| number = ML19257B828 | | number = ML19257B828 | ||
| issue date = 12/10/1979 | | issue date = 12/10/1979 | ||
| title = Forwards Copy of Util 790925 Response to IE Bulletin 79-19, Packaging of Low Level Radwaste for Transport & Burial | | title = Forwards Copy of Util 790925 Response to IE Bulletin 79-19, Packaging of Low Level Radwaste for Transport & Burial | ||
| author name = Borgmann E | | author name = Borgmann E | ||
| author affiliation = CINCINNATI GAS & ELECTRIC CO. | | author affiliation = CINCINNATI GAS & ELECTRIC CO. | ||
| Line 17: | Line 17: | ||
=Text= | =Text= | ||
{{#Wiki_filter:' | {{#Wiki_filter:' | ||
t tm | |||
t | '\\ ' ? | ||
) | |||
b sa h | |||
-M: * - | |||
THE CINCINNATI GAS & ELECTRIC COMPANY DIP | |||
"~~ ~ 1 2 OlNCINN ATI OHIO 4 5201 December 10, 1979 E. A. BORG M AN N vaC E PRE SIDE NT U.S. Nuclear Regulatory Commission Office Of Inspection S Enforcement Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 ATTN: | |||
1.fr. James G. Keppler / | |||
THE CINCINNATI GAS & ELECTRIC COMPANY | Regional Director RE: | ||
WM. H. | |||
ZIICIER NUCLEAR POWER STATION - UNIT 1 IE BULLETIN # 79-19 DOCKET 50-358 W.O. | |||
57300, JOB E-5590 Gentlemen: | |||
Regional Director RE: | Your letter of November 27, 1979 indicated you had not yet received our response to IE Bulletin 79-19. | ||
Your letter of November 27, 1979 indicated you had not yet received our response to IE Bulletin 79-19. | As suggested in your letter, correspondence does sometimes go astray. | ||
We did respond via letter dated September 25, 1979. | It appears that is what happened in this case. | ||
We did respond via {{letter dated|date=September 25, 1979|text=letter dated September 25, 1979}}. | |||
A copy is attached. | |||
We believe this will resolve the matter. | |||
Very truly yours, TIIE CINCINNATI GAS S ELECTRIC COMPANY | Very truly yours, TIIE CINCINNATI GAS S ELECTRIC COMPANY | ||
([ | ([ | ||
E.A. BORGMANN, SEN OR VICE PRFSIDENT IICB/ kj d cc: | e< - | ||
E.A. BORGMANN, SEN OR VICE PRFSIDENT IICB/ kj d cc: | |||
W.D. | |||
Waymiro J.D. | |||
Flynn W.W. Schwiers S.G. | |||
Salay J.R. Schott R.F. Scheibel II.C. Brinkmann NRC Office of Inspection S Enforcement Division of Fuel Facility 4 Materials 1773 011 Safety Inspection Washington, D.C. | |||
20555 DEC 2 81978 8 00121 o 09 D | |||
767, R.2 7ER Lf 4G. S M t | 767, R.2 7ER Lf 4G. S M t | ||
September 25, 1979 | September 25, 1979 U.S. Nuclear Regulatory Commission O'" ice of Inspection and Enforcement nes_on III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention: | ||
Mr. James G. | |||
U.S. Nuclear Regulatory Commission O'" ice of Inspection and Enforcement nes_on III 799 Roosevelt Road Glen Ellyn, Illinois | Keppler legional Director RE: | ||
UNIT 1 - IE BULLETIN 79-19, DOCKET NO. 50-358, W.O. 57300, JOB E-5590 Gentlemen: | WM. H. ZIMMER NUCLEAR POWER STATION - | ||
UNIT 1 - IE BULLETIN 79-19, DOCKET NO. 50-358, W.O. | |||
57300, JOB E-5590 Gentlemen: | |||
In response to the above, please be advised the Zimmer Plant has not yet generated any radioactive waste. | In response to the above, please be advised the Zimmer Plant has not yet generated any radioactive waste. | ||
Initial fuel loading is scheduled for July, 1980. | Initial fuel loading is scheduled for July, 1980. | ||
We are maintaining sets of DOT and NRC regulations concerning transfers of radioactive waste. | We are maintaining sets of DOT and NRC regulations concerning transfers of radioactive waste. | ||
We also have con-tacted waste burial firms requesting their requirements including their State Agreements and requirements imposed by their State. | |||
We have received initial information and are working actively with these firms to identify detailed requirements now. | We have received initial information and are working actively with these firms to identify detailed requirements now. | ||
Plant radwaste procedures are being developed now. | Plant radwaste procedures are being developed now. | ||
We plan to incorporate all appropriate requirements of DOT, NRC and burial States. Management audit of activities is planned. | We plan to incorporate all appropriate requirements of DOT, NRC and burial States. | ||
Management audit of activities is planned. | |||
Since the Zimmer Plant is not yet generating radwaste, we believe this response completes the requirements of IE Bulletin 79-19. | Since the Zimmer Plant is not yet generating radwaste, we believe this response completes the requirements of IE Bulletin 79-19. | ||
Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY nrn l norro | Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY p | ||
12CE : dew ccs | nrn l norro d | ||
INdN By ff,9f/) | |||
E. | |||
A. BORGMANN l'~ | |||
Senior Vice President | |||
/ | |||
12CE : dew 1773 012 ccs W. D. Waymire J. | |||
D. Flynn H. C. Brinkmann W. W. Schwiers NRC Office of Inspection & Enforcement gj: | |||
S. G. Salay Division of Fuel Facility & Materials J. | |||
R. Schott Safety Inspection | |||
+v_a c, o | |||
o cun 4 A,1 wnchincton, D.C. | |||
20555}} | |||
Latest revision as of 19:20, 3 January 2025
| ML19257B828 | |
| Person / Time | |
|---|---|
| Site: | Zimmer |
| Issue date: | 12/10/1979 |
| From: | Borgmann E CINCINNATI GAS & ELECTRIC CO. |
| To: | James Keppler NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| References | |
| IEB-79-19, NUDOCS 8001210020 | |
| Download: ML19257B828 (1) | |
Text
'
t tm
'\\ ' ?
)
b sa h
-M: * -
THE CINCINNATI GAS & ELECTRIC COMPANY DIP
"~~ ~ 1 2 OlNCINN ATI OHIO 4 5201 December 10, 1979 E. A. BORG M AN N vaC E PRE SIDE NT U.S. Nuclear Regulatory Commission Office Of Inspection S Enforcement Region III 799 Roosevelt Road Glen Ellyn, Illinois 60137 ATTN:
1.fr. James G. Keppler /
Regional Director RE:
WM. H.
ZIICIER NUCLEAR POWER STATION - UNIT 1 IE BULLETIN # 79-19 DOCKET 50-358 W.O.
57300, JOB E-5590 Gentlemen:
Your letter of November 27, 1979 indicated you had not yet received our response to IE Bulletin 79-19.
As suggested in your letter, correspondence does sometimes go astray.
It appears that is what happened in this case.
We did respond via letter dated September 25, 1979.
A copy is attached.
We believe this will resolve the matter.
Very truly yours, TIIE CINCINNATI GAS S ELECTRIC COMPANY
([
e< -
E.A. BORGMANN, SEN OR VICE PRFSIDENT IICB/ kj d cc:
W.D.
Waymiro J.D.
Flynn W.W. Schwiers S.G.
Salay J.R. Schott R.F. Scheibel II.C. Brinkmann NRC Office of Inspection S Enforcement Division of Fuel Facility 4 Materials 1773 011 Safety Inspection Washington, D.C.
20555 DEC 2 81978 8 00121 o 09 D
767, R.2 7ER Lf 4G. S M t
September 25, 1979 U.S. Nuclear Regulatory Commission O'" ice of Inspection and Enforcement nes_on III 799 Roosevelt Road Glen Ellyn, Illinois 60137 Attention:
Mr. James G.
Keppler legional Director RE:
WM. H. ZIMMER NUCLEAR POWER STATION -
UNIT 1 - IE BULLETIN 79-19, DOCKET NO. 50-358, W.O.
57300, JOB E-5590 Gentlemen:
In response to the above, please be advised the Zimmer Plant has not yet generated any radioactive waste.
Initial fuel loading is scheduled for July, 1980.
We are maintaining sets of DOT and NRC regulations concerning transfers of radioactive waste.
We also have con-tacted waste burial firms requesting their requirements including their State Agreements and requirements imposed by their State.
We have received initial information and are working actively with these firms to identify detailed requirements now.
Plant radwaste procedures are being developed now.
We plan to incorporate all appropriate requirements of DOT, NRC and burial States.
Management audit of activities is planned.
Since the Zimmer Plant is not yet generating radwaste, we believe this response completes the requirements of IE Bulletin 79-19.
Very truly yours, THE CINCINNATI GAS & ELECTRIC COMPANY p
nrn l norro d
INdN By ff,9f/)
E.
A. BORGMANN l'~
Senior Vice President
/
12CE : dew 1773 012 ccs W. D. Waymire J.
D. Flynn H. C. Brinkmann W. W. Schwiers NRC Office of Inspection & Enforcement gj: