h Public 2420 W. 26th     Service' Avenue, Suite 100D, Denver, Colorado 80211 (Og,c Bm$0 mm April 8, 1991                                                                           A. Clegg Crawford Fort St. Vrain                                                                         gjg*",'on, Unit No. 1 P-91121 U. S. Nuclear Regulatory Commission ATTN:     Document Control Desk Washington, D.C. 20555 ATTN: Mr. Seymour H. Weiss, Director Non-Power Reactor, Decommissioning and Environmental Project Directorate Docket No. 50-267 5UBJECT:         Response to Request for Additional Information (RAl)
(O Bm$0 2420 W. 26th Avenue, Suite 100D, Denver, Colorado 80211 g,c mm April 8, 1991 A. Clegg Crawford Fort St. Vrain gjg*",'on, Unit No. 1 P-91121 U. S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C.
20555 ATTN: Mr. Seymour H. Weiss, Director Non-Power Reactor, Decommissioning and Environmental Project Directorate Docket No. 50-267 5UBJECT:
Response to Request for Additional Information (RAl)


==REFERENCE:==
==REFERENCE:==
Line 24: Line 27:


==Dear Mr. Weiss:==
==Dear Mr. Weiss:==
 
In the reference above, the NRC requested additional information related to the Fort St. Vrain Proposed Decommissioning Plan by April 1,
In the reference above, the NRC requested additional information related to the Fort St. Vrain Proposed Decommissioning Plan by April 1, 1991.         The PSC and Westinghouse effort required to prepare deteiled responses to this request has been greater than originally anticipated. Therefore, PSC requests a delay in the initial response to the RAI until April 26, 1991.
1991.
The PSC and Westinghouse effort required to prepare deteiled responses to this request has been greater than originally anticipated. Therefore, PSC requests a delay in the initial response to the RAI until April 26, 1991.
Should you have any questions concerning this matter, please contact Mr. M. H. Holmer at (303) 480-6960.
Should you have any questions concerning this matter, please contact Mr. M. H. Holmer at (303) 480-6960.
Very truly yours,
Very truly yours,
            'f     Oby blrO A. Clegg Crawford Vice President Nuclear Operations ACC/DCG:km cc:   Regional Administrator, Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011 Mr. J. B. Baird                                                                                         '
'f Oby blrO A. Clegg Crawford Vice President Nuclear Operations ACC/DCG:km cc:
Senior Resident Inspector Fort St. Vrain ji''
Regional Administrator, Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011 Mr. J. B. Baird Senior Resident Inspector Fort St. Vrain ji 90 OOOk bObb!67
p 90     OOOk bObb!67 PDR
[8N p
[8N
PDR
                                                                                                                            /g
/g
                                                                                                                      .-}}
.-}}

Latest revision as of 04:18, 15 December 2024

Responds to NRC 910208 Request for Addl Info Re Proposed Decommissioning Plan.Requests Extension of Initial Response to Request for Addl Info Until 910426 to Enable Westinghouse & Util to Prepare Detailed Response
ML20072T188
Person / Time
Site: Fort Saint Vrain 
Issue date: 04/08/1991
From: Crawford A
PUBLIC SERVICE CO. OF COLORADO
To: Weiss S
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
References
P-91121, NUDOCS 9104180005
Download: ML20072T188 (1)


Text

_

h Public Service' 20.%'L,..

(O Bm$0 2420 W. 26th Avenue, Suite 100D, Denver, Colorado 80211 g,c mm April 8, 1991 A. Clegg Crawford Fort St. Vrain gjg*",'on, Unit No. 1 P-91121 U. S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C.

20555 ATTN: Mr. Seymour H. Weiss, Director Non-Power Reactor, Decommissioning and Environmental Project Directorate Docket No. 50-267 5UBJECT:

Response to Request for Additional Information (RAl)

REFERENCE:

NRC letter, Erickson to Crawford dated February 8, 1991 (G-91020)

Dear Mr. Weiss:

In the reference above, the NRC requested additional information related to the Fort St. Vrain Proposed Decommissioning Plan by April 1,

1991.

The PSC and Westinghouse effort required to prepare deteiled responses to this request has been greater than originally anticipated. Therefore, PSC requests a delay in the initial response to the RAI until April 26, 1991.

Should you have any questions concerning this matter, please contact Mr. M. H. Holmer at (303) 480-6960.

Very truly yours,

'f Oby blrO A. Clegg Crawford Vice President Nuclear Operations ACC/DCG:km cc:

Regional Administrator, Region IV 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76011 Mr. J. B. Baird Senior Resident Inspector Fort St. Vrain ji 90 OOOk bObb!67