ENS 49339: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by Mark Hawes)
 
(Created page by program invented by StriderTol)
 
Line 16: Line 16:
| event date = 09/11/2013 17:31 CDT
| event date = 09/11/2013 17:31 CDT
| last update date = 09/12/2013
| last update date = 09/12/2013
| title = Technical Specification Required Shutdown Due To Loss Of Cooling To Switchgear Rooms
| title = Technical Specification Required Shutdown Due to Loss of Cooling to Switchgear Rooms
| event text = Wolf Creek has commenced a plant shutdown in accordance with Technical Specifications.  The A Train Class 1E Electrical Equipment Air Conditioning unit was declared non-functional due to a possible failed compressor cylinder, as indicated by increased vibration.  This failure could prevent the unit from performing its required function over its required mission time, as required by Technical Specifications 3.8.4, 3.8.7, and 3.8.9.  The following safety related electrical equipment was declared inoperable:  4.16KV Bus NB01; 480 Volt AC buses NG01 and NG03; 120 Volt Instrument AC inverters and buses NN11, NN13, NN01 and NN03; 125 VDC chargers and buses NK11, NK13, NN01 and NN03.
| event text = Wolf Creek has commenced a plant shutdown in accordance with Technical Specifications.  The A Train Class 1E Electrical Equipment Air Conditioning unit was declared non-functional due to a possible failed compressor cylinder, as indicated by increased vibration.  This failure could prevent the unit from performing its required function over its required mission time, as required by Technical Specifications 3.8.4, 3.8.7, and 3.8.9.  The following safety related electrical equipment was declared inoperable:  4.16KV Bus NB01; 480 Volt AC buses NG01 and NG03; 120 Volt Instrument AC inverters and buses NN11, NN13, NN01 and NN03; 125 VDC chargers and buses NK11, NK13, NN01 and NN03.
Technical Specification 3.0.3 was entered at 1645 CDT on 9/11/2013 from Technical Specification 3.8.7 due to two out of four 120 VAC inverters (NN11 and NN13) being inoperable.  Plant shutdown to Mode 5 commenced at 1731 CDT.  The unit is currently at approximately 50% power.
Technical Specification 3.0.3 was entered at 1645 CDT on 9/11/2013 from Technical Specification 3.8.7 due to two out of four 120 VAC inverters (NN11 and NN13) being inoperable.  Plant shutdown to Mode 5 commenced at 1731 CDT.  The unit is currently at approximately 50% power.

Latest revision as of 22:00, 1 March 2018

ENS 49339 +/-
Where
Wolf Creek Wolf Creek Nuclear Operating Corporation icon.png
Kansas (NRC Region 4)
Reporting
10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown

10 CFR 50.72(b)(3)(iv)(A), System Actuation
Time - Person (Reporting Time:+-1.9 h-0.0792 days <br />-0.0113 weeks <br />-0.0026 months <br />)
Opened: Marcy Blow
20:37 Sep 11, 2013
NRC Officer: Mark Abramovitz
Last Updated: Sep 12, 2013
49339 - NRC Website
Loading map...