ML15204A829: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 17: Line 17:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES
{{#Wiki_filter:UNITED STATES  
                            NUCLEAR REGULATORY COMMISSION
NUCLEAR REGULATORY COMMISSION  
                                              REGION III
REGION III  
                                    2443 WARRENVILLE RD. SUITE 210
2443 WARRENVILLE RD. SUITE 210  
                                          LISLE, IL 60532-4352
LISLE, IL 60532-4352  
                                            July 23, 2015
Mr. Ernest Harkness
July 23, 2015  
Site Vice President
FirstEnergy Nuclear Operating Company
Perry Nuclear Power Plant
P. O. Box 97, 10 Center Road, A-PY-A290
Mr. Ernest Harkness  
Perry, OH 44081-0097
Site Vice President
SUBJECT: PERRY NUCLEAR POWER PLANT - NOTIFICATION OF NRC TRIENNIAL FIRE
FirstEnergy Nuclear Operating Company  
              PROTECTION BASELINE INSPECTION REQUEST FOR INFORMATION
Perry Nuclear Power Plant  
              05000440/2015008
P. O. Box 97, 10 Center Road, A-PY-A290  
Dear Mr. Harkness:
Perry, OH 44081-0097  
On September 21, 2015, the U.S. Nuclear Regulatory Commission (NRC) will begin a triennial
SUBJECT: PERRY NUCLEAR POWER PLANT - NOTIFICATION OF NRC TRIENNIAL FIRE  
fire protection baseline inspection at your Perry Nuclear Power Plant. This inspection will be
PROTECTION BASELINE INSPECTION REQUEST FOR INFORMATION  
performed in accordance with Inspection Procedure (IP) 71111.05T, the NRCs baseline fire
05000440/2015008  
protection inspection procedure.
Dear Mr. Harkness:  
Changes were made to the IP 71111.05T, which now requires the fire protection inspection to
On September 21, 2015, the U.S. Nuclear Regulatory Commission (NRC) will begin a triennial  
review your actions to mitigate postulated events that could potentially cause loss of large areas
fire protection baseline inspection at your Perry Nuclear Power Plant. This inspection will be  
of power reactor facilities due to explosions or fires. This requirement was implemented by the
performed in accordance with Inspection Procedure (IP) 71111.05T, the NRCs baseline fire  
issuance of the Interim Compensatory Measures Order EA-02-026, Section B.5.b and the
protection inspection procedure.  
subsequent requirements of 10 CFR 50.54(hh)(2), which are collectively referred to as B.5.b
Changes were made to the IP 71111.05T, which now requires the fire protection inspection to  
requirements. During this inspection, the B.5.b requirements review will be performed during
review your actions to mitigate postulated events that could potentially cause loss of large areas  
the first onsite week of the inspection starting on September 23, 2015.
of power reactor facilities due to explosions or fires. This requirement was implemented by the  
The schedule for the onsite inspection activity is as follows:
issuance of the Interim Compensatory Measures Order EA-02-026, Section B.5.b and the  
    Information Gathering Visit: September 21 - 23, 2015;
subsequent requirements of 10 CFR 50.54(hh)(2), which are collectively referred to as B.5.b  
    B.5.b Requirements: September 23 - 25, 2015; and
requirements. During this inspection, the B.5.b requirements review will be performed during  
    Fire Protection Inspection: October 5 - 9 and October 19 - 23, 2015.
the first onsite week of the inspection starting on September 23, 2015.  
The purpose of the information gathering visit is: (1) to obtain information and documentation
The schedule for the onsite inspection activity is as follows:  
needed to support the inspection; (2) to become familiar with the Perry Nuclear Power Plant fire
protection programs, fire protection features, post-fire safe shutdown capabilities, and plant
Information Gathering Visit: September 21 - 23, 2015;  
layout; and (3) to arrange administrative details, such as office space, availability of
knowledgeable office personnel and to ensure unescorted site access privileges.
B.5.b Requirements: September 23 - 25, 2015; and  
Fire Protection Inspection: October 5 - 9 and October 19 - 23, 2015.  
The purpose of the information gathering visit is: (1) to obtain information and documentation  
needed to support the inspection; (2) to become familiar with the Perry Nuclear Power Plant fire  
protection programs, fire protection features, post-fire safe shutdown capabilities, and plant  
layout; and (3) to arrange administrative details, such as office space, availability of  
knowledgeable office personnel and to ensure unescorted site access privileges.  


E. Harkness                                     -2-
Experience has shown that the baseline fire protection inspections are extremely resource
intensive both for the NRC inspectors and the licensee staff. In order to minimize the inspection
E. Harkness  
impact on the site and to ensure a productive inspection for both organizations, we have
enclosed a request for documents needed for the inspection. These documents have been
divided into four groups. The first group lists information necessary to aid the inspection team
in choosing specific focus areas for the inspection. It is requested that this information be
provided to the lead inspector via mail or electronically no later than September 11, 2015.
-2-  
The second group also lists information and areas for discussion necessary to aid the inspection
Experience has shown that the baseline fire protection inspections are extremely resource  
team in choosing specific fire protection focus areas for the inspection and to ensure that the
intensive both for the NRC inspectors and the licensee staff. In order to minimize the inspection  
inspection team is adequately prepared for the inspection. It is requested this information be
impact on the site and to ensure a productive inspection for both organizations, we have  
available during the information gathering visit (September 21, 2015). The third group of
enclosed a request for documents needed for the inspection. These documents have been  
requested documents consists of those items that the team will review, or need access to,
divided into four groups. The first group lists information necessary to aid the inspection team  
during the inspection. Please have this information available by the first day of the second
in choosing specific focus areas for the inspection. It is requested that this information be  
onsite inspection week (October 5, 2015). The fourth group lists the information necessary to
provided to the lead inspector via mail or electronically no later than September 11, 2015.
aid the inspection team in tracking issues identified as a result of the inspection. It is requested
The second group also lists information and areas for discussion necessary to aid the inspection  
that this information be provided to the lead inspector as the information is generated during the
team in choosing specific fire protection focus areas for the inspection and to ensure that the  
inspection. It is important that all of these documents are up-to-date and complete in order
inspection team is adequately prepared for the inspection. It is requested this information be  
to minimize the number of additional documents requested during the preparation and/or the
available during the information gathering visit (September 21, 2015). The third group of  
onsite portions of the inspection.
requested documents consists of those items that the team will review, or need access to,  
The lead inspector for this inspection is Mr. Dariusz Szwarc. We understand that our regulatory
during the inspection. Please have this information available by the first day of the second  
contact for this inspection is Mr. David Lockwood of your organization. If there are any
onsite inspection week (October 5, 2015). The fourth group lists the information necessary to  
questions about the inspection or the material requested, please contact the lead inspector at
aid the inspection team in tracking issues identified as a result of the inspection. It is requested  
(630) 829-9803 or via e-mail at dariusz.szwarc@nrc.gov.
that this information be provided to the lead inspector as the information is generated during the  
This letter does not contain new or amended information collection requirements subject
inspection. It is important that all of these documents are up-to-date and complete in order  
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
to minimize the number of additional documents requested during the preparation and/or the  
collection requirements were approved by the Office of Management and Budget, Control
onsite portions of the inspection.  
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required
The lead inspector for this inspection is Mr. Dariusz Szwarc. We understand that our regulatory  
to respond to a request for information or an information collection requirement unless the
contact for this inspection is Mr. David Lockwood of your organization. If there are any  
requesting document displays a currently valid Office of Management and Budget control
questions about the inspection or the material requested, please contact the lead inspector at  
number.
(630) 829-9803 or via e-mail at dariusz.szwarc@nrc.gov.  
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public
This letter does not contain new or amended information collection requirements subject  
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information  
collection requirements were approved by the Office of Management and Budget, Control  
Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required  
to respond to a request for information or an information collection requirement unless the  
requesting document displays a currently valid Office of Management and Budget control  
number.  
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public  
Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy  
of this letter, its enclosure, and your response (if any) will be available electronically for public
of this letter, its enclosure, and your response (if any) will be available electronically for public


E. Harkness                               -3-
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
E. Harkness  
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html
(the Public Electronic Reading Room).
                                          Sincerely,
                                          /RA George Hausman Acting for/
                                          Robert C. Daley, Chief
-3-  
                                          Engineering Branch 3
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)  
                                          Division of Reactor Safety
component of the NRC's Agencywide Documents Access and Management System (ADAMS).
Docket No. 50-440
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html  
License No. NPF-58
(the Public Electronic Reading Room).  
Enclosure: Fire Protection Inspection
   Document Request
Sincerely,  
cc w/encl: Distribution via LISTSERV
/RA George Hausman Acting for/  
Robert C. Daley, Chief  
Engineering Branch 3  
Division of Reactor Safety  
Docket No. 50-440  
License No. NPF-58  
Enclosure: Fire Protection Inspection
   Document Request  
cc w/encl: Distribution via LISTSERV


    NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION
NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION  
                                  REQUEST FOR INFORMATION
REQUEST FOR INFORMATION  
Inspection Report:             05000440/2015008
Enclosure
Onsite Inspection Dates:       September 21 - 23, 2015         (Information Gathering Visit)
Inspection Report:  
                              September 23 - 25, 2015         (B.5.b Requirements)
05000440/2015008  
                              October 5 - 9, 2015             (Fire Protection Inspection)
Onsite Inspection Dates:  
                              October 19 - 23, 2015           (Fire Protection Inspection)
September 21 - 23, 2015  
Inspection Procedures:         IP71111.05T, Fire Protection (Triennial)
(Information Gathering Visit)  
                              IP71152, "Identification and Resolution of Problems"
Inspectors:                   Dariusz Szwarc                         Alan Dahbur
                              Senior Reactor Inspector (Lead)         Senior Reactor Inspector
                              (630) 829-9803                         (630) 829-9810
                              dariusz.szwarc@nrc.gov                 alan.dahbur@nrc.gov
September 23 - 25, 2015  
                              George Hausman                         Robert Winter
(B.5.b Requirements)
                              Senior Reactor Inspector               Reactor Inspector
                              (630) 829-9743                         (630) 829-9758
                              george.hausman@nrc.gov                 robert.winter@nrc.gov
I. Information Requested Prior To the Information Gathering Visit
  The following information is requested by September 11, 2015. If you have any questions
  regarding this request, please call the lead inspector as soon as possible. All information
October 5 - 9, 2015
  should be sent to Mr. Dariusz Szwarc (e-mail address dariusz.szwarc@nrc.gov). Electronic
(Fire Protection Inspection)  
  media is preferred. The preferred file format is a searchable pdf file on a compact
  disk (CD). The CD should be indexed and hyper-linked to facilitate ease of use, if possible.
  Please provide four copies of each CD submitted (one for each inspector).
  1. The most risk significant fire areas as determined by probabilistic risk analyses, if
      available. Otherwise, the reactor plant's Individual Plant Examination for External
October 19 - 23, 2015  
      Events (IPEEE) for fire and results of any post-IPEEE reviews for fire.
(Fire Protection Inspection)  
  2. A copy of the current version of the fire protection program (FPP), fire hazards
Inspection Procedures:  
      analysis (FHA), safe shutdown analysis (SSA), updated safety analysis report (USAR),
IP71111.05T, Fire Protection (Triennial)  
      technical specifications, license (including the fire protection license condition), and
IP71152, "Identification and Resolution of Problems"  
      technical requirements manual (TRM) or equivalent for fire protection structures,
Inspectors:  
      systems, and components.
  3. A list of fire areas requiring alternative shutdown capability, (i.e., those areas for which
Dariusz Szwarc  
      10 CFR Part 50, Appendix R, Section III G requirements are satisfied under
      Section III.G.3), or where both safe shutdown trains can be affected.
                                                                                          Enclosure
Alan Dahbur  
Senior Reactor Inspector (Lead)  
Senior Reactor Inspector  
(630) 829-9803  
(630) 829-9810  
dariusz.szwarc@nrc.gov
alan.dahbur@nrc.gov
George Hausman  
Robert Winter  
Senior Reactor Inspector  
Reactor Inspector  
(630) 829-9743  
(630) 829-9758  
george.hausman@nrc.gov  
robert.winter@nrc.gov
I. Information Requested Prior To the Information Gathering Visit  
The following information is requested by September 11, 2015. If you have any questions  
regarding this request, please call the lead inspector as soon as possible. All information  
should be sent to Mr. Dariusz Szwarc (e-mail address dariusz.szwarc@nrc.gov). Electronic  
media is preferred. The preferred file format is a searchable pdf file on a compact  
disk (CD). The CD should be indexed and hyper-linked to facilitate ease of use, if possible.
Please provide four copies of each CD submitted (one for each inspector).  
1. The most risk significant fire areas as determined by probabilistic risk analyses, if  
available. Otherwise, the reactor plant's Individual Plant Examination for External  
Events (IPEEE) for fire and results of any post-IPEEE reviews for fire.  
2. A copy of the current version of the fire protection program (FPP), fire hazards  
analysis (FHA), safe shutdown analysis (SSA), updated safety analysis report (USAR),  
technical specifications, license (including the fire protection license condition), and  
technical requirements manual (TRM) or equivalent for fire protection structures,  
systems, and components.  
3. A list of fire areas requiring alternative shutdown capability, (i.e., those areas for which  
10 CFR Part 50, Appendix R, Section III G requirements are satisfied under  
Section III.G.3), or where both safe shutdown trains can be affected.


      NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION
NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION  
                                  REQUEST FOR INFORMATION
REQUEST FOR INFORMATION  
    4. Plant operating procedures which would be used and describe shutdown for a
2
        postulated fire (for both areas requiring alternative shutdown and areas which do not
4. Plant operating procedures which would be used and describe shutdown for a  
        require alternative shutdown). Only those procedures with actions specific to shutdown
postulated fire (for both areas requiring alternative shutdown and areas which do not  
        in the event of a fire need be included. In addition, please include those procedures
require alternative shutdown). Only those procedures with actions specific to shutdown  
        which operators would use for initial response to a fire, such as annunciator or alarm
in the event of a fire need be included. In addition, please include those procedures  
        response procedures, the procedure used for activating the fire brigade, and the
which operators would use for initial response to a fire, such as annunciator or alarm  
        procedure which directs operators to the applicable safe shutdown procedure.
response procedures, the procedure used for activating the fire brigade, and the  
    5. Analysis performed in support of plant evaluation regarding multiple spurious operation
procedure which directs operators to the applicable safe shutdown procedure.  
        (MSO), which includes the following:
5. Analysis performed in support of plant evaluation regarding multiple spurious operation  
        a. List of identified multiple spurious fire-induced circuit failure configurations;
(MSO), which includes the following:  
        b. List of the generic and plant specific MSOs;
a. List of identified multiple spurious fire-induced circuit failure configurations;  
        c. Results of expert panel process and associated review/evaluation of the generic and
b. List of the generic and plant specific MSOs;  
            plant-specific MSOs and existing safe shutdown analysis; and
c. Results of expert panel process and associated review/evaluation of the generic and  
        d. Evaluations and corrective actions taken for resolution of MSO issues.
plant-specific MSOs and existing safe shutdown analysis; and  
II. Information Requested During the Information Gathering Visit (SEPTEMBER 21, 2015)
d. Evaluations and corrective actions taken for resolution of MSO issues.  
    The following information is requested to be provided to the inspection team during the
II. Information Requested During the Information Gathering Visit (SEPTEMBER 21, 2015)  
    onsite information gathering visit. Except for Item 8, it is requested that the following
The following information is requested to be provided to the inspection team during the  
    information be provided on four sets of CDs (searchable, if possible) with the B.5.b
onsite information gathering visit. Except for Item 8, it is requested that the following  
    Mitigating Strategies information (Items 8.a through 8.h) provided on one separate CD.
information be provided on four sets of CDs (searchable, if possible) with the B.5.b  
    In addition, one set of hard copy drawings are requested for Items 4.a. through 4.d.
Mitigating Strategies information (Items 8.a through 8.h) provided on one separate CD.
    1. One set of hard-copy documents for facility layout drawings which identify plant fire area
In addition, one set of hard copy drawings are requested for Items 4.a. through 4.d.  
        delineation; areas protected by automatic fire suppression and detection; and locations
1. One set of hard-copy documents for facility layout drawings which identify plant fire area  
        of fire protection equipment.
delineation; areas protected by automatic fire suppression and detection; and locations  
    2. Licensing Information:
of fire protection equipment.  
        a.     All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs)
2. Licensing Information:  
              applicable to fire protection (specifically including those SERs referenced by
a.  
              the plant fire protection license condition) and all licensing correspondence
All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs)  
              referenced by the SERs;
applicable to fire protection (specifically including those SERs referenced by  
        b.     All licensing correspondence associated with the comparison to Standard Review
the plant fire protection license condition) and all licensing correspondence  
              Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing purposes;
referenced by the SERs;  
        c.     Exemptions from 10 CFR 50.48 and 10 CFR Part 50, Appendix R, and associated
b.  
              licensing correspondence;
All licensing correspondence associated with the comparison to Standard Review  
                                                    2
Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing purposes;  
c.  
Exemptions from 10 CFR 50.48 and 10 CFR Part 50, Appendix R, and associated  
licensing correspondence;  


NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION
NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION  
                              REQUEST FOR INFORMATION
REQUEST FOR INFORMATION  
  d.     For pre-1979 plants, all licensing correspondence associated with those
3
          sections of 10 CFR Part 50, Appendix R, that are not applicable to the plant under
d.  
          10 CFR 50.48(b)(1). Specifically, the licensing correspondence associated with
For pre-1979 plants, all licensing correspondence associated with those  
          those fire protection features proposed or implemented by the licensee that have
sections of 10 CFR Part 50, Appendix R, that are not applicable to the plant under  
          been accepted by the NRC staff as satisfying the provisions of Appendix A to
10 CFR 50.48(b)(1). Specifically, the licensing correspondence associated with  
          Branch Technical Position (BTP) APCSB 9.5-1 reflected in the NRC fire protection
those fire protection features proposed or implemented by the licensee that have  
          SERs issued before February 19, 1981, (10 CFR 50.48(b)(1)(i)); or those fire
been accepted by the NRC staff as satisfying the provisions of Appendix A to  
          protection features, which were accepted by the NRC staff in comprehensive fire
Branch Technical Position (BTP) APCSB 9.5-1 reflected in the NRC fire protection  
          protection SERs issued before Appendix A to BTP APCSB 9.5-1 was published in
SERs issued before February 19, 1981, (10 CFR 50.48(b)(1)(i)); or those fire  
          August 1976 (10 CFR 50.48(b)(1)(ii)); and
protection features, which were accepted by the NRC staff in comprehensive fire  
  e.     The final safety analysis report (FSAR) sections applicable to fire protection, FHA,
protection SERs issued before Appendix A to BTP APCSB 9.5-1 was published in  
          and SSA in effect at the time of original licensing.
August 1976 (10 CFR 50.48(b)(1)(ii)); and  
3. Fire Protection Program:
e.  
  a.     A listing of changes made to the FPP since the last triennial fire protection
The final safety analysis report (FSAR) sections applicable to fire protection, FHA,  
          inspection;
and SSA in effect at the time of original licensing.  
  b.     For pre-1979 plants, a listing of the protection methodologies identified under
3. Fire Protection Program:  
          10 CFR Part 50, Appendix R, Section III.G used to achieve compliance for
a.  
          selected fire zones/areas (to be determined during information gathering visit).
A listing of changes made to the FPP since the last triennial fire protection  
          That is, please specify whether 3-hour rated fire barriers; (Section III.G.2.a), 20
inspection;  
          foot separation along with detection and suppression; (Section III.G.2.b), 1-hour
b.  
          rated fire barriers with detection and suppression; (Section III.G.2.c), or alternative
For pre-1979 plants, a listing of the protection methodologies identified under  
          shutdown capability; (Section III.G.3) is used as a strategy for each selected fire
10 CFR Part 50, Appendix R, Section III.G used to achieve compliance for  
          zone/area;
selected fire zones/areas (to be determined during information gathering visit).
  c.     A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe-shutdown
That is, please specify whether 3-hour rated fire barriers; (Section III.G.2.a), 20  
          evaluations);
foot separation along with detection and suppression; (Section III.G.2.b), 1-hour  
  d.     A list of applicable codes and standards related to the design of plant fire
rated fire barriers with detection and suppression; (Section III.G.2.c), or alternative  
          protection features. The list should include National Fire Protection Association
shutdown capability; (Section III.G.3) is used as a strategy for each selected fire  
          (NFPA) code versions committed to (i.e., the NFPA Codes of Record); and
zone/area;  
  e.     List of plant deviations from code commitments and associated evaluations.
c.  
4. Facility Information:
A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe-shutdown  
  a.     Piping and instrumentation (flow) diagrams showing the components used to
evaluations);  
          achieve and maintain hot standby and cold shutdown for fires outside the control
d.  
          room, those components used for those areas requiring alternative shutdown
A list of applicable codes and standards related to the design of plant fire  
          capability, and systems relied upon for B.5.b mitigation strategies. These can be
protection features. The list should include National Fire Protection Association  
          of the type that are used for training;
(NFPA) code versions committed to (i.e., the NFPA Codes of Record); and  
                                              3
e.  
List of plant deviations from code commitments and associated evaluations.  
4. Facility Information:  
a.  
Piping and instrumentation (flow) diagrams showing the components used to  
achieve and maintain hot standby and cold shutdown for fires outside the control  
room, those components used for those areas requiring alternative shutdown  
capability, and systems relied upon for B.5.b mitigation strategies. These can be  
of the type that are used for training;  


  NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION
NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION  
                              REQUEST FOR INFORMATION
REQUEST FOR INFORMATION  
    b.   One-line schematic drawings of the electrical distribution system for 4160 Volts
4
        alternating current (Vac) down to 480Vac;
b.  
    c.   One-line schematic drawings of the electrical distribution system for 250 Volts
One-line schematic drawings of the electrical distribution system for 4160 Volts  
        direct current (Vdc) and 125Vdc systems as applicable;
alternating current (Vac) down to 480Vac;  
    d.   Logic diagrams showing the components used to achieve and maintain hot
c.  
        standby and cold shutdown; and
One-line schematic drawings of the electrical distribution system for 250 Volts  
    e.   Safe shutdown cable routing database (requested electronically, such as on
direct current (Vdc) and 125Vdc systems as applicable;  
        compact disc, if available).
d.  
5. Operations Response for Fire Protection:
Logic diagrams showing the components used to achieve and maintain hot  
    a.   Pre-fire plans for selected fire zones/areas (to be determined during information
standby and cold shutdown; and  
        gathering visit);
e.  
    b.   Plant operating procedures which specify the initial operations response to a fire
Safe shutdown cable routing database (requested electronically, such as on  
        alarm or annunciator; and
compact disc, if available).  
    c.   Procedure for calling out the fire brigade and requesting off-site assistance.
5.  
6. Corrective Actions:
Operations Response for Fire Protection:  
    a.   Listing of open and closed fire protection condition reports (i.e., problem
a.  
        identification forms and their resolution reports) since the date of the last triennial
Pre-fire plans for selected fire zones/areas (to be determined during information  
        fire protection inspection; and
gathering visit);  
    b.   List of current fire impairments, including duration.
b.  
7. General Information:
Plant operating procedures which specify the initial operations response to a fire  
    a.   A listing of abbreviations and/or designators for plant systems;
alarm or annunciator; and  
    b.   Organization charts of site personnel down to the level of fire protection staff
c.  
        personnel; and
Procedure for calling out the fire brigade and requesting off-site assistance.  
    c.   A phone list for onsite licensee personnel.
6. Corrective Actions:  
8. B.5.b Mitigating Strategies:
a.  
    a.   A list of all modifications to regulatory commitments made to meet the
Listing of open and closed fire protection condition reports (i.e., problem  
        requirements of Section B.5.b of the ICM Order, EA-02-026, dated
identification forms and their resolution reports) since the date of the last triennial  
          February 25, 2002, the subsequently imposed license conditions, and
fire protection inspection; and
          10 CFR 50.54(hh)(2);
b.  
                                              4
List of current fire impairments, including duration.  
7. General Information:  
a.  
A listing of abbreviations and/or designators for plant systems;
b.  
Organization charts of site personnel down to the level of fire protection staff  
personnel; and
c.  
A phone list for onsite licensee personnel.  
8. B.5.b Mitigating Strategies:  
a.  
A list of all modifications to regulatory commitments made to meet the  
requirements of Section B.5.b of the ICM Order, EA-02-026, dated  
February 25, 2002, the subsequently imposed license conditions, and  
10 CFR 50.54(hh)(2);  


NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION
NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION  
                              REQUEST FOR INFORMATION
REQUEST FOR INFORMATION  
  b.   Copies of procedures/guidelines that were revised or generated to implement the
5
        mitigation strategies. These could be extensive damage mitigation guidelines
b.  
        (EDMGs), severe accident management guidelines (SAMGs), emergency
Copies of procedures/guidelines that were revised or generated to implement the  
        operating procedures (EOPs), abnormal operating procedures (AOPs), etc.;
mitigation strategies. These could be extensive damage mitigation guidelines  
  c.   A matrix that shows the correlation between the mitigation strategies identified in
(EDMGs), severe accident management guidelines (SAMGs), emergency  
        Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that
operating procedures (EOPs), abnormal operating procedures (AOPs), etc.;  
        are used to implement each strategy;
c.  
  d.   A listing of engineering evaluations/calculations that were used to verify
A matrix that shows the correlation between the mitigation strategies identified in  
        engineering bases for the mitigation strategies;
Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that  
  e.   Copies of procedures used to inventory equipment (hoses, fittings, pumps, etc.)
are used to implement each strategy;
        required to be used to implement the mitigation strategies;
d.  
  f.   A list of B.5.b mitigating strategies, if any, which have implementing details that
A listing of engineering evaluations/calculations that were used to verify  
        differ from that documented in the submittals and the safety evaluation report;
engineering bases for the mitigation strategies;  
  g.   Copies of Memoranda of Understanding (MOUs) (e.g., with local fire departments)
e.  
        required to implement any mitigating strategies; and
Copies of procedures used to inventory equipment (hoses, fittings, pumps, etc.)  
  h.   A list of changes made to B.5.b mitigating strategies and associated procedures
required to be used to implement the mitigation strategies;  
        since the previous NRC inspection of B.5.b mitigating strategies (March 13, 2012).
f.  
9. Onsite Discussions:
A list of B.5.b mitigating strategies, if any, which have implementing details that  
  In addition, during the information gathering visit, it is requested that licensee staff be
differ from that documented in the submittals and the safety evaluation report;  
  available for the following:
g.  
  a.   Informal discussion on plant procedures operators would use in the event of fire or
Copies of Memoranda of Understanding (MOUs) (e.g., with local fire departments)  
        explosion (including B.5.b mitigation strategies) and under what conditions would
required to implement any mitigating strategies; and  
        the plant be shutdown using alternative shutdown methodology;
h.  
  b.   Informal discussion on the plants safe shutdown cable routing database and the
A list of changes made to B.5.b mitigating strategies and associated procedures  
        plant-wide cable routing database, as applicable;
since the previous NRC inspection of B.5.b mitigating strategies (March 13, 2012).  
  c.   A tour of alternative shutdown and risk significant fire areas; and
9. Onsite Discussions:  
  d.   A discussion of scheduling of fire drills which may occur during the inspection so
In addition, during the information gathering visit, it is requested that licensee staff be  
        that the inspectors may be able to observe a fire drill, if possible.
available for the following:  
                                              5
a.  
Informal discussion on plant procedures operators would use in the event of fire or  
explosion (including B.5.b mitigation strategies) and under what conditions would  
the plant be shutdown using alternative shutdown methodology;  
b.  
Informal discussion on the plants safe shutdown cable routing database and the  
plant-wide cable routing database, as applicable;  
c.  
A tour of alternative shutdown and risk significant fire areas; and  
d.  
A discussion of scheduling of fire drills which may occur during the inspection so  
that the inspectors may be able to observe a fire drill, if possible.  


      NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION
NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION  
                                    REQUEST FOR INFORMATION
REQUEST FOR INFORMATION  
III. Information Requested to be Available on First Day of the Second ONSITE Inspection
6
    Week (OCTOBER 5, 2015)
III. Information Requested to be Available on First Day of the Second ONSITE Inspection  
    The following information is requested to be provided on the first day of inspection. It is
Week (OCTOBER 5, 2015)  
    requested that this information be provided on four sets of CDs (searchable, if possible).
The following information is requested to be provided on the first day of inspection. It is  
    1. Program Procedures:
requested that this information be provided on four sets of CDs (searchable, if possible).  
        a.     Procedures for:
1. Program Procedures:  
                      i. Administrative controls (such as allowed out of service times and
a.  
                        compensatory measures) for fire protection systems and components;
Procedures for:  
                    ii. Control of transient combustibles; and
i. Administrative controls (such as allowed out of service times and  
                    iii. Control of hot work.
compensatory measures) for fire protection systems and components;  
        b.     List of maintenance and surveillance testing procedures for alternative shutdown
ii. Control of transient combustibles; and  
                capability and fire barriers, detectors, pumps, and suppression systems; and
iii. Control of hot work.  
        c.     List of maintenance procedures which routinely verify fuse breaker coordination
b.  
                in accordance with the post-fire safe shutdown coordination analysis.
List of maintenance and surveillance testing procedures for alternative shutdown  
    2. Design and Equipment Information:
capability and fire barriers, detectors, pumps, and suppression systems; and  
        a.     Coordination calculations and/or justifications that verify fuse/breaker
c.  
                coordination for selected fire zones/areas (to be determined during
List of maintenance procedures which routinely verify fuse breaker coordination  
                information gathering visit) that are fed off of the same electrical buses as
in accordance with the post-fire safe shutdown coordination analysis.  
                components in the protected safe shutdown train;
2. Design and Equipment Information:  
        b.     Copies of significant fire protection and post-fire safe shutdown related design
a.  
                change package descriptions (including their associated 10 CFR 50.59
Coordination calculations and/or justifications that verify fuse/breaker  
                evaluations) and Generic Letter (GL) 86-10 (or adverse to safe shutdown)
coordination for selected fire zones/areas (to be determined during  
                evaluations;
information gathering visit) that are fed off of the same electrical buses as  
        c.     Gaseous suppression system pre-operational testing, if applicable, for selected
components in the protected safe shutdown train;  
                fire zones/areas (to be determined during information gathering visit);
b.  
        d.     Hydraulic calculations and supporting test data which demonstrate operability for
Copies of significant fire protection and post-fire safe shutdown related design  
                water suppression systems, if applicable, for selected fire zones/areas (to be
change package descriptions (including their associated 10 CFR 50.59  
                determined during information gathering visit);
evaluations) and Generic Letter (GL) 86-10 (or adverse to safe shutdown)  
        e.     Alternating current (ac) coordination calculations for 4160Vac down to 480Vac
evaluations;  
                electrical systems; and
c.  
        f.     List of all fire protection or Appendix R calculations.
Gaseous suppression system pre-operational testing, if applicable, for selected  
                                                    6
fire zones/areas (to be determined during information gathering visit);  
d.  
Hydraulic calculations and supporting test data which demonstrate operability for  
water suppression systems, if applicable, for selected fire zones/areas (to be  
determined during information gathering visit);  
e.  
Alternating current (ac) coordination calculations for 4160Vac down to 480Vac  
electrical systems; and  
f.  
List of all fire protection or Appendix R calculations.  


      NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION
NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION  
                                  REQUEST FOR INFORMATION
REQUEST FOR INFORMATION  
    3. Assessment and Corrective Actions:
7
                The three most recent fire protection Quality Assurance (QA) audits and/or fire
3. Assessment and Corrective Actions:  
                protection self-assessments.
The three most recent fire protection Quality Assurance (QA) audits and/or fire  
    4. Any updates to information previously provided.
protection self-assessments.  
IV.     Information Requested to Be Provided Throughout the Inspection
4. Any updates to information previously provided.  
    1. Copies of any corrective action documents generated as a result of the inspection
IV.  
        teams questions or queries during this inspection.
Information Requested to Be Provided Throughout the Inspection  
    2. Copies of the list of questions submitted by the inspection team members and the
1. Copies of any corrective action documents generated as a result of the inspection  
        status/resolution of the information requested (provided daily during the inspection to
teams questions or queries during this inspection.  
        each inspection team member).
2. Copies of the list of questions submitted by the inspection team members and the  
status/resolution of the information requested (provided daily during the inspection to  
each inspection team member).  
If you have questions regarding the information requested, please contact the lead inspector.
If you have questions regarding the information requested, please contact the lead inspector.
                                                7


E. Harkness                                                               -3-
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)
component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS
E. Harkness  
is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic
Reading Room).
                                                                          Sincerely,
                                                                          /RA George Hausman Acting for/
                                                                          Robert C. Daley, Chief
-3-  
                                                                          Engineering Branch 3
inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)  
                                                                          Division of Reactor Safety
component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS  
Docket No. 50-440
is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic  
License No. NPF-58
Reading Room).  
Enclosure: Fire Protection Inspection
   Document Request
Sincerely,  
cc w/encl: Distribution via LISTSERV
DISTRIBUTION w/encl:
/RA George Hausman Acting for/  
Kimyata MorganButler
RidsNrrPMPerry Resource
RidsNrrDorlLpl3-2 Resource
Robert C. Daley, Chief  
RidsNrrDirsIrib Resource
Engineering Branch 3  
Cynthia Pederson
Division of Reactor Safety  
Darrell Roberts
Richard Skokowski
Docket No. 50-440  
Allan Barker
License No. NPF-58  
Carole Ariano
Enclosure: Fire Protection Inspection
Linda Linn
   Document Request  
DRPIII
cc w/encl: Distribution via LISTSERV  
DRSIII
DISTRIBUTION w/encl:  
Jim Clay
Kimyata MorganButler  
Carmen Olteanu
RidsNrrPMPerry Resource  
ROPreports.Resource@nrc.gov
RidsNrrDorlLpl3-2 Resource
ADAMS Accession Number ML15204A829
RidsNrrDirsIrib Resource  
    Publicly Available                           Non-Publicly Available                   Sensitive               Non-Sensitive
Cynthia Pederson  
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy
Darrell Roberts  
OFFICE             RIII                                 RIII                           RIII                               RIII
Richard Skokowski  
  NAME               DSzwarc:jw                           GHausman for
Allan Barker  
                                                          RDaley
Carole Ariano  
  DATE               07/23/15                             07/23/15
Linda Linn  
                                                            OFFICIAL RECORD COPY
DRPIII  
DRSIII  
Jim Clay  
Carmen Olteanu  
ROPreports.Resource@nrc.gov  
ADAMS Accession Number ML15204A829  
Publicly Available  
Non-Publicly Available  
Sensitive  
Non-Sensitive  
To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy  
OFFICE  
RIII  
RIII  
RIII  
RIII  
   
NAME  
DSzwarc:jw  
GHausman for  
RDaley  
   
DATE  
07/23/15  
07/23/15  
OFFICIAL RECORD COPY
}}
}}

Latest revision as of 10:20, 10 January 2025

IR 05000440/2015008, 09/21/15, Perry Nuclear Power Plant - Notification of NRC Triennial Fire Protection Baseline
ML15204A829
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 07/23/2015
From: Robert Daley
Engineering Branch 3
To: Harkness E
FirstEnergy Nuclear Operating Co
References
IR 2015008
Download: ML15204A829 (11)


See also: IR 05000440/2015008

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

July 23, 2015

Mr. Ernest Harkness

Site Vice President

FirstEnergy Nuclear Operating Company

Perry Nuclear Power Plant

P. O. Box 97, 10 Center Road, A-PY-A290

Perry, OH 44081-0097

SUBJECT: PERRY NUCLEAR POWER PLANT - NOTIFICATION OF NRC TRIENNIAL FIRE

PROTECTION BASELINE INSPECTION REQUEST FOR INFORMATION

05000440/2015008

Dear Mr. Harkness:

On September 21, 2015, the U.S. Nuclear Regulatory Commission (NRC) will begin a triennial

fire protection baseline inspection at your Perry Nuclear Power Plant. This inspection will be

performed in accordance with Inspection Procedure (IP) 71111.05T, the NRCs baseline fire

protection inspection procedure.

Changes were made to the IP 71111.05T, which now requires the fire protection inspection to

review your actions to mitigate postulated events that could potentially cause loss of large areas

of power reactor facilities due to explosions or fires. This requirement was implemented by the

issuance of the Interim Compensatory Measures Order EA-02-026, Section B.5.b and the

subsequent requirements of 10 CFR 50.54(hh)(2), which are collectively referred to as B.5.b

requirements. During this inspection, the B.5.b requirements review will be performed during

the first onsite week of the inspection starting on September 23, 2015.

The schedule for the onsite inspection activity is as follows:

Information Gathering Visit: September 21 - 23, 2015;

B.5.b Requirements: September 23 - 25, 2015; and

Fire Protection Inspection: October 5 - 9 and October 19 - 23, 2015.

The purpose of the information gathering visit is: (1) to obtain information and documentation

needed to support the inspection; (2) to become familiar with the Perry Nuclear Power Plant fire

protection programs, fire protection features, post-fire safe shutdown capabilities, and plant

layout; and (3) to arrange administrative details, such as office space, availability of

knowledgeable office personnel and to ensure unescorted site access privileges.

E. Harkness

-2-

Experience has shown that the baseline fire protection inspections are extremely resource

intensive both for the NRC inspectors and the licensee staff. In order to minimize the inspection

impact on the site and to ensure a productive inspection for both organizations, we have

enclosed a request for documents needed for the inspection. These documents have been

divided into four groups. The first group lists information necessary to aid the inspection team

in choosing specific focus areas for the inspection. It is requested that this information be

provided to the lead inspector via mail or electronically no later than September 11, 2015.

The second group also lists information and areas for discussion necessary to aid the inspection

team in choosing specific fire protection focus areas for the inspection and to ensure that the

inspection team is adequately prepared for the inspection. It is requested this information be

available during the information gathering visit (September 21, 2015). The third group of

requested documents consists of those items that the team will review, or need access to,

during the inspection. Please have this information available by the first day of the second

onsite inspection week (October 5, 2015). The fourth group lists the information necessary to

aid the inspection team in tracking issues identified as a result of the inspection. It is requested

that this information be provided to the lead inspector as the information is generated during the

inspection. It is important that all of these documents are up-to-date and complete in order

to minimize the number of additional documents requested during the preparation and/or the

onsite portions of the inspection.

The lead inspector for this inspection is Mr. Dariusz Szwarc. We understand that our regulatory

contact for this inspection is Mr. David Lockwood of your organization. If there are any

questions about the inspection or the material requested, please contact the lead inspector at

(630) 829-9803 or via e-mail at dariusz.szwarc@nrc.gov.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required

to respond to a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter, its enclosure, and your response (if any) will be available electronically for public

E. Harkness

-3-

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html

(the Public Electronic Reading Room).

Sincerely,

/RA George Hausman Acting for/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket No. 50-440

License No. NPF-58

Enclosure: Fire Protection Inspection

Document Request

cc w/encl: Distribution via LISTSERV

NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

REQUEST FOR INFORMATION

Enclosure

Inspection Report: 05000440/2015008

Onsite Inspection Dates:

September 21 - 23, 2015

(Information Gathering Visit)

September 23 - 25, 2015

(B.5.b Requirements)

October 5 - 9, 2015

(Fire Protection Inspection)

October 19 - 23, 2015

(Fire Protection Inspection)

Inspection Procedures:

IP71111.05T, Fire Protection (Triennial)

IP71152, "Identification and Resolution of Problems"

Inspectors:

Dariusz Szwarc

Alan Dahbur

Senior Reactor Inspector (Lead)

Senior Reactor Inspector

(630) 829-9803

(630) 829-9810

dariusz.szwarc@nrc.gov

alan.dahbur@nrc.gov

George Hausman

Robert Winter

Senior Reactor Inspector

Reactor Inspector

(630) 829-9743

(630) 829-9758

george.hausman@nrc.gov

robert.winter@nrc.gov

I. Information Requested Prior To the Information Gathering Visit

The following information is requested by September 11, 2015. If you have any questions

regarding this request, please call the lead inspector as soon as possible. All information

should be sent to Mr. Dariusz Szwarc (e-mail address dariusz.szwarc@nrc.gov). Electronic

media is preferred. The preferred file format is a searchable pdf file on a compact

disk (CD). The CD should be indexed and hyper-linked to facilitate ease of use, if possible.

Please provide four copies of each CD submitted (one for each inspector).

1. The most risk significant fire areas as determined by probabilistic risk analyses, if

available. Otherwise, the reactor plant's Individual Plant Examination for External

Events (IPEEE) for fire and results of any post-IPEEE reviews for fire.

2. A copy of the current version of the fire protection program (FPP), fire hazards

analysis (FHA), safe shutdown analysis (SSA), updated safety analysis report (USAR),

technical specifications, license (including the fire protection license condition), and

technical requirements manual (TRM) or equivalent for fire protection structures,

systems, and components.

3. A list of fire areas requiring alternative shutdown capability, (i.e., those areas for which

10 CFR Part 50, Appendix R, Section III G requirements are satisfied under

Section III.G.3), or where both safe shutdown trains can be affected.

NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

REQUEST FOR INFORMATION

2

4. Plant operating procedures which would be used and describe shutdown for a

postulated fire (for both areas requiring alternative shutdown and areas which do not

require alternative shutdown). Only those procedures with actions specific to shutdown

in the event of a fire need be included. In addition, please include those procedures

which operators would use for initial response to a fire, such as annunciator or alarm

response procedures, the procedure used for activating the fire brigade, and the

procedure which directs operators to the applicable safe shutdown procedure.

5. Analysis performed in support of plant evaluation regarding multiple spurious operation

(MSO), which includes the following:

a. List of identified multiple spurious fire-induced circuit failure configurations;

b. List of the generic and plant specific MSOs;

c. Results of expert panel process and associated review/evaluation of the generic and

plant-specific MSOs and existing safe shutdown analysis; and

d. Evaluations and corrective actions taken for resolution of MSO issues.

II. Information Requested During the Information Gathering Visit (SEPTEMBER 21, 2015)

The following information is requested to be provided to the inspection team during the

onsite information gathering visit. Except for Item 8, it is requested that the following

information be provided on four sets of CDs (searchable, if possible) with the B.5.b

Mitigating Strategies information (Items 8.a through 8.h) provided on one separate CD.

In addition, one set of hard copy drawings are requested for Items 4.a. through 4.d.

1. One set of hard-copy documents for facility layout drawings which identify plant fire area

delineation; areas protected by automatic fire suppression and detection; and locations

of fire protection equipment.

2. Licensing Information:

a.

All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs)

applicable to fire protection (specifically including those SERs referenced by

the plant fire protection license condition) and all licensing correspondence

referenced by the SERs;

b.

All licensing correspondence associated with the comparison to Standard Review

Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing purposes;

c.

Exemptions from 10 CFR 50.48 and 10 CFR Part 50, Appendix R, and associated

licensing correspondence;

NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

REQUEST FOR INFORMATION

3

d.

For pre-1979 plants, all licensing correspondence associated with those

sections of 10 CFR Part 50, Appendix R, that are not applicable to the plant under

10 CFR 50.48(b)(1). Specifically, the licensing correspondence associated with

those fire protection features proposed or implemented by the licensee that have

been accepted by the NRC staff as satisfying the provisions of Appendix A to

Branch Technical Position (BTP) APCSB 9.5-1 reflected in the NRC fire protection

SERs issued before February 19, 1981, (10 CFR 50.48(b)(1)(i)); or those fire

protection features, which were accepted by the NRC staff in comprehensive fire

protection SERs issued before Appendix A to BTP APCSB 9.5-1 was published in

August 1976 (10 CFR 50.48(b)(1)(ii)); and

e.

The final safety analysis report (FSAR) sections applicable to fire protection, FHA,

and SSA in effect at the time of original licensing.

3. Fire Protection Program:

a.

A listing of changes made to the FPP since the last triennial fire protection

inspection;

b.

For pre-1979 plants, a listing of the protection methodologies identified under

10 CFR Part 50, Appendix R, Section III.G used to achieve compliance for

selected fire zones/areas (to be determined during information gathering visit).

That is, please specify whether 3-hour rated fire barriers; (Section III.G.2.a), 20

foot separation along with detection and suppression; (Section III.G.2.b), 1-hour

rated fire barriers with detection and suppression; (Section III.G.2.c), or alternative

shutdown capability; (Section III.G.3) is used as a strategy for each selected fire

zone/area;

c.

A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe-shutdown

evaluations);

d.

A list of applicable codes and standards related to the design of plant fire

protection features. The list should include National Fire Protection Association

(NFPA) code versions committed to (i.e., the NFPA Codes of Record); and

e.

List of plant deviations from code commitments and associated evaluations.

4. Facility Information:

a.

Piping and instrumentation (flow) diagrams showing the components used to

achieve and maintain hot standby and cold shutdown for fires outside the control

room, those components used for those areas requiring alternative shutdown

capability, and systems relied upon for B.5.b mitigation strategies. These can be

of the type that are used for training;

NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

REQUEST FOR INFORMATION

4

b.

One-line schematic drawings of the electrical distribution system for 4160 Volts

alternating current (Vac) down to 480Vac;

c.

One-line schematic drawings of the electrical distribution system for 250 Volts

direct current (Vdc) and 125Vdc systems as applicable;

d.

Logic diagrams showing the components used to achieve and maintain hot

standby and cold shutdown; and

e.

Safe shutdown cable routing database (requested electronically, such as on

compact disc, if available).

5.

Operations Response for Fire Protection:

a.

Pre-fire plans for selected fire zones/areas (to be determined during information

gathering visit);

b.

Plant operating procedures which specify the initial operations response to a fire

alarm or annunciator; and

c.

Procedure for calling out the fire brigade and requesting off-site assistance.

6. Corrective Actions:

a.

Listing of open and closed fire protection condition reports (i.e., problem

identification forms and their resolution reports) since the date of the last triennial

fire protection inspection; and

b.

List of current fire impairments, including duration.

7. General Information:

a.

A listing of abbreviations and/or designators for plant systems;

b.

Organization charts of site personnel down to the level of fire protection staff

personnel; and

c.

A phone list for onsite licensee personnel.

8. B.5.b Mitigating Strategies:

a.

A list of all modifications to regulatory commitments made to meet the

requirements of Section B.5.b of the ICM Order, EA-02-026, dated

February 25, 2002, the subsequently imposed license conditions, and

10 CFR 50.54(hh)(2);

NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

REQUEST FOR INFORMATION

5

b.

Copies of procedures/guidelines that were revised or generated to implement the

mitigation strategies. These could be extensive damage mitigation guidelines

(EDMGs), severe accident management guidelines (SAMGs), emergency

operating procedures (EOPs), abnormal operating procedures (AOPs), etc.;

c.

A matrix that shows the correlation between the mitigation strategies identified in

Nuclear Energy Institute 06-12 and the site-specific procedures or guidelines that

are used to implement each strategy;

d.

A listing of engineering evaluations/calculations that were used to verify

engineering bases for the mitigation strategies;

e.

Copies of procedures used to inventory equipment (hoses, fittings, pumps, etc.)

required to be used to implement the mitigation strategies;

f.

A list of B.5.b mitigating strategies, if any, which have implementing details that

differ from that documented in the submittals and the safety evaluation report;

g.

Copies of Memoranda of Understanding (MOUs) (e.g., with local fire departments)

required to implement any mitigating strategies; and

h.

A list of changes made to B.5.b mitigating strategies and associated procedures

since the previous NRC inspection of B.5.b mitigating strategies (March 13, 2012).

9. Onsite Discussions:

In addition, during the information gathering visit, it is requested that licensee staff be

available for the following:

a.

Informal discussion on plant procedures operators would use in the event of fire or

explosion (including B.5.b mitigation strategies) and under what conditions would

the plant be shutdown using alternative shutdown methodology;

b.

Informal discussion on the plants safe shutdown cable routing database and the

plant-wide cable routing database, as applicable;

c.

A tour of alternative shutdown and risk significant fire areas; and

d.

A discussion of scheduling of fire drills which may occur during the inspection so

that the inspectors may be able to observe a fire drill, if possible.

NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

REQUEST FOR INFORMATION

6

III. Information Requested to be Available on First Day of the Second ONSITE Inspection

Week (OCTOBER 5, 2015)

The following information is requested to be provided on the first day of inspection. It is

requested that this information be provided on four sets of CDs (searchable, if possible).

1. Program Procedures:

a.

Procedures for:

i. Administrative controls (such as allowed out of service times and

compensatory measures) for fire protection systems and components;

ii. Control of transient combustibles; and

iii. Control of hot work.

b.

List of maintenance and surveillance testing procedures for alternative shutdown

capability and fire barriers, detectors, pumps, and suppression systems; and

c.

List of maintenance procedures which routinely verify fuse breaker coordination

in accordance with the post-fire safe shutdown coordination analysis.

2. Design and Equipment Information:

a.

Coordination calculations and/or justifications that verify fuse/breaker

coordination for selected fire zones/areas (to be determined during

information gathering visit) that are fed off of the same electrical buses as

components in the protected safe shutdown train;

b.

Copies of significant fire protection and post-fire safe shutdown related design

change package descriptions (including their associated 10 CFR 50.59

evaluations) and Generic Letter (GL) 86-10 (or adverse to safe shutdown)

evaluations;

c.

Gaseous suppression system pre-operational testing, if applicable, for selected

fire zones/areas (to be determined during information gathering visit);

d.

Hydraulic calculations and supporting test data which demonstrate operability for

water suppression systems, if applicable, for selected fire zones/areas (to be

determined during information gathering visit);

e.

Alternating current (ac) coordination calculations for 4160Vac down to 480Vac

electrical systems; and

f.

List of all fire protection or Appendix R calculations.

NOTIFICATION OF NRC TRIENNIAL FIRE PROTECTION BASELINE INSPECTION

REQUEST FOR INFORMATION

7

3. Assessment and Corrective Actions:

The three most recent fire protection Quality Assurance (QA) audits and/or fire

protection self-assessments.

4. Any updates to information previously provided.

IV.

Information Requested to Be Provided Throughout the Inspection

1. Copies of any corrective action documents generated as a result of the inspection

teams questions or queries during this inspection.

2. Copies of the list of questions submitted by the inspection team members and the

status/resolution of the information requested (provided daily during the inspection to

each inspection team member).

If you have questions regarding the information requested, please contact the lead inspector.

E. Harkness

-3-

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS

is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic

Reading Room).

Sincerely,

/RA George Hausman Acting for/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket No. 50-440

License No. NPF-58

Enclosure: Fire Protection Inspection

Document Request

cc w/encl: Distribution via LISTSERV

DISTRIBUTION w/encl:

Kimyata MorganButler

RidsNrrPMPerry Resource

RidsNrrDorlLpl3-2 Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

Jim Clay

Carmen Olteanu

ROPreports.Resource@nrc.gov

ADAMS Accession Number ML15204A829

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE

RIII

RIII

RIII

RIII

NAME

DSzwarc:jw

GHausman for

RDaley

DATE

07/23/15

07/23/15

OFFICIAL RECORD COPY