ENS 40172: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 09/18/2003 21:11 EDT
| event date = 09/18/2003 21:11 EDT
| last update date = 09/20/2003
| last update date = 09/20/2003
| title = Loss Of Emergency Siren Capability Due To Adverse Weather Conditions
| title = Loss of Emergency Siren Capability Due to Adverse Weather Conditions
| event text = Due to the effects of severe weather related to Hurricane Isabel, local power outages have resulted in an excessive number of sirens within the Salem/Hope Creek 10-mile Emergency Protection Zone (EPZ) being unavailable. At 21:11 on September 18, 2003, 29 offsite sirens were unavailable (22 in Delaware and 7 located in New Jersey). As of 22:11, some sirens have been restored, but there are still 14 unavailable in Delaware and 7 unavailable in New Jersey. It is likely that the functionality of the EPZ sirens will continue to change due to the ongoing severe weather. Sirens will be recovered when power is restored.
| event text = Due to the effects of severe weather related to Hurricane Isabel, local power outages have resulted in an excessive number of sirens within the Salem/Hope Creek 10-mile Emergency Protection Zone (EPZ) being unavailable. At 21:11 on September 18, 2003, 29 offsite sirens were unavailable (22 in Delaware and 7 located in New Jersey). As of 22:11, some sirens have been restored, but there are still 14 unavailable in Delaware and 7 unavailable in New Jersey. It is likely that the functionality of the EPZ sirens will continue to change due to the ongoing severe weather. Sirens will be recovered when power is restored.
This notification is being for both Salem Generating Station and Hope Creek Generating Station pursuant to 10CFR50.72(b)(3)(xiii) as a major loss of emergency assessment, offsite response, or communication capability. Salem Units 1 and 2 are operating at 100% power with all safety related equipment operable.
This notification is being for both Salem Generating Station and Hope Creek Generating Station pursuant to 10CFR50.72(b)(3)(xiii) as a major loss of emergency assessment, offsite response, or communication capability. Salem Units 1 and 2 are operating at 100% power with all safety related equipment operable.

Latest revision as of 22:25, 1 March 2018

ENS 40172 +/-
Where
Hope Creek PSEG icon.png
New Jersey (NRC Region 1)
Reporting
10 CFR 50.72(b)(3)(xiii), Loss of Emergency Preparedness
Time - Person (Reporting Time:+-0.57 h-0.0238 days <br />-0.00339 weeks <br />-7.80786e-4 months <br />)
Opened: Tom Fowler
00:37 Sep 19, 2003
NRC Officer: Steve Sandin
Last Updated: Sep 20, 2003
40172 - NRC Website