ENS 48120: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by Mark Hawes) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 16: | Line 16: | ||
| event date = 07/19/2012 15:30 EDT | | event date = 07/19/2012 15:30 EDT | ||
| last update date = 07/19/2012 | | last update date = 07/19/2012 | ||
| title = Tech Spec Required Shutdown Due | | title = Tech Spec Required Shutdown Due to Inability to Restore Main Steam Isolation Automatic Actuation Logic and Actuation Relays within the Required Time | ||
| event text = At 1530 on July 19, 2012, operators commenced shutdown of DC Cook Unit 1 to comply with LCO 3.3.2, Condition I when the 6 hour time limit to complete Condition C Required Action could not be completed. | | event text = At 1530 on July 19, 2012, operators commenced shutdown of DC Cook Unit 1 to comply with LCO 3.3.2, Condition I when the 6 hour time limit to complete Condition C Required Action could not be completed. | ||
At 0734 on July 19, 2012, operators identified that power had been lost to two of four Steam Generator Stop Valve Dump Valves (Dump Valves) on one of the two trains. DC Cook entered LCO 3.3.2 Condition B for Function 4a, manual initiation: 'restore required channel or train to operable within 48 hours.' DC Cook also entered LCO 3.3.2 Condition C for Function 4b, automatic actuation logic and actuation relays: 'restore required channel or train to operable within 6 hours.' Power was restored to one Dump Valve which was then declared operable at 1030. Efforts continue to restore power to the remaining Dump Valve. | At 0734 on July 19, 2012, operators identified that power had been lost to two of four Steam Generator Stop Valve Dump Valves (Dump Valves) on one of the two trains. DC Cook entered LCO 3.3.2 Condition B for Function 4a, manual initiation: 'restore required channel or train to operable within 48 hours.' DC Cook also entered LCO 3.3.2 Condition C for Function 4b, automatic actuation logic and actuation relays: 'restore required channel or train to operable within 6 hours.' Power was restored to one Dump Valve which was then declared operable at 1030. Efforts continue to restore power to the remaining Dump Valve. |
Latest revision as of 22:03, 1 March 2018
Where | |
---|---|
Cook Michigan (NRC Region 3) | |
Reporting | |
10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown | |
Time - Person (Reporting Time:+-1.03 h-0.0429 days <br />-0.00613 weeks <br />-0.00141 months <br />) | |
Opened: | Kurt Beran 18:28 Jul 19, 2012 |
NRC Officer: | Donald Norwood |
Last Updated: | Jul 19, 2012 |
48120 - NRC Website
| |