ML18141A642: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 12: Line 12:
| document type = E-Mail
| document type = E-Mail
| page count = 1
| page count = 1
| project =
| stage = Other
}}
}}


=Text=
=Text=
{{#Wiki_filter:Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar-18Acceptance Review - Action: Issuance of acceptance letter.4-May-18 FRN (Opportunity to request a hearing (30 d))
{{#Wiki_filter:Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar-18 Acceptance Review - Action: Issuance of acceptance letter.
11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 From: Diaz Maldonado, Marilyn To: weave1dw@westinghouse.com
4-May-18 FRN (Opportunity to request a hearing (30 d))
; Spalding, Amanda J Cc: Johnson, Robert
11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 From:
; Erlanger, Craig
Diaz Maldonado, Marilyn To:
; Smith, Brian
weave1dw@westinghouse.com; Spalding, Amanda J Cc:
Johnson, Robert; Erlanger, Craig; Smith, Brian


==Subject:==
==Subject:==
Westinghouse Transfer of Control Application/Review - Schedule Date: Monday, May 07, 2018 11:16:00 AM Hi Doug, During our last conference call, you requested an understanding of the NRC staff's milestones going forward regarding the Transfer of Control review.
Westinghouse Transfer of Control Application/Review - Schedule Date:
Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule.                   If you have any questions, please let me know.
Monday, May 07, 2018 11:16:00 AM Hi Doug,
Thanks, Marilyn Diaz
 
, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110}}
During our last conference call, you requested an understanding of the NRC staffs milestones going forward regarding the Transfer of Control review. Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule.
 
If you have any questions, please let me know.
: Thanks, Marilyn Diaz, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110}}

Latest revision as of 20:54, 5 January 2025

W05/07/2018 E-mail Westinghouse Transfer of Control Application/Review - Schedule
ML18141A642
Person / Time
Issue date: 05/07/2018
From: Diaz-Maldonado M
Fuel Manufacturing Branch
To: Weaver D
Westinghouse
Diaz M
References
Download: ML18141A642 (1)


Text

Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar-18 Acceptance Review - Action: Issuance of acceptance letter.

4-May-18 FRN (Opportunity to request a hearing (30 d))

11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 From:

Diaz Maldonado, Marilyn To:

weave1dw@westinghouse.com; Spalding, Amanda J Cc:

Johnson, Robert; Erlanger, Craig; Smith, Brian

Subject:

Westinghouse Transfer of Control Application/Review - Schedule Date:

Monday, May 07, 2018 11:16:00 AM Hi Doug,

During our last conference call, you requested an understanding of the NRC staffs milestones going forward regarding the Transfer of Control review. Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule.

If you have any questions, please let me know.

Thanks, Marilyn Diaz, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110