ML18058B827: Difference between revisions
StriderTol (talk | contribs) Created page by program invented by StriderTol |
StriderTol (talk | contribs) StriderTol Bot change |
||
| (3 intermediate revisions by the same user not shown) | |||
| Line 3: | Line 3: | ||
| issue date = 05/19/1993 | | issue date = 05/19/1993 | ||
| title = Responds to NRC 930312 Request for Written Verification of Conformance to Industry Position on Shutdown Mgt,Per Deferment of Amend Request for Shutdown Cooling.Revised TS Pages Encl | | title = Responds to NRC 930312 Request for Written Verification of Conformance to Industry Position on Shutdown Mgt,Per Deferment of Amend Request for Shutdown Cooling.Revised TS Pages Encl | ||
| author name = | | author name = Slade G | ||
| author affiliation = CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.), | | author affiliation = CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.), | ||
| addressee name = | | addressee name = | ||
| Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:' consumers Power POW ERIN& | {{#Wiki_filter:' | ||
PRD&RESS Palisades Nuclear Plant: 27780 Blue Star Memorial Highway, Covert: Ml 49043 May 19, 1993 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 | consumers Power POW ERIN& | ||
MICHl&AN~S PRD&RESS Palisades Nuclear Plant: | |||
: 1) 2) Has assessed current practices, using NUMARC 91-06, | 27780 Blue Star Memorial Highway, Covert: Ml 49043 May 19, 1993 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 GB Slade General Manager DOCKET 50-255 - LICENSE DPR PALISADES PLANT - REPLY TO NRC REQUEST FOR WRITTEN VERIFICATION OF CONFORMANCE TO INDUSTRY POSITION ON SHUTDOWN MANAGEMENT We have received your letter of March 12, 1993, regarding 11 DEFERMENT OF AMENDMENT REQUEST FOR SHUTDOWN COOLING 11 In the interest of closing the issue of adding consideration of shutdown risk issues to the Palisades Technical Specifications, by this letter we provide the written verification you request, that Palisades: | ||
We must temper this verification with a note that the above verification can only apply to our interpretation of the NUMARC document and that the current view of proper management of shutdown risk is in a state of change. If forthcoming information convince us that there are better or additional methods of assuring safety during shutdown periods we will consider those methods. We will inform the NRC of any significant changes in our approach to shutdown risk management. | : 1) | ||
: 2) | |||
Has assessed current practices, using NUMARC 91-06, 11Guidelines for Industry Action to Assess Shutdown Management, 11 to plan outages, and Has implemented improvements adopted as a result of the assessment. | |||
We must temper this verification with a note that the above verification can only apply to our interpretation of the NUMARC document and that the current view of proper management of shutdown risk is in a state of change. | |||
If forthcoming information convince us that there are better or additional methods of assuring safety during shutdown periods we will consider those methods. | |||
We will inform the NRC of any significant changes in our approach to shutdown risk management. | |||
Revised Technical Specifications pages, including both the changes proposed in our earlier Shutdown Cooling submittals and changes made by intervening amendments are attached. | Revised Technical Specifications pages, including both the changes proposed in our earlier Shutdown Cooling submittals and changes made by intervening amendments are attached. | ||
We request that the associated license amendment become effective no sooner than 90 days after approval, to allow completion of the associated training and procedure changes. | We request that the associated license amendment become effective no sooner than 90 days after approval, to allow completion of the associated training and procedure changes. | ||
Gerald B. Slade Plant General Manager Palisades Nuclear Plant CC Administrator, Region III, USNRC NRC Resident Inspector | ~~13~ | ||
-Palisades Document Control Desk NUMARC | Gerald B. Slade Plant General Manager Palisades Nuclear Plant CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades Document Control Desk NUMARC | ||
---- --- 2.li1HQ_*r1 9305260042 930519-- | |||
PPDR ADOCK 05000255 l\\)f\\f} \\ I A CMS ENERGY COMPANY 1\\V" | |||
\\ | |||
PDR}} | |||
Latest revision as of 07:56, 6 January 2025
| ML18058B827 | |
| Person / Time | |
|---|---|
| Site: | Palisades |
| Issue date: | 05/19/1993 |
| From: | Slade G CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.) |
| To: | NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM) |
| Shared Package | |
| ML18058B829 | List: |
| References | |
| NUDOCS 9305260042 | |
| Download: ML18058B827 (1) | |
Text
'
consumers Power POW ERIN&
MICHl&AN~S PRD&RESS Palisades Nuclear Plant:
27780 Blue Star Memorial Highway, Covert: Ml 49043 May 19, 1993 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 GB Slade General Manager DOCKET 50-255 - LICENSE DPR PALISADES PLANT - REPLY TO NRC REQUEST FOR WRITTEN VERIFICATION OF CONFORMANCE TO INDUSTRY POSITION ON SHUTDOWN MANAGEMENT We have received your letter of March 12, 1993, regarding 11 DEFERMENT OF AMENDMENT REQUEST FOR SHUTDOWN COOLING 11 In the interest of closing the issue of adding consideration of shutdown risk issues to the Palisades Technical Specifications, by this letter we provide the written verification you request, that Palisades:
- 1)
- 2)
Has assessed current practices, using NUMARC 91-06, 11Guidelines for Industry Action to Assess Shutdown Management, 11 to plan outages, and Has implemented improvements adopted as a result of the assessment.
We must temper this verification with a note that the above verification can only apply to our interpretation of the NUMARC document and that the current view of proper management of shutdown risk is in a state of change.
If forthcoming information convince us that there are better or additional methods of assuring safety during shutdown periods we will consider those methods.
We will inform the NRC of any significant changes in our approach to shutdown risk management.
Revised Technical Specifications pages, including both the changes proposed in our earlier Shutdown Cooling submittals and changes made by intervening amendments are attached.
We request that the associated license amendment become effective no sooner than 90 days after approval, to allow completion of the associated training and procedure changes.
~~13~
Gerald B. Slade Plant General Manager Palisades Nuclear Plant CC Administrator, Region III, USNRC NRC Resident Inspector - Palisades Document Control Desk NUMARC
--- 2.li1HQ_*r1 9305260042 930519--
PPDR ADOCK 05000255 l\\)f\\f} \\ I A CMS ENERGY COMPANY 1\\V"
\\