| event date = 10/14/2007 02:00 EST | | event date = 10/14/2007 02:00 EST | ||
| last update date = 12/12/2007 | | last update date = 12/12/2007 | ||
| title = Inadvertent Actuation | | title = Inadvertent Actuation of Emergency Diesel Generator | ||
| event text = This 60-day optional telephone notification as allowed by 10 CFR 50.73(a)(1) is being made in lieu of an LER submittal. This notification is made pursuant to the reporting requirements specified in 10 CFR50.73(a)(2)(iv)(A) for an invalid actuation of one of the systems listed in 10 CFR 50.73(a)(2)(iv)(B). | | event text = This 60-day optional telephone notification as allowed by 10 CFR 50.73(a)(1) is being made in lieu of an LER submittal. This notification is made pursuant to the reporting requirements specified in 10 CFR50.73(a)(2)(iv)(A) for an invalid actuation of one of the systems listed in 10 CFR 50.73(a)(2)(iv)(B). | ||
On October 14, 2007, at approximately 0200 hours EST with the plant in Mode 5, Refueling, while performing ECCS Start and Load Reject surveillance testing on Emergency Diesel Generator (EDG) 14, the EDG unexpectedly auto-started. Investigation revealed that the auto-start was caused by a faulty test switch. The test switch had been tested multiple times prior to performing the surveillance with no abnormalities noted. | On October 14, 2007, at approximately 0200 hours EST with the plant in Mode 5, Refueling, while performing ECCS Start and Load Reject surveillance testing on Emergency Diesel Generator (EDG) 14, the EDG unexpectedly auto-started. Investigation revealed that the auto-start was caused by a faulty test switch. The test switch had been tested multiple times prior to performing the surveillance with no abnormalities noted. |
Latest revision as of 22:15, 1 March 2018
Where | |
---|---|
Fermi ![]() Michigan (NRC Region 3) | |
Reporting | |
10 CFR 50.73(a)(1), Submit an LER, Invalid Actuation | |
Time - Person (Reporting Time:+1425.03 h59.376 days <br />8.482 weeks <br />1.952 months <br />) | |
Opened: | Rodney Johnson 17:02 Dec 12, 2007 |
NRC Officer: | Joe O'Hara |
Last Updated: | Dec 12, 2007 |