ML18312A367: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(4 intermediate revisions by the same user not shown)
Line 9: Line 9:
| docket = PROJ0753
| docket = PROJ0753
| license number =  
| license number =  
| contact person = Honcharik M C
| contact person = Honcharik M
| package number = ML18312A362
| package number = ML18312A362
| document type = Meeting Briefing Package/Handouts
| document type = Meeting Briefing Package/Handouts
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:}}
{{#Wiki_filter:Page 1 EXCEL Services Corporation TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program Original Schedule 3/18/18 Change 5/3/18 Change 9/7/18 Change 11/1/18 Reason Submitted 12/19/17 RAIs 4/17/18 No RAIs Draft SE 9/28/18 10/26/18 11/8/18 OGC then DORL delays Final SE 12/19/18 RAI Response to Final SE: 10 Months TSTF-563, Rev. 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program Original Schedule 7/3/17 Change 7/3/17 Change 2/15/18 Change 7/3/18 Change 8/2/18 Change 9/20/18 Change 10/12/18 Reason Submitted 5/10/17 RAIs 9/7/17 10/5/17 2/15/18 Draft RAIs from EICB and APLA.
Second round APLA RAI on 2/15/18.
TSTF
 
===Response===
4/17/18 TSTF to respond to draft to save time.
Draft SE 3/3/18 8/31/18 10/31/18 9/20/18 Actual on 9/20/18 Final SE 5/17/18 12/20/18 RAI Response to Final SE: 8 Months
 
Page 2 EXCEL Services Corporation TSTF-564, Rev. 1, Safety Limit MCPR - High priority, plant startup related Original Schedule 11/18/17 Change 4/12/18 Change 6/8/18 Change 7/3/18 Change 9/7/18 Change 10/4/18 Change 10/24/18 Reason Submitted 8/28/17 RAIs 3/16/18 4/12/18 Draft RAI 3/20/18 TSTF
 
===Response===
5/29/18 TSTF provided draft on 5/3/18.
Revised draft response based on NRC comments Draft SE 5/30/18 6/29/18 8/31/18 9/30/18 10/4/18 Actual 10/4/18 Final SE 7/31/18 11/26/18 RAI Response to Final SE: 6 Months TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Original Schedule 3/26/18 Change 4/5/18 Change 10/29/18 Change Reason Submitted 1/18/18 RAIs 5/4/18 Determined no RAI needed Draft SE 10/16/18 11/8/18 On schedule as of 9/7/18 Final SE 1/18/19
??
RAI Response to Final SE: 9 Months}}

Latest revision as of 09:46, 5 January 2025

Handout from 11/08/2018 TSTF Meeting for Agenda Item Ii.B.C November 2018 Traveler Review Schedule Changes
ML18312A367
Person / Time
Site: Technical Specifications Task Force
Issue date: 11/08/2018
From:
Technical Specifications Task Force
To:
Office of Nuclear Reactor Regulation
Honcharik M
Shared Package
ML18312A362 List:
References
Download: ML18312A367 (2)


Text

Page 1 EXCEL Services Corporation TSTF-557, Rev. 1, Spent Fuel Storage Rack Neutron Absorber Monitoring Program Original Schedule 3/18/18 Change 5/3/18 Change 9/7/18 Change 11/1/18 Reason Submitted 12/19/17 RAIs 4/17/18 No RAIs Draft SE 9/28/18 10/26/18 11/8/18 OGC then DORL delays Final SE 12/19/18 RAI Response to Final SE: 10 Months TSTF-563, Rev. 0, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program Original Schedule 7/3/17 Change 7/3/17 Change 2/15/18 Change 7/3/18 Change 8/2/18 Change 9/20/18 Change 10/12/18 Reason Submitted 5/10/17 RAIs 9/7/17 10/5/17 2/15/18 Draft RAIs from EICB and APLA.

Second round APLA RAI on 2/15/18.

TSTF

Response

4/17/18 TSTF to respond to draft to save time.

Draft SE 3/3/18 8/31/18 10/31/18 9/20/18 Actual on 9/20/18 Final SE 5/17/18 12/20/18 RAI Response to Final SE: 8 Months

Page 2 EXCEL Services Corporation TSTF-564, Rev. 1, Safety Limit MCPR - High priority, plant startup related Original Schedule 11/18/17 Change 4/12/18 Change 6/8/18 Change 7/3/18 Change 9/7/18 Change 10/4/18 Change 10/24/18 Reason Submitted 8/28/17 RAIs 3/16/18 4/12/18 Draft RAI 3/20/18 TSTF

Response

5/29/18 TSTF provided draft on 5/3/18.

Revised draft response based on NRC comments Draft SE 5/30/18 6/29/18 8/31/18 9/30/18 10/4/18 Actual 10/4/18 Final SE 7/31/18 11/26/18 RAI Response to Final SE: 6 Months TSTF-566, Rev. 0, Revise Actions for Inoperable RHR Shutdown Cooling Subsystems Original Schedule 3/26/18 Change 4/5/18 Change 10/29/18 Change Reason Submitted 1/18/18 RAIs 5/4/18 Determined no RAI needed Draft SE 10/16/18 11/8/18 On schedule as of 9/7/18 Final SE 1/18/19

??

RAI Response to Final SE: 9 Months