site Vice President Northern States Power Company Monticello Nuclear Generating Plant 2807 West County Road 75 Monticello, MN 55362-9637 Nine Mile Point Nuclear Station Exelon Generation Co., LLC Docket Nos. 50-220 and 50-41 0 License Nos. DPR-63 and NPF-69 Mr. Christopher Costanzo Vice President Nine Mile Point Exelon Generation Co., LLC P. 0. Box 63 Lycoming, NY 13093 North Anna Power Station Virginia Electric and Power Company Docket Nos. 50-338 and 50-339 License Nos. NPF-4 and NPF-7 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Oconee Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-269, 50-270 and 50-287 License Nos. DPR-38, DPR-47 and DPR-55 Mr. Scott Batson Vice President, Oconee Nuclear Station Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672 Oyster Creek Nuclear Generating Station Exelon Generation Co., LLC Docket No. 50-219 License No. DPR-16 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Palisades Nuclear Plant Entergy Nuclear Operations, Inc.
Exelon Generation Co., LLC                 Docket No. 50-255 Docket Nos. 50-220 and 50-41 0             License No. DPR-20 License Nos. DPR-63 and NPF-69 Vice President, Operations Mr. Christopher Costanzo                   Entergy Nuclear Operations, Inc.
Docket No. 50-255 License No. DPR-20 Vice President, Operations Entergy Nuclear Operations, Inc.
Vice President Nine Mile Point             Palisades Nuclear Plant Exelon Generation Co., LLC                 27780 Blue Star Memorial Highway P. 0. Box 63                               Covert, Ml 49043-9530 Lycoming, NY 13093 Palo Verde Nuclear Generating Station North Anna Power Station                   Arizona Public Service Company Virginia Electric and Power Company       Docket Nos. 50-528, 50-529 and 50-530 Docket Nos. 50-338 and 50-339              License Nos. NPF-41, NPF-51 and NPF-74 License Nos. NPF-4 and NPF-7 Mr. Randall K. Edington Mr. David A. Heacock                      Executive Vice President Nuclear and Chief President and Chief Nuclear Officer          Nuclear Officer Virginia Electric and Power Company        Arizona Public Service Company lnnsbrook Technical Center                P.O. Box 52034, MS 7602 5000 Dominion Boulevard                    Phoenix, AZ 85072-2034 Glen Allen, VA 23060-6711 Peach Bottom Atomic Power Station Oconee Nuclear Station                    Exelon Generation Co., LLC Duke Energy Carolinas, LLC                Docket Nos. 50-277 and 50-278 Docket Nos. 50-269, 50-270 and 50-287      License Nos. DPR-44 and DPR-56 License Nos. DPR-38, DPR-47 and DPR-55 Mr. Michael J. Pacilio Mr. Scott Batson                          President and Chief Nuclear Officer Vice President, Oconee Nuclear Station    Exelon Nuclear Duke Energy Carolinas, LLC                4300 Winfield Road 7800 Rochester Highway                    Warrenville, IL 60555 Seneca, SC 29672
Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, Ml 49043-9530 Palo Verde Nuclear Generating Station Arizona Public Service Company Docket Nos. 50-528, 50-529 and 50-530 License Nos. NPF-41, NPF-51 and NPF-74 Mr. Randall K. Edington Executive Vice President Nuclear and Chief Nuclear Officer Arizona Public Service Company P.O. Box 52034, MS 7602 Phoenix, AZ 85072-2034 Peach Bottom Atomic Power Station Exelon Generation Co., LLC Docket Nos. 50-277 and 50-278 License Nos. DPR-44 and DPR-56 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555  


Perry Nuclear Power Plant                   Quad Cities Nuclear Power Station FirstEnergy Nuclear Operating Co.           Exelon Generation Co., LLC Docket No. 50-440                           Docket Nos. 50-254 and 50-265 License No. NPF-58                           License Nos. DPR-29 and DPR-30 Mr. Ernest J. Harkness                       Mr. Michael J. Pacilio Site Vice President- Nuclear- Perry         President and Chief Nuclear Officer FirstEnergy Nuclear Operating Co.           Exelon Nuclear Perry Nuclear Power Plant                   4300 Winfield Road PO Box 97, A290                             Warrenville, IL 60555 Perry, OH 44081 R. E. Ginna Nuclear Power Plant Pilgrim Nuclear Power Station               Exelon Generation Co., LLC Entergy Nuclear Operations, Inc.             Docket No. 50-244 Docket No. 50-293                           License No. DPR-18 License No. DPR-35 Mr. Joseph E. Pacher Mr. John Dent, Jr.                           Vice President Vice President - Site VP                     R.E. Ginna Nuclear Power Plant Pilgrim Nuclear Power Station               Exelon Generation Co., LLC 600 Rocky Hill Road                          1503 Lake Road Plymouth, MA 02360-5508                     Ontario, NY 14519 Point Beach Nuclear Plant                   River Bend Station NextEra Energy Point Beach, LLC             Entergy Operations, Inc.
Perry Nuclear Power Plant FirstEnergy Nuclear Operating Co.
Docket Nos. 50-266 and 50-301               Docket No. 50-458 License Nos. DPR-24 and DPR-27               License No. NPF-47 Mr. Eric McCartney                           Vice President, Operations Site Vice President                         Entergy Operations, Inc.
Docket No. 50-440 License No. NPF-58 Mr. Ernest J. Harkness Site Vice President-Nuclear-Perry FirstEnergy Nuclear Operating Co.
NextEra Energy Point Beach, LLC             River Bend Station 6610 Nuclear Road                           5485 U.S. Highway 61 N Two Rivers, WI 54241-9516                   St. Francisville, LA 70775 Prairie Island Nuclear Generating Plant     Salem Nuclear Generating Station Northern States Power Company               PSEG Nuclear LLC.
Perry Nuclear Power Plant PO Box 97, A290 Perry, OH 44081 Pilgrim Nuclear Power Station Entergy Nuclear Operations, Inc.
Docket Nos. 50-282 and 50-306               Docket Nos. 50-272 and 50-311 License Nos. DPR-42 and DPR-60              License Nos. DPR-70 and DPR-75 Mr. Kevin K. Davison                        Mr. Thomas Joyce Site Vice President                          President and Chief Nuclear Officer Northern States Power Company                PSEG Nuclear LLC - N09 Prairie Island Nuclear Generating Plant      P. 0. Box 236 1717 Wakonade Drive East                    Hancocks Bridge, NJ 08038 Welch, MN 55089-9642
Docket No. 50-293 License No. DPR-35 Mr. John Dent, Jr.
Vice President - Site VP Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Point Beach Nuclear Plant NextEra Energy Point Beach, LLC Docket Nos. 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Mr. Eric McCartney Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516 Prairie Island Nuclear Generating Plant Northern States Power Company Docket Nos. 50-282 and 50-306 License Nos. DPR-42 and DPR-60 Mr. Kevin K. Davison Site Vice President Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Drive East Welch, MN 55089-9642 Quad Cities Nuclear Power Station Exelon Generation Co., LLC Docket Nos. 50-254 and 50-265 License Nos. DPR-29 and DPR-30 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 R. E. Ginna Nuclear Power Plant Exelon Generation Co., LLC Docket No. 50-244 License No. DPR-18 Mr. Joseph E. Pacher Vice President R.E. Ginna Nuclear Power Plant Exelon Generation Co., LLC 1503 Lake Road Ontario, NY 14519 River Bend Station Entergy Operations, Inc.
Docket No. 50-458 License No. NPF-47 Vice President, Operations Entergy Operations, Inc.
River Bend Station 5485 U.S. Highway 61 N St. Francisville, LA 70775 Salem Nuclear Generating Station PSEG Nuclear LLC.
Docket Nos. 50-272 and 50-311 License Nos. DPR-70 and DPR-75 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P. 0. Box 236 Hancocks Bridge, NJ 08038  


Seabrook Station                       St. Lucie Plant NextEra Energy Seabrook, LLC           Florida Power and Light Company Docket No. 50-443                      Docket Nos. 50-335 and 50-389 License No. NPF-86                      License Nos. DPR-67 and NPF-16 Mr. Dean Curtland                      Mr. Mano Nazar Vice President, Seabrook Station      President and Chief Nuclear Officer c/o Michael Ossing                    NextEra Energy NextEra Energy Seabrook, LLC          P. 0. Box 14000 P.O. Box 300                          Juno Beach, FL 33408-0420 Seabrook, NH 03874 Surry Power Station Sequoyah Nuclear Plant                Virginia Electric and Power Company Tennessee Valley Authority            Docket Nos. 50-280 and 50-281 Docket Nos. 50-327 and 50-328          License Nos. DPR-32 and DPR-37 License Nos. DPR-77 and DPR-79 Mr. David A. Heacock Mr. Joseph W. Shea                    President and Chief Nuclear Officer Vice President, Nuclear Licensing      Virginia Electric and Power Company Tennessee Valley Authority            lnnsbrook Technical Center 1101 Market Street LP 3D-C            5000 Dominion Blvd.
Seabrook Station NextEra Energy Seabrook, LLC Docket No. 50-443 License No. NPF-86 Mr. Dean Curtland Vice President, Seabrook Station c/o Michael Ossing NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Sequoyah Nuclear Plant Tennessee Valley Authority Docket Nos. 50-327 and 50-328 License Nos. DPR-77 and DPR-79 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street LP 3D-C Chattanooga, TN 37402-2801 Shearon Harris Nuclear Power Plant Duke Energy Progress, Inc.
Chattanooga, TN 37402-2801            Glen Allen, VA 23060-6711 Shearon Harris Nuclear Power Plant    Susquehanna Steam Electric Station Duke Energy Progress, Inc.            PPL Susquehanna, LLC Docket No. 50-400                      Docket Nos. 50-387 and 50-388 License No. NPF-63                    License Nos. NPF-14 and NPF-22 Mr. Ernest J. Kapopoulos, Jr.          Mr. Timothy S. Rausch Vice President                        Senior Vice President and Chief Nuclear Shearon Harris Nuclear Power Plant      Officer 5413 Shearon Harris Rd                PPL Susquehanna, LLC New Hill, NC 27562-0165                NUCSB3 769 Salem Boulevard South Texas Project                    Berwick, PA 18603-0467 STP Nuclear Operating Company Docket Nos. 50-498 and 50-499          Three Mile Island Nuclear Station License Nos. NPF-76 and NPF-80        Exelon Generation Company, LLC.
Docket No. 50-400 License No. NPF-63 Mr. Ernest J. Kapopoulos, Jr.
Docket No. 50-289 Mr. Dennis L. Koehl                    License No. DPR-50 President and CEO/CNO STP Nuclear Operating Company          Mr. Michael J. Pacilio South Texas Project                    President and Chief Nuclear Officer P.O. Box 289                          Exelon Nuclear Wadsworth, TX 77483                    4300 Winfield Road Warrenville, IL 60555
Vice President Shearon Harris Nuclear Power Plant 5413 Shearon Harris Rd New Hill, NC 27562-0165 South Texas Project STP Nuclear Operating Company Docket Nos. 50-498 and 50-499 License Nos. NPF-76 and NPF-80 Mr. Dennis L. Koehl President and CEO/CNO STP Nuclear Operating Company South Texas Project P.O. Box 289 Wadsworth, TX 77483 St. Lucie Plant Florida Power and Light Company Docket Nos. 50-335 and 50-389 License Nos. DPR-67 and NPF-16 Mr. Mano Nazar President and Chief Nuclear Officer NextEra Energy P. 0. Box 14000 Juno Beach, FL 33408-0420 Surry Power Station Virginia Electric and Power Company Docket Nos. 50-280 and 50-281 License Nos. DPR-32 and DPR-37 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company lnnsbrook Technical Center 5000 Dominion Blvd.
Glen Allen, VA 23060-6711 Susquehanna Steam Electric Station PPL Susquehanna, LLC Docket Nos. 50-387 and 50-388 License Nos. NPF-14 and NPF-22 Mr. Timothy S. Rausch Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC NUCSB3 769 Salem Boulevard Berwick, PA 18603-0467 Three Mile Island Nuclear Station Exelon Generation Company, LLC.
Docket No. 50-289 License No. DPR-50 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555  


Turkey Point Nuclear Generating Units     Waterford Steam Electric Station Florida Power and Light Company           Entergy Operations, Inc.
Turkey Point Nuclear Generating Units Florida Power and Light Company Docket Nos. 50-250 and 50-251 License Nos. DPR-31 and DPR-41 Mr. Mano Nazar President and Chief Nuclear Officer NextEra Energy P. 0. Box 14000 Juno Beach, FL 33408-0420 Vermont Yankee Nuclear Power Station Entergy Nuclear Operations, Inc.
Docket Nos. 50-250 and 50-251             Docket No. 50-382 License Nos. DPR-31 and DPR-41             License No. NPF-38 Mr. Mano Nazar                             Vice President, Operations President and Chief Nuclear Officer       Entergy Operations, Inc.
Docket No. 50-271 License No. DPR-28 Site Vice President Entergy Nuclear Operations, Inc.
NextEra Energy                             Waterford Steam Electric Station, Unit 3 P. 0. Box 14000                           17265 River Road Juno Beach, FL 33408-0420                 Killona, LA 70057-0751 Vermont Yankee Nuclear Power Station       Watts Bar Nuclear Plant Entergy Nuclear Operations, Inc.           Tennessee Valley Authority Docket No. 50-271                         Docket Nos. 50-390 and 50-391 License No. DPR-28                         License No. NPF-90 Site Vice President                       Mr. Joseph W. Shea Entergy Nuclear Operations, Inc.           Vice President, Nuclear Licensing Vermont Yankee Nuclear Power Station       Tennessee Valley Authority 320 Governor Hunt Road                     1101 Market Street, LP 3D-C Vernon, VT 05354                           Chattanooga, TN 37402-2801 Virgil C. Summer Nuclear Station          Wolf Creek Generating Station South Carolina Electric & Gas Company     Wolf Creek Nuclear Operating Corp.
Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 Virgil C. Summer Nuclear Station South Carolina Electric & Gas Company Docket No. 50-395 License No. NPF-12 Mr. Thomas D. Gatlin, Vice President Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 800 Jenkinsville, SC 29065 Vogtle Electric Generating Plant Southern Nuclear Operating Co., Inc.
Docket No. 50-395                         Docket No. 50-482 License No. NPF-12                         License No. NPF-42 Mr. Thomas D. Gatlin, Vice President       Mr. Adam C. Heflin Nuclear Operations                         President, Chief Executive Officer, South Carolina Electric & Gas Company       and Chief Nuclear Officer Virgil C. Summer Nuclear Station           Wolf Creek Nuclear Operating Corporation Post Office Box 88, Mail Code 800         P.O. Box 411 Jenkinsville, SC 29065                     Burlington, KS 66839 Vogtle Electric Generating Plant Southern Nuclear Operating Co., Inc.
Docket Nos. 50-424 and 50-425 License Nos. NPF-68 and NPF-81 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Co., Inc.
Docket Nos. 50-424 and 50-425 License Nos. NPF-68 and NPF-81 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Co., Inc.
P.O. Box 1295/Bin 038 Birmingham, AL 35201-1295
P.O. Box 1295/Bin 038 Birmingham, AL 35201-1295 Waterford Steam Electric Station Entergy Operations, Inc.
Docket No. 50-382 License No. NPF-38 Vice President, Operations Entergy Operations, Inc.
Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-0751 Watts Bar Nuclear Plant Tennessee Valley Authority Docket Nos. 50-390 and 50-391 License No. NPF-90 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37 402-2801 Wolf Creek Generating Station Wolf Creek Nuclear Operating Corp.
Docket No. 50-482 License No. NPF-42 Mr. Adam C. Heflin President, Chief Executive Officer, and Chief Nuclear Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839


ML14248A308 OFFICE     NRR/JLD/JOMB/PM         NRR/JLD/LA               NRR/JLD/JOMB/BC(A)
ML14248A308 OFFICE NRR/JLD/JOMB/PM NRR/JLD/LA NRR/JLD/JOMB/BC(A)
NAME       SMonarque (JBoska for) Slent                     MHalter DATE       09/09/14               09/08/14                 09/09/14 OFFICE     NRR/JLD/JHMB/BC         NRR/JLD/0 NAME       SWhaley                 JDavis DATE       09/09/14               09/10/14
NAME SMonarque (JBoska for)
Slent MHalter DATE 09/09/14 09/08/14 09/09/14 OFFICE NRR/JLD/JHMB/BC NRR/JLD/0 NAME SWhaley JDavis DATE 09/09/14 09/10/14  


Letter to All Power Reactor Licensees from Jack Davis dated September 10, 2014
Letter to All Power Reactor Licensees from Jack Davis dated September 10, 2014  


==SUBJECT:==
==SUBJECT:==
ASSIGNMENT OF PROJECT MANAGERS WITHIN THE U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION JAPAN-LESSONS LEARNED DIVISION DISTRIBUTION:
ASSIGNMENT OF PROJECT MANAGERS WITHIN THE U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION JAPAN-LESSONS LEARNED DIVISION DISTRIBUTION:
PUBLIC                           RidsNrrPMBrunswick          RidsNrrPMPalisades LPL 1-1 R/F                     RidsNrrPMByron              RidsNrrPMPaloVerde LPL 1-2 R/F                     RidsNrrPMCalaway            RidsNrrPMPeachBottom LPL2-1 R/F                       RidsNrrPMCalvertCiiffs      RidsNrrPMPerry LPL2-2 R/F                       RidsNrrPMCatawba            RidsNrrPMPilgrim LPL3-1 R/F                       RidsNrrPMCiinton            RidsNrrPMPointBeach LPL3-2 R/F                       RidsNrrPMColumbia            RidsNrrPMPrairielsland LPL4-1 R/F                       RidsNrrPMCooper              RidsNrrPMQuadCities LPL4-2 R/F                       RidsNrrPMComanchePeak        RidsNrrPMREGinna LP _WB R/F                       RidsnNrrPMCrystaiRiver      RidsNrrPMRiverBend RidsNrrDorl                     RidsNrrPMDavisBesse          RidsNrrPMRobinson RidsNrrDoriLpl1-1               RidsNrrPMDCCook              RidsNrrPMSalem RidsNrrDoriLpl1-2               RidsNrrPMDiabloCanyon        RidsNrrPMSanOnofre RidsNrrDoriLpl2-1               RidsNrrPMDresden            RidsNrrPMSeabrook RidsNrrDoriLpl2-2               RidsNrrDuaneArnold          RidsNrrPMSequoyah RidsNrrDoriLpl3-1               RidsNrrPMFarley              RidsNrrPMShearonHarris RidsNrrDoriLpl3-2               RidsNrrPMFermi              RidsNrrPMSouthTexas RidsNrrDoriLpl4-1               RidsNrrPMFitzPatrick        RidsNrrPMSummer Rids NrrDorl Lpl4-2             RidsNrrPMFortCalhoun        RidsNrrPMSurry RidsNrrDolrLp_WB                 RidsNrrPMGrandGulf          RidsNrrPMStLucie RidsOgcMaiiCenter               RidsNrrPMHatch              RidsNrrPMSusquehanna RidsNrrLAABaxter                 RidsNrrPMHopeCreek          RidsNrrPMThreeMilelsland RidsNrrLAJBurkhardt             RidsNrrPMindianPoint        RidsNrrPMTurkeyPoint RidsNrrLABCiayton               RidsNrrPMKewaunee            RidsN rrPMVermontYankee RidsNrrLASFigueroa               RidsNrrPMLaSalle            RidsNrrPMVogtle RidsNrrLAKGoldstein             RidsNrrPMLimerick            RidsNrrPMWaterford RidsNrrLASRohrer                 RidsNrrPMMcGuire            RidsNrrPMWattsBar1 RidsNrrLAMHenderson             RidsNrrPMMillstone          RidsNrrPMWattsBar2 RidsNrrLASLent                   RidsNrrMonticello            RidsNrrPMWolfCreek RidsNrrPMANO                     RidsNrrPMNineMilePoint      RidsRgn1 MaiiCenter Resource RidsNrrPMBeaverValley           RidsNrrPMNorthAnna          RidsRgn2MaiiCenter Resource RidsNrrPMBraidwood               RidsNrrPMOconee              RidsRgn3MaiiCenter Resource RidsNrrPMBrownsFerry             RidsNrrPMOysterCreek        RidsRgn4MaiiCenter Resource BHarris, NRR KWilliams, NSIR MMitchell, NRR}}
PUBLIC LPL 1-1 R/F LPL 1-2 R/F LPL2-1 R/F LPL2-2 R/F LPL3-1 R/F LPL3-2 R/F LPL4-1 R/F LPL4-2 R/F LP _WB R/F RidsNrrDorl RidsNrrDoriLpl1-1 RidsNrrDoriLpl1-2 RidsNrrDoriLpl2-1 RidsNrrDoriLpl2-2 RidsNrrDoriLpl3-1 RidsNrrDoriLpl3-2 RidsNrrDoriLpl4-1 Rids N rrDorl Lpl4-2 RidsNrrDolrLp_WB RidsOgcMaiiCenter RidsNrrLAABaxter RidsNrrLAJBurkhardt RidsNrrLABCiayton RidsNrrLASFigueroa RidsNrrLAKGoldstein RidsNrrLASRohrer RidsNrrLAMHenderson RidsNrrLASLent RidsNrrPMANO RidsNrrPMBeaverValley RidsNrrPMBraidwood RidsNrrPMBrownsFerry BHarris, NRR KWilliams, NSIR MMitchell, NRR RidsNrrPMBrunswick RidsNrrPMByron RidsNrrPMCalaway RidsNrrPMCalvertCiiffs RidsNrrPMCatawba RidsNrrPMCiinton RidsNrrPMColumbia RidsNrrPMCooper RidsNrrPMComanchePeak RidsnNrrPMCrystaiRiver RidsNrrPMDavisBesse RidsNrrPMDCCook RidsNrrPMDiabloCanyon RidsNrrPMDresden RidsNrrDuaneArnold RidsNrrPMFarley RidsNrrPMFermi RidsNrrPMFitzPatrick RidsNrrPMFortCalhoun RidsNrrPMGrandGulf RidsNrrPMHatch RidsNrrPMHopeCreek RidsNrrPMindianPoint RidsNrrPMKewaunee RidsNrrPMLaSalle RidsNrrPMLimerick RidsNrrPMMcGuire RidsNrrPMMillstone RidsNrrMonticello RidsNrrPMNineMilePoint RidsNrrPMNorthAnna RidsNrrPMOconee RidsNrrPMOysterCreek RidsNrrPMPalisades RidsNrrPMPaloVerde RidsNrrPMPeachBottom RidsNrrPMPerry RidsNrrPMPilgrim RidsNrrPMPointBeach RidsNrrPMPrairielsland RidsNrrPMQuadCities RidsNrrPMREGinna RidsNrrPMRiverBend RidsNrrPMRobinson RidsNrrPMSalem RidsNrrPMSanOnofre RidsNrrPMSeabrook RidsNrrPMSequoyah RidsNrrPMShearonHarris RidsNrrPMSouthTexas RidsNrrPMSummer RidsNrrPMSurry RidsNrrPMStLucie RidsNrrPMSusquehanna RidsNrrPMThreeMilelsland RidsNrrPMTurkeyPoint RidsN rrPMVermontYankee RidsNrrPMVogtle RidsNrrPMWaterford RidsNrrPMWattsBar1 RidsNrrPMWattsBar2 RidsNrrPMWolfCreek RidsRgn1 MaiiCenter Resource RidsRgn2MaiiCenter Resource RidsRgn3MaiiCenter Resource RidsRgn4MaiiCenter Resource}}

Latest revision as of 17:07, 10 January 2025

Assignment of Project Managers within the U.S. Nuclear Regulatory Commission, Office of Nuclear Reactor Regulation, Japan Lessons-Learned Division
ML14248A308
Person / Time
Site: Beaver Valley, Hatch, Calvert Cliffs, Dresden, Davis Besse, Browns Ferry, Fermi, Catawba, Grand Gulf, Cooper, Byron, Arkansas Nuclear, Braidwood, Columbia, Brunswick, Diablo Canyon, Callaway, Duane Arnold, Robinson, Clinton, Cook, Comanche Peak, 05000385  Constellation icon.png
Issue date: 09/10/2014
From: Jennifer Davis
Japan Lessons-Learned Division
To:
Calvert Cliffs, Duke Energy Carolinas, Duke Energy Progress, Energy Northwest, Entergy Operations, Exelon Generation Co, FirstEnergy Nuclear Operating Co, Luminant Generation Co, Nebraska Public Power District (NPPD), Pacific Gas & Electric Co, Tennessee Valley Authority, Union Electric Co
Monarque S, NRR/JLD, 415-1544
References
EA-12-049, EA-12-051, EA-13-109
Download: ML14248A308 (15)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 All Power Reactor Licensees on the Enclosed List September 10, 2014

SUBJECT:

ASSIGNMENT OF PROJECT MANAGERS WITHIN THE U.S. NUCLEAR REGULATORY COMMISSION, OFFICE OF NUCLEAR REACTOR REGULATION, JAPAN LESSONS-LEARNED DIVISION The purpose of this letter is to inform licensees that the U.S. Nuclear Regulatory Commission (NRC) has completed its assignment of project managers, within the Japan Lessons-Learned Division, to facilitate the managing of NRC Orders EA-12-049, "Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," EA-12-051, "Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," and EA-13-109, "Issuance of Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions" (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML12054A736, ML12054A679 and ML13143A321, respectively), and the Request for Information letter (ADAMS Accession No. ML12053A340) issued pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), regarding Recommendation 2.1 (seismic and flooding evaluations), Recommendation 2.3 (seismic and flooding walkdowns), and Recommendation 9.3 (emergency preparedness communication and staffing) of the Near-Term Task Force (NTTF) review of insights from the Fukushima Dai-ichi accident. includes the project managers and their respective assigned nuclear plants. These project managers will serve as the primary point of contact in processing NRC Orders EA 049, EA-12-051, and EA-13-109, and NTTF Recommendation 9.3fortheirassigned plants.

Please use these project managers as your primary points of contact and include them on your distribution list to receive correspondence related to the NRC orders and Recommendation 9.3 for their assigned plants.

Regarding NTTF Recommendations 2.1 and 2.3, Mr. Robert Kuntz and Mr. Nicholas DiFrancesco are assigned as the lead project managers for flooding and seismic, respectively.

Mr. Kuntz may be reached at (301) 415-3733 and Mr. DiFrancesco may be reached at (301) 415-1115. Please use these project managers as your primary points of contact and include them on your distribution list to receive correspondence related to NTTF Recommendations 2.1 and 2.3.

If you have any questions regarding this letter, please contact the project manager assigned for your plant on the enclosed list.

Sincerely,

' a k Davis, Director a an Lessons-Learned Division ice of Nuclear Reactor Regulation

Enclosures:

1. Project Manager Assignments
2. Addressee List cc w/encl: Distribution via Listserv

Assignment of NRC Project Managers Relating to NRC Orders EA-12-049, EA-12-051, EA-13-109 and Near-Term Task Force Recommendation 9.3 Plant Name Project Manager Contact Information Arkansas Nuclear One, Units 1 Peter Bamford 301-415-2833 and 2 Peter. Bamford@nrc.gov Beaver Valley Power Station, John Hughey 301-415-3204 Units 1 and 2 John.Hughey@nrc.gov Braidwood Station, Units 1 and John Hughey 301-415-3204 2

John.Hughey@nrc.gov Browns Ferry Nuclear Plant, Tony Brown Tony.Brown@nrc.gov Units 1, 2 and 3 Brunswick Steam Electric Peter Bamford 301-415-2833 Plant, Units 1 and 2 Peter. Bamford_@ nrc. gov Byron Station, Units 1 and 2 John Hughey 301-415-3204 John.Hughey@nrc.gov Callaway Plant, Unit 1 Peter Bamford 301-415-2833 Peter. Bamford@nrc.gov Calvert Cliffs Nuclear Power Jason Paige 301-415-5888 Plant, Units 1 and 2 Jason. Paige@nrc.gov Catawba Nuclear Station, Peter Bamford 301-415-2833 Units 1 and 2 Peter. Bamford@nrc.gov Clinton Power Station, Unit John Boska 301-415-2901 No.1 John. Boska@nrc.gov Columbia Generating Station Stephen Monarque 301-415-1544 Stephen. Monarque@nrc.gov Comanche Peak Nuclear Stephen Monarque 301-415-1544 Power Plant, Units 1 and 2 Stephen.Monarque@nrc.gov Cooper Nuclear Station John Hughey 301-415-3204 John. Hughey@nrc.gov Davis-Besse Nuclear Power John Hughey 301-415-3204 Station, Unit 1 John.Hughey@nrc.gov Diablo Canyon Nuclear Power Tony Brown Tony. Brown@nrc.gov Plant, Unit Nos. 1 and 2 Donald C. Cook Nuclear Plant, John Boska 301-415-2901 Units 1 and 2 John. Boska@nrc.gov Dresden Nuclear Power John Boska 301-415-2901 Station, Units 2 and 3 John. Boska@nrc.gov Duane Arnold Energy Center Jason Paige 301-415-5888 Jason. Paige@nrc.gov Edwin I. Hatch Nuclear Plant, Jason Paige 301-415-5888 Units 1 and 2 Jason.Paige@nrc.gov Plant Name Project Manager Contact Information 301-415-1544 Fermi, Unit 2 Stephen Monarque Ste_Qhen. Mona~ue@nrc.gov Fort Calhoun Station, Unit 1 Tony Brown Tony. Brown@nrc.gov 301-415-2901 Grand Gulf Nuclear Station, John Boska John. Boska@nrc.:.9_ov Unit 1 301-415-5888 H.B. Robinson Steam Electric Jason Paige Jason. Pa_ig_e@nrc.:.9_ov Plant, Unit No. 2 301-415-2901 Hope Creek Generating John Boska John.Boska@nrc.:.9_ov Station 301-415-2901 Indian Point Nuclear John Boska John. Boska@nrc:9_ov Generating, Unit Nos. 2 and 3 301-415-2833 James A. FitzPatrick Nuclear Peter Bamford Peter. Bamford_@nrc.gov Power Plant 301-415-1544 Joseph M. Farley Nuclear Stephen Monarque Stephen. Monarque@nrc.gov Plant Units 1 and 2 301-415-2901 Lasalle County Station, Units John Boska John. Boska@nrc:9_ov 1 and 2 301-415-3204 Limerick Generating Station, John Hughey John. Hughey@nrc.gov Units 1 and 2 301-415-2901 McGuire Nuclear Station, Units John Boska John. Boska@nrc.gov 1 and 2 Tony. Brown@nrc.gov Millstone Power Station, Units Tony Brown 2 and 3 301-415-2833 Monticello Nuclear Generating Peter Bamford Peter. Bamford@nrc.gov Plant, Unit 1 301-415-5888 Nine Mile Point Nuclear Jason Paige Jason.Paige@nrc.gov Station, Units 1 and 2 Tony.Brown@nrc.gov North Anna Power Station, Tony Brown Units 1 and 2 301-415-2901 Oconee Nuclear Station, Units John Boska John.Boska_@nrc.gov 1, 2, and 3 301-415-3204 Oyster Creek Nuclear John Hughey John. Hugh~nrc.gov Generating Station 301-415-3204 Palisades Nuclear Plant John Hughey John. Hughey@nrc.gov Palo Verde Nuclear 301-415-2901 Generating Station, Units 1, 2, John Boska John. Boska@nrc.gov and 3 301-415-2833 Peach Bottom Atomic Power Peter Bamford Peter. Bamford_@nrc.gov Station, Units 2 and 3 301-415-2833 Perry Nuclear Power Plant, Peter Bamford Peter. Bamford@nrc.gov Unit 1 301-415-1544 Pilgrim Nuclear Power Station Stephen Monarque Stephen. Monarque@nrc:9_ov Plant Name Project Manager Contact Information 301-415-5888 Point Beach Nuclear Plant, Jason Paige Jason. Paige@nrc.gov Units 1 and 2 301-415-2833 Prairie Island Nuclear Generating Plant, Units 1 and Peter Bamford Peter. Bamford@nrc.gov 2

301-415-2901 Quad Cities Nuclear Power John Boska John. Boska@nrc.g_ov Station, Units 1 and 2 301-415-2901 R. E. Ginna Nuclear Power John Boska John. Boska@nrc.g_ov Plant 301-415-3204 River Bend Station John Hughey John. HLJg_he_y@_nrc.gov 301-415-2901 Salem Nuclear Generating John Boska John. Boska@nrc.gov Station, Units 1 and 2 301-415-5888 Seabrook, Unit 1 Jason Paige Jason. Paige@nrc.g_ov Sequoyah Nuclear Plant, Units Tony Brown Tony. Brown@nrc.gov 1 and 2 301-415-1544 Shearon Harris Nuclear Power Stephen Monarque Ste_2_hen. Monarqu~@nrc.gov Plant, Unit 1 Tony.Brown@nrc.gov South Texas Project, Units 1 Tony Brown and 2 301-415-5888 St. Lucie Plant, Units 1 and 2 Jason Paige Jason. Paig_e@nrc.gov Surry Power Station, Unit Nos.

Tony Brown Tony.Brown@nrc.gov 1 and 2 301-415-3204 Susquehanna Steam Electric John Hughey John. Hughey@nrc.gov Station, Units 1 and 2 301-415-3204 Three Mile Island Nuclear John Hughey John. HLJg_hey@nrc.g_ov Station, Unit 1 301-415-5888 Turkey Point Plant, Units 3 Jason Paige Jason. Paige_@nrc.gov and 4 301-415-5888 Vermont Yankee Nuclear Jason Paige Jason. Paig_e@nrc.gov Power Station Tony. Brown@nrc.gov Virgil c. Summer Nuclear Tony Brown Station, Unit 1 301-415-1544 Vogtle Electric Generating Stephen Monarque Stephen. Monarque@nrc.gov Plant, Units 1 and 2 301-415-2833 Waterford Steam Electric Peter Bamford Peter. Bamford@nrc.gov Station, Unit 3 301-415-5888 Watts Bar Nuclear Plant, Units Jason Paige Jason. Paige@nrc.gov 1 and 2 301-415-1544 Wolf Creek Generating Stephen Monarque Stephen. Monarq ue@nrc.g_ov Station, Unit 1

Arkansas Nuclear One Entergy Operations, Inc.

List of Addressees Docket Nos. 50-313 and 50-368 License Nos. DPR-51 and NPF-6 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802 Beaver Valley Power Station FirstEnergy Nuclear Operating Co.

Docket Nos. 50-334 and 50-412 License Nos. DPR-66 and NPF-73 Mr. Eric A. Larson Site Vice President Beaver Valley Power Station P.O. Box 4, Route 168 Shippingport, PA 15077 Braidwood Station Exelon Generation Co., LLC Docket Nos. STN 50-456 and STN 50-457 License Nos. NPF-72 and NPF-77 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Browns Ferry Nuclear Plant Tennessee Valley Authority Docket Nos. 50-259, 50-260 and 50-296 License Nos. DPR-33, DPR-52 and DPR-68 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37402-2801 Brunswick Steam Electric Plant Duke Energy Progress, Inc.

Docket Nos. 50-325 and 50-324 License Nos. DPR-71 and DPR-62 Mr. George T. Hamrick Vice President Brunswick Steam Electric Plant P. 0. Box 10429 Southport, NC 28461-0429 Byron Station Exelon Generation Co., LLC Docket Nos. STN 50-454 and STN 50-455 License Nos. NPF-37 and NPF-66 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Callaway Plant Union Electric Company Docket No. 50-483 License No. NPF-30 Mr. Fadi Diya Senior Vice President and Chief Nuclear Officer Ameren Missouri Callaway Plant P.O. 620 Fulton, MO 65251 Calvert Cliffs Nuclear Power Plant Calvert Cliffs Nuclear Power Plant, LLC Docket Nos. 50-317 and 50-318 License Nos. DPR-53 and DPR-69 Mr. George H. Gellrich Vice President Calvert Cliffs Nuclear Power Plant, LLC Calvert Cliffs Nuclear Power Plant 1650 Calvert Cliffs Parkway Lusby, MD 20657-4702

Catawba Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-413 and 50-414 License Nos. NPF-35 and NPF-52 Mr. Kelvin Henderson Site Vice President Duke Energy Carolinas, LLC Catawba Nuclear Station 4800 Concord Road York, SC 297 45 Clinton Power Station Exelon Generation Co., LLC Docket No. 50-461 License No. NPF-62 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Rd.

Warrenville, IL 60555 Columbia Generating Station Energy Northwest Docket No. 50-397 License No. NPF-21 Mr. Mark E. Reddemann Chief Executive Officer Energy Northwest MD 1023 P.O. Box 968 Richland, WA 99352 Comanche Peak Nuclear Power Plant Luminant Generation Company LLC Docket Nos. 50-445 and 50-446 License Nos. NPF-87 and NPF-89 Mr. Rafael Flores Senior Vice President and Chief Nuclear Officer Attn: Regulatory Affairs Luminant Generation Company LLC P.O. Box 1002 Glen Rose, TX 76043 Cooper Nuclear Station Nebraska Public Power District Docket No. 50-298 License No. DPR-46 Mr. Oscar A. Limpias Vice President -Nuclear and Chief Nuclear Officer Nebraska Public Power District 72676 648A Avenue P.O. Box 98 Brownville, NE 68321 Davis-Besse Nuclear Power Station FirstEnergy Nuclear Operating Company Docket No. 50-346 License No. NPF-3 Mr. Raymond A. Lieb Site Vice President FirstEnergy Nuclear Operating Company c/o Davis-Besse NPS 5501 N. State Route 2 Oak Harbor, OH 43449-9760 Diablo Canyon Nuclear Power Plant Pacific Gas and Electric Company Docket Nos. 50-275 and 50-323 License Nos. DPR-80 and DPR-82 Mr. Edward D. Halpin Senior Vice President and Chief Nuclear Officer Pacific Gas and Electric Company P.O. Box 56 Mail Code 1 04/6 Avila Beach, CA 93424

Donald C. Cook Nuclear Plant Indiana Michigan Power Company Docket Nos. 50-315 and 50-316 License Nos. DPR-58 and DPR-7 4 Mr. Lawrence J. Weber Senior Vice President and Chief Nuclear Officer Indiana Michigan Power Company Nuclear Generation Group One Cook Place Bridgman, Ml 49106 Dresden Nuclear Power Station Exelon Generation Co., LLC Docket Nos. 50-237 and 50-249 License Nos. DPR-19 and DPR-25 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Duane Arnold Energy Center NextEra Energy Duane Arnold, LLC Docket No. 50-331 License No. DPR-49 Mr. Rich Anderson Site Vice President NextEra Energy Duane Arnold Energy Center 3277 DAEC Road Palo, lA 52324-9785 Edwin I. Hatch Nuclear Plant Southern Nuclear Operating Co. Inc.

Docket Nos. 50-321 and 50-366 License Nos. DPR-57 and NPF-5 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Co., Inc.

P.O. Box 1295/BIN B038 Birmingham, AL 35201-1295 Fermi DTE Electric Company Docket No. 50-341 License No. NPF-43 Joseph H. Plona, Senior Vice President and Chief Nuclear Officer DTE Electric Company Fermi 2-210 NOC 6400 North Dixie Highway Newport, Ml 48166 Fort Calhoun Station Omaha Public Power District Docket No. 50-285 License No.DPR-40 Mr. Louis Cortopassi Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station Mail Stop FC-2-4 9610 Power Lane Blair, NE 68008 Grand Gulf Nuclear Station Entergy Operations, Inc.

Docket No. 50-416 License No. NPF-29 Vice President, Operations Entergy Operations, Inc.

Grand Gulf Nuclear Station P.O. Box 756 Port Gibson, MS 39150 H.B Robinson Steam Electric Plant Duke Energy Progress, Inc.

Docket No. 50-261 License No. DPR-23 Mr. William R. Gideon, Vice President H. B. Robinson Steam Electric Plant 3581 West Entrance Road Hartsville, SC 29550

Hope Creek Generating Station PSEG Nuclear LLC Docket No. 50-354 License No. NPF-57 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P. 0. Box 236 Hancocks Bridge, NJ 08038 Indian Point Nuclear Generating Units Entergy Nuclear Operations, Inc.

Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64 Vice President, Operations Entergy Nuclear Operations, Inc.

Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 James A. FitzPatrick Nuclear Power Plant Entergy Nuclear Operations, Inc.

Docket No. 50-333 License No. DPR-59 Vice President, Operations Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093 Joseph M. Farley Nuclear Plant Southern Nuclear Operating Company Docket Nos. 50-348 and 50-364 License Nos. NPF-2 and NPF-8 Mr. C.R. Pierce Regulatory Affairs Director Southern Nuclear Operating Company P.O. Box 1295/Bin 038 Birmingham, AL 35201-1295 LaSalle County Station Exelon Generation Co., LLC Docket Nos. 50-373 and 50-37 4 License Nos. NPF-11 and NPF-18 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Limerick Generating Station Exelon Generation Co., LLC Docket Nos. 50-352 and 50-353 License Nos. NPF-39 and NPF-85 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 McGuire Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-369 and 50-370 License Nos. NPF-9 and NPF-17 Mr. Steven D. Capps Vice President - McGuire Site Duke Energy Carolinas, LLC McGuire Nuclear Station 12700 Hagers Ferry Road Huntersville, NC 28078-8985 Millstone Power Station Dominion Nuclear Connecticut, Inc.

Docket Nos. 50-336 and 50-423 License Nos. DPR-65 and NPF-49 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric & Power Company lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711

Monticello Nuclear Generating Plant Northern States Power Company Docket No. 50-263 License No. DPR-22 Mrs. Karen D. Fili Site Vice President Northern States Power Company Monticello Nuclear Generating Plant 2807 West County Road 75 Monticello, MN 55362-9637 Nine Mile Point Nuclear Station Exelon Generation Co., LLC Docket Nos. 50-220 and 50-41 0 License Nos. DPR-63 and NPF-69 Mr. Christopher Costanzo Vice President Nine Mile Point Exelon Generation Co., LLC P. 0. Box 63 Lycoming, NY 13093 North Anna Power Station Virginia Electric and Power Company Docket Nos. 50-338 and 50-339 License Nos. NPF-4 and NPF-7 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company lnnsbrook Technical Center 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Oconee Nuclear Station Duke Energy Carolinas, LLC Docket Nos. 50-269, 50-270 and 50-287 License Nos. DPR-38, DPR-47 and DPR-55 Mr. Scott Batson Vice President, Oconee Nuclear Station Duke Energy Carolinas, LLC 7800 Rochester Highway Seneca, SC 29672 Oyster Creek Nuclear Generating Station Exelon Generation Co., LLC Docket No. 50-219 License No. DPR-16 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 Palisades Nuclear Plant Entergy Nuclear Operations, Inc.

Docket No. 50-255 License No. DPR-20 Vice President, Operations Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, Ml 49043-9530 Palo Verde Nuclear Generating Station Arizona Public Service Company Docket Nos. 50-528, 50-529 and 50-530 License Nos. NPF-41, NPF-51 and NPF-74 Mr. Randall K. Edington Executive Vice President Nuclear and Chief Nuclear Officer Arizona Public Service Company P.O. Box 52034, MS 7602 Phoenix, AZ 85072-2034 Peach Bottom Atomic Power Station Exelon Generation Co., LLC Docket Nos. 50-277 and 50-278 License Nos. DPR-44 and DPR-56 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

Perry Nuclear Power Plant FirstEnergy Nuclear Operating Co.

Docket No. 50-440 License No. NPF-58 Mr. Ernest J. Harkness Site Vice President-Nuclear-Perry FirstEnergy Nuclear Operating Co.

Perry Nuclear Power Plant PO Box 97, A290 Perry, OH 44081 Pilgrim Nuclear Power Station Entergy Nuclear Operations, Inc.

Docket No. 50-293 License No. DPR-35 Mr. John Dent, Jr.

Vice President - Site VP Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508 Point Beach Nuclear Plant NextEra Energy Point Beach, LLC Docket Nos. 50-266 and 50-301 License Nos. DPR-24 and DPR-27 Mr. Eric McCartney Site Vice President NextEra Energy Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516 Prairie Island Nuclear Generating Plant Northern States Power Company Docket Nos. 50-282 and 50-306 License Nos. DPR-42 and DPR-60 Mr. Kevin K. Davison Site Vice President Northern States Power Company Prairie Island Nuclear Generating Plant 1717 Wakonade Drive East Welch, MN 55089-9642 Quad Cities Nuclear Power Station Exelon Generation Co., LLC Docket Nos. 50-254 and 50-265 License Nos. DPR-29 and DPR-30 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 R. E. Ginna Nuclear Power Plant Exelon Generation Co., LLC Docket No. 50-244 License No. DPR-18 Mr. Joseph E. Pacher Vice President R.E. Ginna Nuclear Power Plant Exelon Generation Co., LLC 1503 Lake Road Ontario, NY 14519 River Bend Station Entergy Operations, Inc.

Docket No. 50-458 License No. NPF-47 Vice President, Operations Entergy Operations, Inc.

River Bend Station 5485 U.S. Highway 61 N St. Francisville, LA 70775 Salem Nuclear Generating Station PSEG Nuclear LLC.

Docket Nos. 50-272 and 50-311 License Nos. DPR-70 and DPR-75 Mr. Thomas Joyce President and Chief Nuclear Officer PSEG Nuclear LLC - N09 P. 0. Box 236 Hancocks Bridge, NJ 08038

Seabrook Station NextEra Energy Seabrook, LLC Docket No. 50-443 License No. NPF-86 Mr. Dean Curtland Vice President, Seabrook Station c/o Michael Ossing NextEra Energy Seabrook, LLC P.O. Box 300 Seabrook, NH 03874 Sequoyah Nuclear Plant Tennessee Valley Authority Docket Nos. 50-327 and 50-328 License Nos. DPR-77 and DPR-79 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street LP 3D-C Chattanooga, TN 37402-2801 Shearon Harris Nuclear Power Plant Duke Energy Progress, Inc.

Docket No. 50-400 License No. NPF-63 Mr. Ernest J. Kapopoulos, Jr.

Vice President Shearon Harris Nuclear Power Plant 5413 Shearon Harris Rd New Hill, NC 27562-0165 South Texas Project STP Nuclear Operating Company Docket Nos. 50-498 and 50-499 License Nos. NPF-76 and NPF-80 Mr. Dennis L. Koehl President and CEO/CNO STP Nuclear Operating Company South Texas Project P.O. Box 289 Wadsworth, TX 77483 St. Lucie Plant Florida Power and Light Company Docket Nos. 50-335 and 50-389 License Nos. DPR-67 and NPF-16 Mr. Mano Nazar President and Chief Nuclear Officer NextEra Energy P. 0. Box 14000 Juno Beach, FL 33408-0420 Surry Power Station Virginia Electric and Power Company Docket Nos. 50-280 and 50-281 License Nos. DPR-32 and DPR-37 Mr. David A. Heacock President and Chief Nuclear Officer Virginia Electric and Power Company lnnsbrook Technical Center 5000 Dominion Blvd.

Glen Allen, VA 23060-6711 Susquehanna Steam Electric Station PPL Susquehanna, LLC Docket Nos. 50-387 and 50-388 License Nos. NPF-14 and NPF-22 Mr. Timothy S. Rausch Senior Vice President and Chief Nuclear Officer PPL Susquehanna, LLC NUCSB3 769 Salem Boulevard Berwick, PA 18603-0467 Three Mile Island Nuclear Station Exelon Generation Company, LLC.

Docket No. 50-289 License No. DPR-50 Mr. Michael J. Pacilio President and Chief Nuclear Officer Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

Turkey Point Nuclear Generating Units Florida Power and Light Company Docket Nos. 50-250 and 50-251 License Nos. DPR-31 and DPR-41 Mr. Mano Nazar President and Chief Nuclear Officer NextEra Energy P. 0. Box 14000 Juno Beach, FL 33408-0420 Vermont Yankee Nuclear Power Station Entergy Nuclear Operations, Inc.

Docket No. 50-271 License No. DPR-28 Site Vice President Entergy Nuclear Operations, Inc.

Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 Virgil C. Summer Nuclear Station South Carolina Electric & Gas Company Docket No. 50-395 License No. NPF-12 Mr. Thomas D. Gatlin, Vice President Nuclear Operations South Carolina Electric & Gas Company Virgil C. Summer Nuclear Station Post Office Box 88, Mail Code 800 Jenkinsville, SC 29065 Vogtle Electric Generating Plant Southern Nuclear Operating Co., Inc.

Docket Nos. 50-424 and 50-425 License Nos. NPF-68 and NPF-81 Mr. C. R. Pierce Regulatory Affairs Director Southern Nuclear Operating Co., Inc.

P.O. Box 1295/Bin 038 Birmingham, AL 35201-1295 Waterford Steam Electric Station Entergy Operations, Inc.

Docket No. 50-382 License No. NPF-38 Vice President, Operations Entergy Operations, Inc.

Waterford Steam Electric Station, Unit 3 17265 River Road Killona, LA 70057-0751 Watts Bar Nuclear Plant Tennessee Valley Authority Docket Nos. 50-390 and 50-391 License No. NPF-90 Mr. Joseph W. Shea Vice President, Nuclear Licensing Tennessee Valley Authority 1101 Market Street, LP 3D-C Chattanooga, TN 37 402-2801 Wolf Creek Generating Station Wolf Creek Nuclear Operating Corp.

Docket No. 50-482 License No. NPF-42 Mr. Adam C. Heflin President, Chief Executive Officer, and Chief Nuclear Officer Wolf Creek Nuclear Operating Corporation P.O. Box 411 Burlington, KS 66839

ML14248A308 OFFICE NRR/JLD/JOMB/PM NRR/JLD/LA NRR/JLD/JOMB/BC(A)

NAME SMonarque (JBoska for)

Slent MHalter DATE 09/09/14 09/08/14 09/09/14 OFFICE NRR/JLD/JHMB/BC NRR/JLD/0 NAME SWhaley JDavis DATE 09/09/14 09/10/14

Letter to All Power Reactor Licensees from Jack Davis dated September 10, 2014

SUBJECT:

ASSIGNMENT OF PROJECT MANAGERS WITHIN THE U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR REACTOR REGULATION JAPAN-LESSONS LEARNED DIVISION DISTRIBUTION:

PUBLIC LPL 1-1 R/F LPL 1-2 R/F LPL2-1 R/F LPL2-2 R/F LPL3-1 R/F LPL3-2 R/F LPL4-1 R/F LPL4-2 R/F LP _WB R/F RidsNrrDorl RidsNrrDoriLpl1-1 RidsNrrDoriLpl1-2 RidsNrrDoriLpl2-1 RidsNrrDoriLpl2-2 RidsNrrDoriLpl3-1 RidsNrrDoriLpl3-2 RidsNrrDoriLpl4-1 Rids N rrDorl Lpl4-2 RidsNrrDolrLp_WB RidsOgcMaiiCenter RidsNrrLAABaxter RidsNrrLAJBurkhardt RidsNrrLABCiayton RidsNrrLASFigueroa RidsNrrLAKGoldstein RidsNrrLASRohrer RidsNrrLAMHenderson RidsNrrLASLent RidsNrrPMANO RidsNrrPMBeaverValley RidsNrrPMBraidwood RidsNrrPMBrownsFerry BHarris, NRR KWilliams, NSIR MMitchell, NRR RidsNrrPMBrunswick RidsNrrPMByron RidsNrrPMCalaway RidsNrrPMCalvertCiiffs RidsNrrPMCatawba RidsNrrPMCiinton RidsNrrPMColumbia RidsNrrPMCooper RidsNrrPMComanchePeak RidsnNrrPMCrystaiRiver RidsNrrPMDavisBesse RidsNrrPMDCCook RidsNrrPMDiabloCanyon RidsNrrPMDresden RidsNrrDuaneArnold RidsNrrPMFarley RidsNrrPMFermi RidsNrrPMFitzPatrick RidsNrrPMFortCalhoun RidsNrrPMGrandGulf RidsNrrPMHatch RidsNrrPMHopeCreek RidsNrrPMindianPoint RidsNrrPMKewaunee RidsNrrPMLaSalle RidsNrrPMLimerick RidsNrrPMMcGuire RidsNrrPMMillstone RidsNrrMonticello RidsNrrPMNineMilePoint RidsNrrPMNorthAnna RidsNrrPMOconee RidsNrrPMOysterCreek RidsNrrPMPalisades RidsNrrPMPaloVerde RidsNrrPMPeachBottom RidsNrrPMPerry RidsNrrPMPilgrim RidsNrrPMPointBeach RidsNrrPMPrairielsland RidsNrrPMQuadCities RidsNrrPMREGinna RidsNrrPMRiverBend RidsNrrPMRobinson RidsNrrPMSalem RidsNrrPMSanOnofre RidsNrrPMSeabrook RidsNrrPMSequoyah RidsNrrPMShearonHarris RidsNrrPMSouthTexas RidsNrrPMSummer RidsNrrPMSurry RidsNrrPMStLucie RidsNrrPMSusquehanna RidsNrrPMThreeMilelsland RidsNrrPMTurkeyPoint RidsN rrPMVermontYankee RidsNrrPMVogtle RidsNrrPMWaterford RidsNrrPMWattsBar1 RidsNrrPMWattsBar2 RidsNrrPMWolfCreek RidsRgn1 MaiiCenter Resource RidsRgn2MaiiCenter Resource RidsRgn3MaiiCenter Resource RidsRgn4MaiiCenter Resource