| title = Forwards Constituent Hg Haby 841102 Ltr Re Delays in Facility Licensing Process Resulting in Higher Costs
| title = Forwards Constituent Hg Haby Re Delays in Facility Licensing Process Resulting in Higher Costs
| author name = Bentsen L
| author name = Bentsen L
| author affiliation = SENATE
| author affiliation = SENATE
Line 11: Line 11:
| contact person =  
| contact person =  
| document report number = NUDOCS 8412280451
| document report number = NUDOCS 8412280451
| title reference date = 11-02-1984
| package number = ML20101J179
| package number = ML20101J179
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE
Line 17: Line 18:


=Text=
=Text=
{{#Wiki_filter:r -- c , egEENT5EN                                                                                           cI***stTEv a
{{#Wiki_filter:r -- c, egEENT5EN cI***stTEv a f*
    ,_      f*         Ttx ,a                                                                                     rms. Net.
Ttx,a rms. Net.
                                        ~                                                           guy,poNugNT At 3 ruhic woaxs s      .' .        !                        e
~
* somT ECONOMIC
guy,poNugNT At 3 ruhic woaxs e
                                                                ?JCnifeb Sinica Senab WASHINGTON. D.C. 20$10 November 15, 1984 Mr. Carlton C. Kammerer, Director Office of Congressi'onal Affairs
s somT ECONOMIC
                              'The United States Nuclear Regulatory Commission,                             .
?JCnifeb Sinica Senab WASHINGTON. D.C. 20$10 November 15, 1984 Mr. Carlton C. Kammerer, Director Office of Congressi'onal Affairs
1717 H~ Street, N.W.                         -
'The United States Nuclear Regulatory Commission, 1717 H~ Street, N.W.
Washington,"D.C._ 20555
Washington,"D.C._ 20555


==Dear Mr. Kammerer:==
==Dear Mr. Kammerer:==
 
Enclosed for your review is a copy of a letter I have received from Mr. Hayden G. Haby, Jr. of Granbury, Texas.
Enclosed for your review is a copy of a letter I have received from Mr. Hayden G. Haby, Jr. of Granbury, Texas.         I would certainly appreciate your sending me any pertinent information that you might have in this regard.
I would certainly appreciate your sending me any pertinent information that you might have in this regard.
Thank you for your assistance.                                                                      ,.
Thank you for your assistance.
Sincerely,
Sincerely, n.
                      .....            n.                     ''
~C.
  !                    ~C.           .'',2 ~ ''           ,
.'',2 ~ ''
                                                                              /                                                 ,
/
i ,.               ,
i,.
(
(
Lloyd Bentsen
Lloyd Bentsen
                                -a /
-a /
Encl'osure PLEASE REPLY TO:
Encl'osure PLEASE REPLY TO:
912 Federal Building Austin, Texas 78701                                                                                 .
912 Federal Building Austin, Texas 78701 l
l l
l I
I 1
1 OS h h5 PH pm
H P                    OS hpm      h5


w     ,
w
    .  ./'
./'
  ,y     g   'L                       '.  .
,y g
November 2,   1984 The Honorable Lloyd Bentson United States Senate
'L November 2, 1984 The Honorable Lloyd Bentson United States Senate
                - 703 Hart Senate Office. Building Washington, D.C. 20510 Dear Mr. Bentson                 -
- 703 Hart Senate Office. Building Washington, D.C.
I would 1-ike to ex, press my deep concern about the delays in the Comanche Peak Steam Electric Station Licensing Process which only result in higher consumer cost and unavailable electrical reserves.
20510 Dear Mr. Bentson I would 1-ike to ex, press my deep concern about the delays in the Comanche Peak Steam Electric Station Licensing Process which only result in higher consumer cost and unavailable electrical reserves.
The Comanche Peak Plant is practically ready to load fuel and commence testing to begin commercial operation. The,follo-wing are facts concerning the Texas Utilities (TU) system.                 ,
The Comanche Peak Plant is practically ready to load fuel and commence testing to begin commercial operation.
: 1.     The TU system reached a peak load of 15265 Megawatts (MW)_on August 29, 1984 exceeding the 1983 estimate of 14300 f                         MW s The operating reserve decreased to 2652 MW or 14.7% based on the TU System capacity of 17890 MW. However, the TU Sys- ~
The,follo-wing are facts concerning the Texas Utilities (TU) system.
1.
The TU system reached a peak load of 15265 Megawatts (MW)_on August 29, 1984 exceeding the 1983 estimate of 14300 f
MW The operating reserve decreased to 2652 MW or 14.7% based s
on the TU System capacity of 17890 MW.
However, the TU Sys- ~
tem's only had an actual 6 x reserve capacity on. August 29 due to unanticipated plant outages.
tem's only had an actual 6 x reserve capacity on. August 29 due to unanticipated plant outages.
: 2.     The TU System did not have an alternate source of power during the load peak.
2.
: 3.     The 1985 summer peak is expected to be 8.8% greater than the 1983 peak. A 16608 MW peak would leave 1282 MW or 7.2 x r e r.e r v e . The Comanche Peak Unit One could provide an addi-tional 1139 MW.
The TU System did not have an alternate source of power during the load peak.
Depending on the TU System total capacity is some what risky and idealistic due unexpected generating loss, excessive load growth cnd natural gas curtailment.           The consequences of the slightest unexpected circumstance can be a system brownout causing a loss of industrial production and residential service.
3.
The 1985 summer peak is expected to be 8.8% greater than the 1983 peak. A 16608 MW peak would leave 1282 MW or 7.2 x r e r.e r v e.
The Comanche Peak Unit One could provide an addi-tional 1139 MW.
Depending on the TU System total capacity is some what risky and idealistic due unexpected generating loss, excessive load growth cnd natural gas curtailment.
The consequences of the slightest unexpected circumstance can be a system brownout causing a loss of industrial production and residential service.
Each day of delay at Conanche Peak cost the Utility and consumer about one million dollars in preventabic interest, ope-rating and replacement fuel costs.
Each day of delay at Conanche Peak cost the Utility and consumer about one million dollars in preventabic interest, ope-rating and replacement fuel costs.
I feel there is a nocessity for the Atomic Safety Board Licensing hearings however, certain anti-nuclear power groups use j                   t h e r. as delaying tactics.       Therefore the Hearings need to be expedited in the following manner.
I feel there is a nocessity for the Atomic Safety Board Licensing hearings however, certain anti-nuclear power groups use j
t h e r.
as delaying tactics.
Therefore the Hearings need to be expedited in the following manner.
i
i


i       f*   ,,
i f*
j        ..      =                   ..                      ..
=
November 2,                   1984 Page 2
j November 2, 1984 Page 2 1.
: 1. Create alternate ASLB hearings.
Create alternate ASLB hearings.
                    .-      2. Create deadlines for submitting all safety concerns. Any subs,equent concern.would be submitted to the NRC for investi-gation.                                          .
2.
                                                                      ~
Create deadlines for submitting all safety concerns.
3.- Inform your colleagues with TU constituents of the conse-quences of licensing delays.
Any subs,equent concern.would be submitted to the NRC for investi-gation.
~
3.-
Inform your colleagues with TU constituents of the conse-quences of licensing delays.
I would deeply appreciate your response on this issue and thank you for your concern.
I would deeply appreciate your response on this issue and thank you for your concern.
Thank You Sincerely Yours,                                                                ,
Thank You Sincerely Yours,
                      /Haydena/G. AA
/
                                                                                                            ~
a/ AA
~
Hayden G.
Haby, Jr.
Haby, Jr.
403 Cherokee Pecan Plantation                                                         .,
403 Cherokee Pecan Plantation Granbury, Texas 76048
Granbury, Texas 76048
'W
                            'W
\\
!                                                                                          \
l
r l
-s r
,                                                                          .              -s I.                                 - _ _ _ . - - _ _ . _ _ _ - , _ . _      -
I.


e                                                                                                         ,
e
        , QJ a ~ ' >R RE E =       d     %
, QJ a ~ '
      - '- \ ''               #e                       UNITED STATES
>R RE E =
            '' E
d
                              ~h
'- \\ ''
                        ~
#e UNITED STATES
NUCLEAR REGULATORY COMMISSION i
'' E
h             ;$                    WASHINGTON, D. C. 20555 t
~ h NUCLEAR REGULATORY COMMISSION
s.,.....J i                                       EDO PRINCIPAL CORRESPONDENCE CONTROL FROM:                                       DUE: 12/07/84         EDO CONTROL: 000130 DOC DT: 11/15/84 SEN. LLOYD BENTSEN                                             FINAL REPLY:
~
h WASHINGTON, D. C. 20555 i
t s.,.....J i
EDO PRINCIPAL CORRESPONDENCE CONTROL FROM:
DUE: 12/07/84 EDO CONTROL: 000130 DOC DT: 11/15/84 SEN. LLOYD BENTSEN FINAL REPLY:
TO:
TO:
KAMMERER FOR SIGNATURE OF:                           **    GREEN       **    SECY NO: 84-2001 EXECUTIVE DIRECTOR DESC:                                                             ROUTING:
KAMMERER FOR SIGNATURE OF:
ENCLOSES LTR FM HAYDEN G. HABY, JR.RE CONCERNS                   RMARTIN ABOUT DELAYS IN COMANCHE PEAK LICENSING PROCESS                 GCUNNINGHAM ASSIGNED TO: NR51                 DATE: 11/21/84 CONTACT: DENTON                                                                             l SPECIAL INSTRUCTIONS OR REMARKS:                                                                 )
GREEN SECY NO: 84-2001 EXECUTIVE DIRECTOR DESC:
l REPLY TO AUSTIN, TEXAS OFFICE Received flRR:     11/23/84 contact: Eisenhut- #1 -t                 hg cc: Case /Denton PPAS l
ROUTING:
                                                                                                        ?
ENCLOSES LTR FM HAYDEN G. HABY, JR.RE CONCERNS RMARTIN ABOUT DELAYS IN COMANCHE PEAK LICENSING PROCESS GCUNNINGHAM ASSIGNED TO: NR51 DATE: 11/21/84 CONTACT: DENTON l
SPECIAL INSTRUCTIONS OR REMARKS:
)
l REPLY TO AUSTIN, TEXAS OFFICE Received flRR:
11/23/84 contact: Eisenhut- #1 -t hg cc: Case /Denton PPAS l
?
l r
l r


l
l
:p,. _ .-_ .           ~ %       - - ~.-J     - ' si -- ~ L-         .,~.. - --         _~ --                                   - - - ~ ~
:p,. _.-_.
v,. u. r.- r.:..
~ %
: q. v. a. - -:6.-
- - ~.-J si -- ~ L-
                                                                                      ....                   . .,,_ -~~- Sen Lloyd Bentsen -
.,~.. - --
i I    -
_~ --
i'O.u.NER:
..,,_ -~~- Sen Lloyd Bentsen -
            ~
- - - ~ ~
84$001                                                                   ' LOGGING DATE:
,.. - q. v.. -....
11/20/84
v u r. r.:..
..                                                                      c....,._             .._ . . . _ . . .
a
: a. :: .       a _ . .- : : . . . n r.s.
-:6.-
J
i i'O.u.NER:
              , r- . n . C~~2'" -.r. ...
84$001
n.12 E00
' LOGGING DATE:
      .        P AUNOE                                               Sen Lloyd Bentsen, Const Ref AFFILIATION:                                     .Hayden G. Haby l             L:. ::.R DATE:'                                     11/15/84                     FILE CODE:
11/20/84 I
:              ADDRESSEE:                                         OCA
~
c....,._
: a. ::.
a _..- : :... n r.s.
J n.12 C~~2'" -.r....
, r-. n.
E00 P
AUNOE Sen Lloyd Bentsen, Const Ref AFFILIATION:
.Hayden G. Haby l
L:. ::.R DATE:'
11/15/84 FILE CODE:
ADDRESSEE:
OCA


==SUBJECT:==
==SUBJECT:==
Expresses concern about the delays in the Comanche Peake lic process ACTION:
Expresses concern about the delays in the Comanche Peake lic process ACTION:
Direct Reply... Suspense.. .Dec 3 DlSTRIBUTION:                                       OCA to Ack tec'd Date. . . .ctf) 0.M.I SPECIAL HANDLING.           -                      None                                                Time . . . . .               . . . . . .hw
Direct Reply... Suspense...Dec 3 DlSTRIBUTION:
                                                                                                                                            .wm. b. 1 SIGNATilP.E DATE:                                                               FOR THE C0KMISSION:               Billie
OCA to Ack tec'd ctf) 0.M.I
                              '%=-
. m. b. 1......hw Date....
g- .._q
SPECIAL HANDLING.
None Time.....
w SIGNATilP.E DATE:
FOR THE C0KMISSION:
Billie
'%=-
g-
.._q


s e
e s
  ,    ,i $LL,0 d BENTSEPS                                                                     couurrrars TEuaQ                                                                 FINANCE ENVIRONMENT AND PUBUC WORKS
,i $LL,0 d BENTSEPS couurrrars TEuaQ FINANCE ENVIRONMENT AND PUBUC WORKS JOINT ECONOMIC 3Cnifeb Sfales Senale WASHINGTON, D.C. 20510 November 15, 1984 Mr. Carlton C. Kammerer, Director l
          .                                                                                  JOINT ECONOMIC 3Cnifeb Sfales Senale WASHINGTON, D.C. 20510 November 15, 1984
Office of Congressional Affairs l
;                                Mr. Carlton C. Kammerer, Director l                                 Office of Congressional Affairs l                                 The United States Nuclear Regulatory Commission 1717 H Street, N.W.
The United States Nuclear Regulatory Commission 1717 H Street, N.W.
Washington, D.C. 20555
Washington, D.C.
20555


==Dear Mr. Kammerer:==
==Dear Mr. Kammerer:==
 
Enclosed for your review is a copy of a letter I have received from Mr. Hayden G. Haby, Jr. of Granbury, Texas.
Enclosed for your review is a copy of a letter I have received from Mr. Hayden G. Haby, Jr. of Granbury, Texas. I would certainly appreciate your sending me any pertinent information that you might have in this regard.
I would certainly appreciate your sending me any pertinent information that you might have in this regard.
Thank you for your assistance.
Thank you for your assistance.
Sincerely, yd     entsen Encl sure PLEASE REPLY TO:
Sincerely, yd entsen Encl sure PLEASE REPLY TO:
912 Federal Building Austin, Texas 78701 l
912 Federal Building Austin, Texas 78701 l
J
J


  .          . $-            ?
?
* 4 November 2,   1984                                   j The Honorable Lloyd Bentson United States Senate 703 Hart Senate Office Building Washington, D.C.20510 Dear Mr. Bentson I would like to express my deep concern about the delays in the Comanche Peak Steam Electric Station Licensing Process which
4 November 2, 1984 j
,                  only result in higher consumer cost and unavailable electrical reserves.
The Honorable Lloyd Bentson United States Senate 703 Hart Senate Office Building Washington, D.C.20510 Dear Mr. Bentson I would like to express my deep concern about the delays in the Comanche Peak Steam Electric Station Licensing Process which only result in higher consumer cost and unavailable electrical reserves.
;                      . The Comanche Peak Plant is practically ready to load fuel and commence testing to begin commercial operation. The follo-wing are facts concerning the Texas Utilities (TU) system.
. The Comanche Peak Plant is practically ready to load fuel and commence testing to begin commercial operation.
: 1. The TU system reached a peak     load of 15265 Megawatts (MW) on August 29, 1984 exceeding the 1983 estimate of 14300 MW. The operating reserve decreased to 2652 MW or 14.7% based on the TU System capacity of 17890 MW. However, the TU Sys-tem's only had an actual 6 x reserve capacity on August 29 due to unanticipated plant outages.
The follo-wing are facts concerning the Texas Utilities (TU) system.
: 2. The TU System did not have an alternate source of power during the load peak.
1.
: 3. The 1985 summer peak is expected to be 8.8k greater than the 1983 peak. A 16608 MW peak would leave 1282 MW or 7.2 x reserve. The Comanche Peak Unit One could provide an addi-                   ,
The TU system reached a peak load of 15265 Megawatts (MW) on August 29, 1984 exceeding the 1983 estimate of 14300 MW.
tional 1139 MW.
The operating reserve decreased to 2652 MW or 14.7% based on the TU System capacity of 17890 MW.
Depending on the TU System total capacity is some what risky and                     ,
However, the TU Sys-tem's only had an actual 6 x reserve capacity on August 29 due to unanticipated plant outages.
idealistic due unexpected generating loss, excessive load growth                     ,
2.
.                  and natural gas curtailment. The consequences of the slightest                     '
The TU System did not have an alternate source of power during the load peak.
unexpected circumstance can be a system brownout causing a loss of industrial production and residential service.
3.
The 1985 summer peak is expected to be 8.8k greater than the 1983 peak. A 16608 MW peak would leave 1282 MW or 7.2 x reserve.
The Comanche Peak Unit One could provide an addi-tional 1139 MW.
Depending on the TU System total capacity is some what risky and idealistic due unexpected generating loss, excessive load growth and natural gas curtailment.
The consequences of the slightest unexpected circumstance can be a system brownout causing a loss of industrial production and residential service.
Each day of delay at Comanche Peak cost the Utility and consumer about one million dollars in preventable interest, ope-rating and replacement fuel costs.
Each day of delay at Comanche Peak cost the Utility and consumer about one million dollars in preventable interest, ope-rating and replacement fuel costs.
I feel there is a necessity for the Atomic Safety Board Licensing hearings however, certain anti-nuclear power groups use them as delaying tactics. Therefore the Hearings need to be                             ,
I feel there is a necessity for the Atomic Safety Board Licensing hearings however, certain anti-nuclear power groups use them as delaying tactics.
expedited in the following manner.
Therefore the Hearings need to be expedited in the following manner.


r'
r'
      ..    . e j       ~
. e j
          .>-s-             g >s
~
  ~, . i ;-i '
.>-s-g
November 2, 1984 Page 2
>s
: 1. Create alternate ASLB hearings.
~,. i ;-i '
: 2. Create deadlines for submitting all safety concerns. Any subsequent concern would be submitted to the NRC for investi-gation.
November 2, 1984 Page 2 1.
: 3. Inform your colleagues with TU constituents of the conse-quances of licensing delays.
Create alternate ASLB hearings.
2.
Create deadlines for submitting all safety concerns.
Any subsequent concern would be submitted to the NRC for investi-gation.
3.
Inform your colleagues with TU constituents of the conse-quances of licensing delays.
I would deeply appreciate your response on this issue and thank you for your concern.
I would deeply appreciate your response on this issue and thank you for your concern.
Thank You Sincerely Yours,
Thank You Sincerely Yours,
                  /     a/ AA Hayden G. Haby, Jr.
/
a/ AA Hayden G.
Haby, Jr.
403 Cherokee Pecan Plantation Granbury, Texas 76048 t
403 Cherokee Pecan Plantation Granbury, Texas 76048 t
                                                                                        .q
.q
  .}}
.}}

Latest revision as of 04:44, 13 December 2024

Forwards Constituent Hg Haby Re Delays in Facility Licensing Process Resulting in Higher Costs
ML20101J187
Person / Time
Site: Comanche Peak  
Issue date: 11/15/1984
From: Bentsen L
SENATE
To: Kammerer C
NRC OFFICE OF CONGRESSIONAL AFFAIRS (OCA)
Shared Package
ML20101J179 List:
References
NUDOCS 8412280451
Download: ML20101J187 (8)


Text

r -- c, egEENT5EN cI***stTEv a f*

Ttx,a rms. Net.

~

guy,poNugNT At 3 ruhic woaxs e

s somT ECONOMIC

?JCnifeb Sinica Senab WASHINGTON. D.C. 20$10 November 15, 1984 Mr. Carlton C. Kammerer, Director Office of Congressi'onal Affairs

'The United States Nuclear Regulatory Commission, 1717 H~ Street, N.W.

Washington,"D.C._ 20555

Dear Mr. Kammerer:

Enclosed for your review is a copy of a letter I have received from Mr. Hayden G. Haby, Jr. of Granbury, Texas.

I would certainly appreciate your sending me any pertinent information that you might have in this regard.

Thank you for your assistance.

Sincerely, n.

~C.

.,2 ~

/

i,.

(

Lloyd Bentsen

-a /

Encl'osure PLEASE REPLY TO:

912 Federal Building Austin, Texas 78701 l

l I

1 OS h h5 PH pm

w

./'

,y g

'L November 2, 1984 The Honorable Lloyd Bentson United States Senate

- 703 Hart Senate Office. Building Washington, D.C.

20510 Dear Mr. Bentson I would 1-ike to ex, press my deep concern about the delays in the Comanche Peak Steam Electric Station Licensing Process which only result in higher consumer cost and unavailable electrical reserves.

The Comanche Peak Plant is practically ready to load fuel and commence testing to begin commercial operation.

The,follo-wing are facts concerning the Texas Utilities (TU) system.

1.

The TU system reached a peak load of 15265 Megawatts (MW)_on August 29, 1984 exceeding the 1983 estimate of 14300 f

MW The operating reserve decreased to 2652 MW or 14.7% based s

on the TU System capacity of 17890 MW.

However, the TU Sys- ~

tem's only had an actual 6 x reserve capacity on. August 29 due to unanticipated plant outages.

2.

The TU System did not have an alternate source of power during the load peak.

3.

The 1985 summer peak is expected to be 8.8% greater than the 1983 peak. A 16608 MW peak would leave 1282 MW or 7.2 x r e r.e r v e.

The Comanche Peak Unit One could provide an addi-tional 1139 MW.

Depending on the TU System total capacity is some what risky and idealistic due unexpected generating loss, excessive load growth cnd natural gas curtailment.

The consequences of the slightest unexpected circumstance can be a system brownout causing a loss of industrial production and residential service.

Each day of delay at Conanche Peak cost the Utility and consumer about one million dollars in preventabic interest, ope-rating and replacement fuel costs.

I feel there is a nocessity for the Atomic Safety Board Licensing hearings however, certain anti-nuclear power groups use j

t h e r.

as delaying tactics.

Therefore the Hearings need to be expedited in the following manner.

i

i f*

=

j November 2, 1984 Page 2 1.

Create alternate ASLB hearings.

2.

Create deadlines for submitting all safety concerns.

Any subs,equent concern.would be submitted to the NRC for investi-gation.

~

3.-

Inform your colleagues with TU constituents of the conse-quences of licensing delays.

I would deeply appreciate your response on this issue and thank you for your concern.

Thank You Sincerely Yours,

/

a/ AA

~

Hayden G.

Haby, Jr.

403 Cherokee Pecan Plantation Granbury, Texas 76048

'W

\\

l

-s r

I.

e

, QJ a ~ '

>R RE E =

d

'- \\

  1. e UNITED STATES

E

~ h NUCLEAR REGULATORY COMMISSION

~

h WASHINGTON, D. C. 20555 i

t s.,.....J i

EDO PRINCIPAL CORRESPONDENCE CONTROL FROM:

DUE: 12/07/84 EDO CONTROL: 000130 DOC DT: 11/15/84 SEN. LLOYD BENTSEN FINAL REPLY:

TO:

KAMMERER FOR SIGNATURE OF:

GREEN SECY NO: 84-2001 EXECUTIVE DIRECTOR DESC:

ROUTING:

ENCLOSES LTR FM HAYDEN G. HABY, JR.RE CONCERNS RMARTIN ABOUT DELAYS IN COMANCHE PEAK LICENSING PROCESS GCUNNINGHAM ASSIGNED TO: NR51 DATE: 11/21/84 CONTACT: DENTON l

SPECIAL INSTRUCTIONS OR REMARKS:

)

l REPLY TO AUSTIN, TEXAS OFFICE Received flRR:

11/23/84 contact: Eisenhut- #1 -t hg cc: Case /Denton PPAS l

?

l r

l

p,. _.-_.

~ %

- - ~.-J si -- ~ L-

.,~.. - --

_~ --

..,,_ -~~- Sen Lloyd Bentsen -

- - - ~ ~

,.. - q. v.. -....

v u r. r.:..

a

-:6.-

i i'O.u.NER:

84$001

' LOGGING DATE:

11/20/84 I

~

c....,._

a. ::.

a _..- : :... n r.s.

J n.12 C~~2'" -.r....

, r-. n.

E00 P

AUNOE Sen Lloyd Bentsen, Const Ref AFFILIATION:

.Hayden G. Haby l

L:. ::.R DATE:'

11/15/84 FILE CODE:

ADDRESSEE:

OCA

SUBJECT:

Expresses concern about the delays in the Comanche Peake lic process ACTION:

Direct Reply... Suspense...Dec 3 DlSTRIBUTION:

OCA to Ack tec'd ctf) 0.M.I

. m. b. 1......hw Date....

SPECIAL HANDLING.

None Time.....

w SIGNATilP.E DATE:

FOR THE C0KMISSION:

Billie

'%=-

g-

.._q

e s

,i $LL,0 d BENTSEPS couurrrars TEuaQ FINANCE ENVIRONMENT AND PUBUC WORKS JOINT ECONOMIC 3Cnifeb Sfales Senale WASHINGTON, D.C. 20510 November 15, 1984 Mr. Carlton C. Kammerer, Director l

Office of Congressional Affairs l

The United States Nuclear Regulatory Commission 1717 H Street, N.W.

Washington, D.C.

20555

Dear Mr. Kammerer:

Enclosed for your review is a copy of a letter I have received from Mr. Hayden G. Haby, Jr. of Granbury, Texas.

I would certainly appreciate your sending me any pertinent information that you might have in this regard.

Thank you for your assistance.

Sincerely, yd entsen Encl sure PLEASE REPLY TO:

912 Federal Building Austin, Texas 78701 l

J

?

4 November 2, 1984 j

The Honorable Lloyd Bentson United States Senate 703 Hart Senate Office Building Washington, D.C.20510 Dear Mr. Bentson I would like to express my deep concern about the delays in the Comanche Peak Steam Electric Station Licensing Process which only result in higher consumer cost and unavailable electrical reserves.

. The Comanche Peak Plant is practically ready to load fuel and commence testing to begin commercial operation.

The follo-wing are facts concerning the Texas Utilities (TU) system.

1.

The TU system reached a peak load of 15265 Megawatts (MW) on August 29, 1984 exceeding the 1983 estimate of 14300 MW.

The operating reserve decreased to 2652 MW or 14.7% based on the TU System capacity of 17890 MW.

However, the TU Sys-tem's only had an actual 6 x reserve capacity on August 29 due to unanticipated plant outages.

2.

The TU System did not have an alternate source of power during the load peak.

3.

The 1985 summer peak is expected to be 8.8k greater than the 1983 peak. A 16608 MW peak would leave 1282 MW or 7.2 x reserve.

The Comanche Peak Unit One could provide an addi-tional 1139 MW.

Depending on the TU System total capacity is some what risky and idealistic due unexpected generating loss, excessive load growth and natural gas curtailment.

The consequences of the slightest unexpected circumstance can be a system brownout causing a loss of industrial production and residential service.

Each day of delay at Comanche Peak cost the Utility and consumer about one million dollars in preventable interest, ope-rating and replacement fuel costs.

I feel there is a necessity for the Atomic Safety Board Licensing hearings however, certain anti-nuclear power groups use them as delaying tactics.

Therefore the Hearings need to be expedited in the following manner.

r'

. e j

~

.>-s-g

>s

~,. i ;-i '

November 2, 1984 Page 2 1.

Create alternate ASLB hearings.

2.

Create deadlines for submitting all safety concerns.

Any subsequent concern would be submitted to the NRC for investi-gation.

3.

Inform your colleagues with TU constituents of the conse-quances of licensing delays.

I would deeply appreciate your response on this issue and thank you for your concern.

Thank You Sincerely Yours,

/

a/ AA Hayden G.

Haby, Jr.

403 Cherokee Pecan Plantation Granbury, Texas 76048 t