| event date = 01/02/2015 03:14 CST | | event date = 01/02/2015 03:14 CST | ||
| last update date = 01/02/2015 | | last update date = 01/02/2015 | ||
| title = Loss | | title = Loss of Meteorological Emergency Assessment Capability | ||
| event text = At 0314 [CST] on 01/02/2015, a partial loss of the 25KV Power Distribution Systems caused a loss of both the Primary and Backup Meteorological Towers at the Comanche Peak Nuclear Power Plant. This resulted in a major loss of emergency assessment capabilities in regard to meteorological conditions. | | event text = At 0314 [CST] on 01/02/2015, a partial loss of the 25KV Power Distribution Systems caused a loss of both the Primary and Backup Meteorological Towers at the Comanche Peak Nuclear Power Plant. This resulted in a major loss of emergency assessment capabilities in regard to meteorological conditions. | ||
The 25 KV Plant Support Power Loop feeds certain non-safety-related equipment and does not affect plant operation. | The 25 KV Plant Support Power Loop feeds certain non-safety-related equipment and does not affect plant operation. |
Latest revision as of 20:48, 1 March 2018
Where | |
---|---|
Comanche Peak Texas (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(3)(xiii), Loss of Emergency Preparedness | |
Time - Person (Reporting Time:+2.48 h0.103 days <br />0.0148 weeks <br />0.0034 months <br />) | |
Opened: | Danny Bradford 11:43 Jan 2, 2015 |
NRC Officer: | Vince Klco |
Last Updated: | Jan 2, 2015 |