{{#Wiki_filter:Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar- | {{#Wiki_filter:Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar-18 Acceptance Review - Action: Issuance of acceptance letter. | ||
11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 From: Diaz Maldonado, Marilyn To: weave1dw@westinghouse.com | 4-May-18 FRN (Opportunity to request a hearing (30 d)) | ||
; Spalding, Amanda J Cc: Johnson, Robert | 11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 From: | ||
; Erlanger, Craig | Diaz Maldonado, Marilyn To: | ||
; Smith, Brian | weave1dw@westinghouse.com; Spalding, Amanda J Cc: | ||
Johnson, Robert; Erlanger, Craig; Smith, Brian | |||
==Subject:== | ==Subject:== | ||
Westinghouse Transfer of Control Application/Review - Schedule Date: Monday, May 07, 2018 11:16:00 AM Hi Doug, During our last conference call, you requested an understanding of the NRC | Westinghouse Transfer of Control Application/Review - Schedule Date: | ||
Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule. | Monday, May 07, 2018 11:16:00 AM Hi Doug, | ||
Thanks, | |||
, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110}} | During our last conference call, you requested an understanding of the NRC staffs milestones going forward regarding the Transfer of Control review. Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule. | ||
If you have any questions, please let me know. | |||
: Thanks, Marilyn Diaz, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110}} | |||
Latest revision as of 20:54, 5 January 2025
| ML18141A642 | |
| Person / Time | |
|---|---|
| Issue date: | 05/07/2018 |
| From: | Diaz-Maldonado M Fuel Manufacturing Branch |
| To: | Weaver D Westinghouse |
| Diaz M | |
| References | |
| Download: ML18141A642 (1) | |
Text
Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar-18 Acceptance Review - Action: Issuance of acceptance letter.
4-May-18 FRN (Opportunity to request a hearing (30 d))
11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 From:
Diaz Maldonado, Marilyn To:
weave1dw@westinghouse.com; Spalding, Amanda J Cc:
Johnson, Robert; Erlanger, Craig; Smith, Brian
Subject:
Westinghouse Transfer of Control Application/Review - Schedule Date:
Monday, May 07, 2018 11:16:00 AM Hi Doug,
During our last conference call, you requested an understanding of the NRC staffs milestones going forward regarding the Transfer of Control review. Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule.
If you have any questions, please let me know.
- Thanks, Marilyn Diaz, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110