The following information was provided by the licensee via email:
At 0159 EDT on 6-27-24, DC Cook Unit 2 commenced a controlled shutdown to address identified leakage through 2-QRV-251, CVCS [chemical and volume control system] charging pumps discharge flow control valve, valve packing. The leakage started at 2303 EDT on 6-26-24 and was determined to be greater than the 10 gallons per minute limit per technical specification 3.4.13 allowable leakage. The leakage was determined to not be repairable at power.
Per 10CFR 50.72(b)(2) this is a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> non-emergency report for Technical Specification required shutdown."
The NRC Resident Inspector was notified.
The following additional information was obtained from the licensee in accordance with Headquarters Operations Officers Report Guidance:
A normal shutdown is expected to be completed by 0900 EDT. There are no radiological releases. Unit 1 was not affected. There is no estimate for the time of the repairs.