Line 2: Line 2:
| number = ML20206B095
| number = ML20206B095
| issue date = 04/23/1999
| issue date = 04/23/1999
| title = Ack Receipt of 990325 Ltr Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-416/99-01 & NOV Dtd 990226.Reply Found to Be Responsive to Concerns Raised in Nov.Implementation of C/As Will Be Reviewed in Future Insps
| title = Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-416/99-01 & NOV .Reply Found to Be Responsive to Concerns Raised in Nov.Implementation of C/As Will Be Reviewed in Future Insps
| author name = Good G
| author name = Good G
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
| author affiliation = NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Line 11: Line 11:
| contact person =  
| contact person =  
| document report number = 50-416-99-01, 50-416-99-1, NUDOCS 9904290144
| document report number = 50-416-99-01, 50-416-99-1, NUDOCS 9904290144
| title reference date = 03-25-1999
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE
| document type = CORRESPONDENCE-LETTERS, OUTGOING CORRESPONDENCE
| page count = 5
| page count = 5
Line 18: Line 19:
=Text=
=Text=
{{#Wiki_filter:'
{{#Wiki_filter:'
        ,
,
    4    #* "*%                                     UNITED STATES
#* "*%
..    p             1                 NUCLEAR REGULATORY COMMISSION
UNITED STATES
      $                                               REGION IV
4
        *
p
                    e                         611 RYAN PLAZA DRIVE, sUlTE 400
1
          ,                                      ARUNGTON, texas 76011-8064
NUCLEAR REGULATORY COMMISSION
                                                      April 23,1999
..
                                                                                                            i
$
            William A. Eaton, Vice President
REGION IV
            Operations - Grand Gulf Nuclear Station
*
            Entergy Operations, Inc.
e
            P.O. Box 756
611 RYAN PLAZA DRIVE, sUlTE 400
            Port Gibson, Mississippi 39150
ARUNGTON, texas 76011-8064
            SUBJECT: NRC INSPECTION REPORT 50-416/99-01
,
                    Thank you for your letter of March 25,1999, in response to our letter and Notice of
April 23,1999
            Violation dated February 26,1999. We have reviewed your reply and find it responsive to the
i
            concern raised in our Notice of Violation. We will review the implementation of your corrective
William A. Eaton, Vice President
            actions during a future inspection to determine that full compliance has been achieved and will
Operations - Grand Gulf Nuclear Station
            be maintained.'
Entergy Operations, Inc.
                                                          Sincerely,
P.O. Box 756
                                                          j
Port Gibson, Mississippi 39150
                                                                  '
SUBJECT: NRC INSPECTION REPORT 50-416/99-01
                                                                        N                                  !
Thank you for your letter of March 25,1999, in response to our letter and Notice of
                                                          Gail M. Good, Chief
Violation dated February 26,1999. We have reviewed your reply and find it responsive to the
                                                          Plant Support Branch                               l
concern raised in our Notice of Violation. We will review the implementation of your corrective
                                                          Division of Reactor Safety                 f     i
actions during a future inspection to determine that full compliance has been achieved and will
            Docket No.: 50-416
be maintained.'
            License No.: NPF-29
Sincerely,
            cc:                                                                                             ;
N
                                                                                                            '
'
            Executive Vice President
j
              and Chief Operating Officer                                                                   i
Gail M. Good, Chief
            Entergy Operations, Inc.
Plant Support Branch
            P.O. Box 31995 -
Division of Reactor Safety
            Jackson, Mississippi 39286-1995
f
            Wise, Carter, Chilt! & Caraway
Docket No.: 50-416
            P.O. Box 651
License No.: NPF-29
            Jackson, Mississippi 39205
cc:
                                                                                                            4
;
                                                    "
Executive Vice President
                    9904290144 990423'
'
                    PDR   ADOCK 05000416
i
                    G                     PDR
and Chief Operating Officer
Entergy Operations, Inc.
P.O. Box 31995 -
Jackson, Mississippi 39286-1995
Wise, Carter, Chilt! & Caraway
P.O. Box 651
Jackson, Mississippi 39205
4
9904290144 990423'
"
PDR
ADOCK 05000416
G
PDR


  .
.
    *  ,
l
l
      .
*
                                                      ,
,
.
,
..
..
            Entergy Operations, Inc.             -2-
Entergy Operations, Inc.
            Winston & Strawn
-2-
l           1400 L Street, N.W. - 12th Floor
Winston & Strawn
            Washington, D.C. 20005-3502
l
            Sam Mabry, Director
1400 L Street, N.W. - 12th Floor
            Division of Solid Waste Management
Washington, D.C. 20005-3502
Sam Mabry, Director
Division of Solid Waste Management
Mississippi Department of Natural
,
,
            Mississippi Department of Natural
Resources
              Resources
P.O. Box 10385
            P.O. Box 10385
Jackson, Mississippi 39209
            Jackson, Mississippi 39209
President
            President
Claiborne County Board of Supervisors
            Claiborne County Board of Supervisors
Port Gibson, Mississippi 39150
            Port Gibson, Mississippi 39150
Manager of Operations
            Manager of Operations
Bechtel Power Corporation
            Bechtel Power Corporation
P.O. Box 2166
            P.O. Box 2166
Houston, Texas 77252-2166
            Houston, Texas 77252-2166
General Manager
            General Manager
Grand Gulf Nuclear Station
            Grand Gulf Nuclear Station                     i
i
            Entergy Operations, Inc.                       l
Entergy Operations, Inc.
            P.O. Box 756
P.O. Box 756
            Port Gibson, Mississippi 39150
Port Gibson, Mississippi 39150
            The Honorable William J. Guste, Jr.
The Honorable William J. Guste, Jr.
            Attorney General
Attorney General
            Department of Justice
Department of Justice
            State of Louisiana
State of Louisiana
            P.O. Box 94005
P.O. Box 94005
            Baton Rouge, Louisiana 70804-9005
Baton Rouge, Louisiana 70804-9005
            Office of the Governor
Office of the Governor
          . State of Mississippi
. State of Mississippi
          . Jackson, Mississippi 39201
. Jackson, Mississippi 39201
            Mike Moore, Attomey General
Mike Moore, Attomey General
            Frank Spencer, Asst. Attorney General
Frank Spencer, Asst. Attorney General
            State of Mississippi                         j
State of Mississippi
          . P.O. Box 22947                               :
j
            Jackson, Mississippi 39225                   {
. P.O. Box 22947
            Dr. F. E. Thompson, Jr.
:
            State Health Officer
Jackson, Mississippi 39225
            State Board of Health                         )
{
            P.O. Box 1700                                 l
Dr. F. E. Thompson, Jr.
            Jackson, Mississ?ppi 39205 -                 )
State Health Officer
                                                          !
State Board of Health
                                                        '
)
                                                          I
P.O. Box 1700
                                                          !
l
                                                          '
Jackson, Mississ?ppi 39205 -
                                                          i
)
'
I
!
'
i


r .s
r .s
    -- .
-- .
          .
.
                                                  E
E
e
e
              Entergy Operations, Inc.         -3-
Entergy Operations, Inc.
              Robert W. Goff, Director
-3-
              State Liaison Officer
Robert W. Goff, Director
            ' Division of Radiation Health
State Liaison Officer
              Mississippi Department of Health
' Division of Radiation Health
              P.O. Box 1700
Mississippi Department of Health
            ' Jackson, Mississippi 39215-1700
P.O. Box 1700
              Vice President                         i
' Jackson, Mississippi 39215-1700
              Operations Support                     l
Vice President
              Entergy Operations, Inc.
i
              P.O. Box 31995
Operations Support
              Jackson, Mississippi 39286-1995
Entergy Operations, Inc.
              Director, Nuclear Safety
P.O. Box 31995
              and Regulatory Affairs
Jackson, Mississippi 39286-1995
              Entergy Operations, Inc.
Director, Nuclear Safety
              P.O. Box 756                           :
and Regulatory Affairs
              Port Gibson, Mississippi 39150
Entergy Operations, Inc.
              Vice President, Operations
P.O. Box 756
              Grand Gulf Nuclear Station
Port Gibson, Mississippi 39150
              Entergy Operations, Inc.
Vice President, Operations
              P.O. Box 756
Grand Gulf Nuclear Station
              Port Gibson, Mississippi 39150
Entergy Operations, Inc.
                                                    l
P.O. Box 756
Port Gibson, Mississippi 39150


    <
<
        ,
,
      a                                                                                                                       ,
a
  ,s-
,
            Entergy Operations, Inc                                   -4-
,s-
            DISTRIBUTION w/ copy of licensee's letter dated March 25.1999:
Entergy Operations, Inc
          ,0MB(HioS);f
-4-
            Rsgional Administrator
DISTRIBUTION w/ copy of licensee's letter dated March 25.1999:
            Senior Resident inspector (River Bend) -
,0MB(HioS);f
          ' DRP Director
Rsgional Administrator
            DRS-PSB
Senior Resident inspector (River Bend) -
            Branch Chief (DRP/4)
' DRP Director
            Project Engineer (DRP/$)
DRS-PSB
            Branch Chief (DRP/TSS)
Branch Chief (DRP/4)
            Senior Resident inspector (Grand Gulf)
Project Engineer (DRP/$)
            MIS System
Branch Chief (DRP/TSS)
            RIV File -
Senior Resident inspector (Grand Gulf)
MIS System
RIV File -
l
l
            DRS Action item File (98-G-0043)(Goines)
DRS Action item File (98-G-0043)(Goines)
1
1
                                          us0004
us0004
DOCUMENT NAME: R:(GG\\GG901AK.MPS
)
,
,
            DOCUMENT NAME: R:(GG\GG901AK.MPS                                                                                    )
To recohn oopy of document, andlesto in box: "C" = Copy without enclosures *E" = Copy with enclosuree *N" = No copy
            To recohn oopy of document, andlesto in box: "C" = Copy without enclosures *E" = Copy with enclosuree *N" = No copy
RIV:PSB
            RIV:PSB               E     C:DRS\PSB
E
                                                                '
C:DRS\\PSB
            MPShannon:nhM(lk GMGood (Mb
MPShannon:nhM(lk GMGood (Mb
            04/ L, /99         W 04/ (d99
'
                                                      OFFICIAL RECORD COPY
04/ L, /99
W
04/ (d99
OFFICIAL RECORD COPY
f
f
!                   .
!
.


  -
-
      .
.
    .
.
.
.
        Entergy Operations, Inc.                                     -4-
Entergy Operations, Inc.
        DISTRIBUTION w/coov of licensee's letter dated March 25.1999:
-4-
        DMB (IE06)
DISTRIBUTION w/coov of licensee's letter dated March 25.1999:
        Regional Administrator
DMB (IE06)
        Senior Resident inspector (River Bend)
Regional Administrator
        DRP Director
Senior Resident inspector (River Bend)
        DRS-PSB
DRP Director
        Branch Chief (DRP/4) b)
DRS-PSB
        Project Engineer (DRP/A
Branch Chief (DRP/4) b)
        Branch Chief (DRP/TSS)
Project Engineer (DRP/A
        Senior Resident inspector (Grand Gulf)
Branch Chief (DRP/TSS)
        MIS System
Senior Resident inspector (Grand Gulf)
        RIV File
MIS System
        DRS Action item File (98-G-0043)(Goines)
RIV File
        DOCUMENT NAME: R:\_GG\GG901AK.MPS
DRS Action item File (98-G-0043)(Goines)
        To receive copy of document. Indicate in box: 'C' = Copy without enclosures "E" = Copy with enclosures 'N" = No copy
DOCUMENT NAME: R:\\_GG\\GG901AK.MPS
        ' 31V:PSB               E IC:DRS\PSB
To receive copy of document. Indicate in box: 'C' = Copy without enclosures "E" = Copy with enclosures 'N" = No copy
                                                              '
' 31V:PSB
          MPShannon:nhWP GMGood (MUe
E IC:DRS\\PSB
          04/[,/99           W         04/ (c;/99
MPShannon:nhWP GMGood (MUe
                                                    OFFICIAL RECORD COPY
'
04/[,/99
W
04/ (c;/99
OFFICIAL RECORD COPY


      '*
'* ./%
    =
=
            ./%
Ent:rgy oportti:ns. Inc.
          .
.
                                                                                              Ent:rgy oportti:ns. Inc.
'
        '         '
'
  ,'*                                                                                           o G son MS 39150
, ' *
                                                                                              Tel 601 337 6409
o G son MS 39150
                                                                                              Fax 601437 2795
Tel 601 337 6409
l                                                                                             William A. Eaton
Fax 601437 2795
                                                                                              Vice President
l
l                                                                                             Operatons
William A. Eaton
                                                                                              Grand GuH Nuclear Station
Vice President
                    March 25, 1999                                      f_@@@ly/@f
l
                                                                        y               '
Operatons
                                                                        ..  APR-lS99       g
Grand GuH Nuclear Station
                    U.S. Nuclear Regulatory Commission                     L
f_@@@ly/@f
                    Mail Station P1-37
March 25, 1999
                    Washington, D.C. 20555
y
                                                                      _
'
                                                                            REGIONIV
APR-lS99
                    Attention:           Document Control Desk
g
                    Subject:             Grand Gulf Nuclear Station
..
                                          Docket No. 50-416
U.S. Nuclear Regulatory Commission
                                          License No. NPF-29
L
                                          Reply To a Notice of Violation,50-416/9901-01, Violation of
Mail Station P1-37
                                          Technical Specification 5.7.3
Washington, D.C. 20555
                    Reference:           NRC Inspection Report No. 50-416/99-01, deted
_
                                          February 26,1999 (GNRI-99/00008)
REGIONIV
                    GNRO-99/00028
Attention:
                ,  Gentlemen:
Document Control Desk
                                                                                                                        '
Subject:
                    Entergy Operations, Inc. is hereby submitting the response to Notice of Violation
Grand Gulf Nuclear Station
                    50-416/9901-01 for Grand Gulf Nuclear Station. This Notice of Violation was
Docket No. 50-416
                    issued as a result of NRC Inspection 50-416/99-01 which was conducted during
License No. NPF-29
                    the period of February 1 through February 5,1999.
Reply To a Notice of Violation,50-416/9901-01, Violation of
                    Entergy Operations concurs that the overall findings of the inspection are valid. A
Technical Specification 5.7.3
                    program wi!! be implemented to ensure that accessible areas with radiation levels
Reference:
                    > 1000 mrem /hr, and not enclosed, have documentation to support the
NRC Inspection Report No. 50-416/99-01, deted
                    reasonable determination as outlined in GGNS Technical Specification 5.7.3.
February 26,1999 (GNRI-99/00008)
                    Should you have any questions or require clarification of our response, please
GNRO-99/00028
                    contact this office.
Gentlemen:
                    Yours truly,
,
                                Y5kW.
Entergy Operations, Inc. is hereby submitting the response to Notice of Violation
'
50-416/9901-01 for Grand Gulf Nuclear Station. This Notice of Violation was
issued as a result of NRC Inspection 50-416/99-01 which was conducted during
the period of February 1 through February 5,1999.
Entergy Operations concurs that the overall findings of the inspection are valid. A
program wi!! be implemented to ensure that accessible areas with radiation levels
> 1000 mrem /hr, and not enclosed, have documentation to support the
reasonable determination as outlined in GGNS Technical Specification 5.7.3.
Should you have any questions or require clarification of our response, please
contact this office.
Yours truly,Y5kW.
!
!
                    WAE/WKH/MJL
WAE/WKH/MJL
l                   attachment:           Response to Violation 50-416/9901-01
l
                    cc:                 - (See Next Page)
attachment:
Response to Violation 50-416/9901-01
cc:
- (See Next Page)
1
1
              % 3/OO N h'
% 3/OO N h'


e                                                                             ,
e
    *~   .
,
        .
* ~
      n
.
  .
.
              GNRO 99/00028
n
.
GNRO 99/00028
. Page 2 of 2
'
'
            . Page 2 of 2
Ms. J. L. Dixon-Herrity, GGNS Senior Resident (w/a)
              cc:          Ms. J. L. Dixon-Herrity, GGNS Senior Resident (w/a)
cc:
                          Mr. L. J. Smith (Wise Carter) (w/a)
Mr. L. J. Smith (Wise Carter) (w/a)
                          Mr. N. S. Reynolds (w/a)
Mr. N. S. Reynolds (w/a)
                          Mr. H. L. Thomas (w/o)
Mr. H. L. Thomas (w/o)
                          Mr. E. W. Merschoff (w/a)
Mr. E. W. Merschoff (w/a)
                          Regional Administrator
Regional Administrator
                          U.S. Nuclear Regulatory Commission
U.S. Nuclear Regulatory Commission
                          Region IV
Region IV
                          611 Ryan Plaza Drive, Suite 400
611 Ryan Plaza Drive, Suite 400
                          Arlington, TX 76011
Arlington, TX 76011
                                        .
.
                          Mr. S. P. Sekerak, Project Manager (w/2)             ;
Mr. S. P. Sekerak, Project Manager (w/2)
                          Office of Nuclear Reactor Regulation
;
                                                                                  l
Office of Nuclear Reactor Regulation
                          U.S. Nuclear Regulatory Commission
U.S. Nuclear Regulatory Commission
                                                                                  i
Mail Stop 13H3-D
                          Mail Stop 13H3-D
Washington, D.C. 20555
                          Washington, D.C. 20555
!
                                                                                ;!
1
                                                                                  1
.
      .                                                                         .
.
                                                                                  :
:
  m
m


[~
[~
'
'
      . <<   .
. <<
l -   u                                                                              Attachm:nt t3 GNRO-99/00028
.
          -
l -
        *
Attachm:nt t3 GNRO-99/00028
                                                                                                        Pag 31 cf 3
u
      .
-
    .
Pag 31 cf 3
                                              Notice of Violation 50-416/9901-01
*
              During a NRC inspection conducted on February 1-5,1999, one violation of NRC requirements
.
              was identified. In accordance with the " General Statement of Policy and Procedure for NRC
.
              Enforcement Actions," NUREG-1600, the violation is listed below:
Notice of Violation 50-416/9901-01
                      Technical Specification 5.7.2 requires, in part, that areas with radiation levels greater
During a NRC inspection conducted on February 1-5,1999, one violation of NRC requirements
                      than or equal to 1000 millirems per hour be provided with locked or continuously
was identified. In accordance with the " General Statement of Policy and Procedure for NRC
                      guarded doors to prevent unauthorized entry. Technical Specification 5.7.3 states, la
Enforcement Actions," NUREG-1600, the violation is listed below:
                      part, that for individual high radiation areas with radiation levels greater than 1000
Technical Specification 5.7.2 requires, in part, that areas with radiation levels greater
                      mrem per hour, accessible to personnel, that are located within large areas such as the
than or equal to 1000 millirems per hour be provided with locked or continuously
                      reactor containment, where no enclosure exists for purposes of locking, or that cannot
guarded doors to prevent unauthorized entry. Technical Specification 5.7.3 states, la
                      be continuously guarded, and where no enclosure can be reasonably constructed
part, that for individual high radiation areas with radiation levels greater than 1000
                      around the individual area, that individual area shall be barricaded and conspicuously
mrem per hour, accessible to personnel, that are located within large areas such as the
                      posted, and a flashing light shall be activated as a waming device.
reactor containment, where no enclosure exists for purposes of locking, or that cannot
                      Contrary to the above, on February 1,1999, NRC inspectors identified that an area
be continuously guarded, and where no enclosure can be reasonably constructed
                      with dose rates greater than 1000 millirems per hour was not provided with locked or
around the individual area, that individual area shall be barricaded and conspicuously
                      continuously guarded doors to prevent unauthorized entry. Specifically, the area
posted, and a flashing light shall be activated as a waming device.
                      around the spe,)t fuel pool cooling and cleanup heat exchangers, an area which is
Contrary to the above, on February 1,1999, NRC inspectors identified that an area
l                   . accessible to personnel and in which an enclosure reasonably could be constructed,
with dose rates greater than 1000 millirems per hour was not provided with locked or
continuously guarded doors to prevent unauthorized entry. Specifically, the area
around the spe,)t fuel pool cooling and cleanup heat exchangers, an area which is
l
. accessible to personnel and in which an enclosure reasonably could be constructed,
was not provided with locked or continuously guarded doors to prevent unauthorized
!
!
                      was not provided with locked or continuously guarded doors to prevent unauthorized
entry.
                      entry.
l
l
,
,
                                                                                                                    1
4
                                                                                                                    4
l                                                                                                                  !
l
l
!                                                                                                                  l
l
                                                                                                                    !
!
                                                                                                                    I
i
i
i
  i


  .-
.-
      ..
..
      .
.
                                                                                Attachm:nt to GNRO-99/00028
Attachm:nt to GNRO-99/00028
          +
.
      ;.
+
                                                                                                    P ge 2 cf 3
P ge 2 cf 3
  "
;.
"
l
l
                I. Admission or Denial of the Allemed Violation
I.
Admission or Denial of the Allemed Violation
'
'
                    Entergy Operations, Inc. admits to the violation, as outlined in NRC Inspection Report
Entergy Operations, Inc. admits to the violation, as outlined in NRC Inspection Report
                    No: 50-416/99-01, which stated that we had violated GGNS TS (Technical
No: 50-416/99-01, which stated that we had violated GGNS TS (Technical
                  Specification) 5.7.3.
Specification) 5.7.3.
                  GGNS reviewed the section of GGNS TS listed in the violation, it is important to note
GGNS reviewed the section of GGNS TS listed in the violation, it is important to note
                  that the area in question (185 foot elevation of Auxiliary Building in the area around the
that the area in question (185 foot elevation of Auxiliary Building in the area around the
                  fuel pool heat exchangers) had TS 5.7.3 allowed measures (flashing light, barricade,
fuel pool heat exchangers) had TS 5.7.3 allowed measures (flashing light, barricade,
                  and posting) in place for preventing unauthorized entry. Per TS 5.7.3, individual areas
and posting) in place for preventing unauthorized entry. Per TS 5.7.3, individual areas
                  shall be barricaded and conspicuously posted, and a flashing light shall be activated as
shall be barricaded and conspicuously posted, and a flashing light shall be activated as
                  a waming device for areas that are not enclosed or guarded and where no enclosure
a waming device for areas that are not enclosed or guarded and where no enclosure
                  can be reasonably constructed. The area in question fully complied with these
can be reasonably constructed. The area in question fully complied with these
                  requirements to prevent unauthorized entry.
requirements to prevent unauthorized entry.
                  However, GGNS could not produce clear documentation of our decision that             .
However, GGNS could not produce clear documentation of our decision that
                  construction of an enclosure around the fuel pool heat exchanger was not considered
.
                  " reasonable". GGNS believes that the use of a flashing light, barricade, and posting
construction of an enclosure around the fuel pool heat exchanger was not considered
                  was appropriate and in accordance with the requirements of TS 5.7.3. Nevertheless,
" reasonable". GGNS believes that the use of a flashing light, barricade, and posting
                  GGNS also understands that the implied TS requirement on deciding whether
was appropriate and in accordance with the requirements of TS 5.7.3. Nevertheless,
L                 enclosure is reasonable or not should be formally documented. Therefore, Grand Gulf
GGNS also understands that the implied TS requirement on deciding whether
L
enclosure is reasonable or not should be formally documented. Therefore, Grand Gulf
;
;
                  Nuclear Station will not contest the violation.
Nuclear Station will not contest the violation.
              . H. 'Ibe Reason for the Violation, if Admitted
. H.
                  No formai program exists to document evaluations conducted to determine whether it is
'Ibe Reason for the Violation, if Admitted
                  " reasonable" to erect an enclosure when radiation levels, in areas without an enclosure,
No formai program exists to document evaluations conducted to determine whether it is
                  are 11000 mrom/hr.
" reasonable" to erect an enclosure when radiation levels, in areas without an enclosure,
              IH. Corrective Steps Which Have Been Taken and Results Achieved
are 11000 mrom/hr.
                                                                                                                  g
IH.
i                                                                                                                 !
Corrective Steps Which Have Been Taken and Results Achieved
                  r>ntact permanent lead shielding has been applied to the area in question and                   ,
g
                  accessible area doserates are now <1000 mrem /hr. This has allowed exiting from TS           *
i
                                                                                                                  j
r>ntact permanent lead shielding has been applied to the area in question and
                  5.7.3.                                                                                         !
,
                                                                                                                  L
accessible area doserates are now <1000 mrem /hr. This has allowed exiting from TS
              IV. Corrective Steps to be Taken to Preclude Further Violations                                     !
j
!                  An evaluation program is being established to aid in the determination of enclosing of
*
                  areas which have long term (>90 days) doserates 21000 mrem /hr. The evaluation will
5.7.3.
                  be documented and available for review. The essential elements of the evaluation               l
IV.
                  program willinclude:
Corrective Steps to be Taken to Preclude Further Violations
                  .  Impact on operator and maintenance access to plant equipment.
!
                  .   A requirement to address ALARA concems prior to installing enclosures.                     !
An evaluation program is being established to aid in the determination of enclosing of
                  .   Engineering controls that should be applied prior to enclosing.                             l
areas which have long term (>90 days) doserates 21000 mrem /hr. The evaluation will
                  .
be documented and available for review. The essential elements of the evaluation
                      Cost benefit analysis versus dose for installation of enclosures or other options as
program willinclude:
                      outlined in the evaluation,
Impact on operator and maintenance access to plant equipment.
                                                                                                                  ,
.
                                                                                                                  i
A requirement to address ALARA concems prior to installing enclosures.
                                                                                                                  \
.
                                                                                                                  l
Engineering controls that should be applied prior to enclosing.
                                                                    '
.
    .
Cost benefit analysis versus dose for installation of enclosures or other options as
.
outlined in the evaluation,
,
i
\\
l
'
.


r:.
r:.
    8-   . .
8-
    -
. .
                                                                        Attachment to CNRO-99/00028
Attachment to CNRO-99/00028
    ',; *                                                                                   P ge 3 ef 3
-
    *
',; *
  .
P ge 3 ef 3
              V. Date When Full Compliance Will be Achieved
*
.
V.
Date When Full Compliance Will be Achieved
1. Permanent shielding was installed and accessible area doserates were confirmed
t
t
                1. Permanent shielding was installed and accessible area doserates were confirmed
to be <1000 mrem /hr. Completed 3/2/1999
                    to be <1000 mrem /hr. Completed 3/2/1999
2. Development of an evaluation program as outlined in Section IV - 7/31/1999
                2. Development of an evaluation program as outlined in Section IV - 7/31/1999
l
                                                                                                        l
                                                                                                        !
                                                                                                        l
                                                                                                        I
i
i
l
l
                                                                                                        ,
,
}}
}}

Latest revision as of 02:28, 7 December 2024

Ack Receipt of Informing NRC of Steps Taken to Correct Violations Noted in Insp Rept 50-416/99-01 & NOV .Reply Found to Be Responsive to Concerns Raised in Nov.Implementation of C/As Will Be Reviewed in Future Insps
ML20206B095
Person / Time
Site: Grand Gulf 
Issue date: 04/23/1999
From: Good G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To: Eaton W
ENTERGY OPERATIONS, INC.
References
50-416-99-01, 50-416-99-1, NUDOCS 9904290144
Download: ML20206B095 (5)


See also: IR 05000416/1999001

Text

'

,

    • "*%

UNITED STATES

4

p

1

NUCLEAR REGULATORY COMMISSION

..

$

REGION IV

e

611 RYAN PLAZA DRIVE, sUlTE 400

ARUNGTON, texas 76011-8064

,

April 23,1999

i

William A. Eaton, Vice President

Operations - Grand Gulf Nuclear Station

Entergy Operations, Inc.

P.O. Box 756

Port Gibson, Mississippi 39150

SUBJECT: NRC INSPECTION REPORT 50-416/99-01

Thank you for your letter of March 25,1999, in response to our letter and Notice of

Violation dated February 26,1999. We have reviewed your reply and find it responsive to the

concern raised in our Notice of Violation. We will review the implementation of your corrective

actions during a future inspection to determine that full compliance has been achieved and will

be maintained.'

Sincerely,

N

'

j

Gail M. Good, Chief

Plant Support Branch

Division of Reactor Safety

f

Docket No.: 50-416

License No.: NPF-29

cc:

Executive Vice President

'

i

and Chief Operating Officer

Entergy Operations, Inc.

P.O. Box 31995 -

Jackson, Mississippi 39286-1995

Wise, Carter, Chilt! & Caraway

P.O. Box 651

Jackson, Mississippi 39205

4

9904290144 990423'

"

PDR

ADOCK 05000416

G

PDR

.

l

,

.

,

..

Entergy Operations, Inc.

-2-

Winston & Strawn

l

1400 L Street, N.W. - 12th Floor

Washington, D.C. 20005-3502

Sam Mabry, Director

Division of Solid Waste Management

Mississippi Department of Natural

,

Resources

P.O. Box 10385

Jackson, Mississippi 39209

President

Claiborne County Board of Supervisors

Port Gibson, Mississippi 39150

Manager of Operations

Bechtel Power Corporation

P.O. Box 2166

Houston, Texas 77252-2166

General Manager

Grand Gulf Nuclear Station

i

Entergy Operations, Inc.

P.O. Box 756

Port Gibson, Mississippi 39150

The Honorable William J. Guste, Jr.

Attorney General

Department of Justice

State of Louisiana

P.O. Box 94005

Baton Rouge, Louisiana 70804-9005

Office of the Governor

. State of Mississippi

. Jackson, Mississippi 39201

Mike Moore, Attomey General

Frank Spencer, Asst. Attorney General

State of Mississippi

j

. P.O. Box 22947

Jackson, Mississippi 39225

{

Dr. F. E. Thompson, Jr.

State Health Officer

State Board of Health

)

P.O. Box 1700

l

Jackson, Mississ?ppi 39205 -

)

'

I

!

'

i

r .s

-- .

.

E

e

Entergy Operations, Inc.

-3-

Robert W. Goff, Director

State Liaison Officer

' Division of Radiation Health

Mississippi Department of Health

P.O. Box 1700

' Jackson, Mississippi 39215-1700

Vice President

i

Operations Support

Entergy Operations, Inc.

P.O. Box 31995

Jackson, Mississippi 39286-1995

Director, Nuclear Safety

and Regulatory Affairs

Entergy Operations, Inc.

P.O. Box 756

Port Gibson, Mississippi 39150

Vice President, Operations

Grand Gulf Nuclear Station

Entergy Operations, Inc.

P.O. Box 756

Port Gibson, Mississippi 39150

<

,

a

,

,s-

Entergy Operations, Inc

-4-

DISTRIBUTION w/ copy of licensee's letter dated March 25.1999:

,0MB(HioS);f

Rsgional Administrator

Senior Resident inspector (River Bend) -

' DRP Director

DRS-PSB

Branch Chief (DRP/4)

Project Engineer (DRP/$)

Branch Chief (DRP/TSS)

Senior Resident inspector (Grand Gulf)

MIS System

RIV File -

l

DRS Action item File (98-G-0043)(Goines)

1

us0004

DOCUMENT NAME: R:(GG\\GG901AK.MPS

)

,

To recohn oopy of document, andlesto in box: "C" = Copy without enclosures *E" = Copy with enclosuree *N" = No copy

RIV:PSB

E

C:DRS\\PSB

MPShannon:nhM(lk GMGood (Mb

'

04/ L, /99

W

04/ (d99

OFFICIAL RECORD COPY

f

!

.

-

.

.

.

Entergy Operations, Inc.

-4-

DISTRIBUTION w/coov of licensee's letter dated March 25.1999:

DMB (IE06)

Regional Administrator

Senior Resident inspector (River Bend)

DRP Director

DRS-PSB

Branch Chief (DRP/4) b)

Project Engineer (DRP/A

Branch Chief (DRP/TSS)

Senior Resident inspector (Grand Gulf)

MIS System

RIV File

DRS Action item File (98-G-0043)(Goines)

DOCUMENT NAME: R:\\_GG\\GG901AK.MPS

To receive copy of document. Indicate in box: 'C' = Copy without enclosures "E" = Copy with enclosures 'N" = No copy

' 31V:PSB

E IC:DRS\\PSB

MPShannon:nhWP GMGood (MUe

'

04/[,/99

W

04/ (c;/99

OFFICIAL RECORD COPY

'* ./%

=

Ent:rgy oportti:ns. Inc.

.

'

'

, ' *

o G son MS 39150

Tel 601 337 6409

Fax 601437 2795

l

William A. Eaton

Vice President

l

Operatons

Grand GuH Nuclear Station

f_@@@ly/@f

March 25, 1999

y

'

APR-lS99

g

..

U.S. Nuclear Regulatory Commission

L

Mail Station P1-37

Washington, D.C. 20555

_

REGIONIV

Attention:

Document Control Desk

Subject:

Grand Gulf Nuclear Station

Docket No. 50-416

License No. NPF-29

Reply To a Notice of Violation,50-416/9901-01, Violation of

Technical Specification 5.7.3

Reference:

NRC Inspection Report No. 50-416/99-01, deted

February 26,1999 (GNRI-99/00008)

GNRO-99/00028

Gentlemen:

,

Entergy Operations, Inc. is hereby submitting the response to Notice of Violation

'

50-416/9901-01 for Grand Gulf Nuclear Station. This Notice of Violation was

issued as a result of NRC Inspection 50-416/99-01 which was conducted during

the period of February 1 through February 5,1999.

Entergy Operations concurs that the overall findings of the inspection are valid. A

program wi!! be implemented to ensure that accessible areas with radiation levels

> 1000 mrem /hr, and not enclosed, have documentation to support the

reasonable determination as outlined in GGNS Technical Specification 5.7.3.

Should you have any questions or require clarification of our response, please

contact this office.

Yours truly,Y5kW.

!

WAE/WKH/MJL

l

attachment:

Response to Violation 50-416/9901-01

cc:

- (See Next Page)

1

% 3/OO N h'

e

,

  • ~

.

.

n

.

GNRO 99/00028

. Page 2 of 2

'

Ms. J. L. Dixon-Herrity, GGNS Senior Resident (w/a)

cc:

Mr. L. J. Smith (Wise Carter) (w/a)

Mr. N. S. Reynolds (w/a)

Mr. H. L. Thomas (w/o)

Mr. E. W. Merschoff (w/a)

Regional Administrator

U.S. Nuclear Regulatory Commission

Region IV

611 Ryan Plaza Drive, Suite 400

Arlington, TX 76011

.

Mr. S. P. Sekerak, Project Manager (w/2)

Office of Nuclear Reactor Regulation

U.S. Nuclear Regulatory Commission

Mail Stop 13H3-D

Washington, D.C. 20555

!

1

.

.

m

[~

'

. <<

.

l -

Attachm:nt t3 GNRO-99/00028

u

-

Pag 31 cf 3

.

.

Notice of Violation 50-416/9901-01

During a NRC inspection conducted on February 1-5,1999, one violation of NRC requirements

was identified. In accordance with the " General Statement of Policy and Procedure for NRC

Enforcement Actions," NUREG-1600, the violation is listed below:

Technical Specification 5.7.2 requires, in part, that areas with radiation levels greater

than or equal to 1000 millirems per hour be provided with locked or continuously

guarded doors to prevent unauthorized entry. Technical Specification 5.7.3 states, la

part, that for individual high radiation areas with radiation levels greater than 1000

mrem per hour, accessible to personnel, that are located within large areas such as the

reactor containment, where no enclosure exists for purposes of locking, or that cannot

be continuously guarded, and where no enclosure can be reasonably constructed

around the individual area, that individual area shall be barricaded and conspicuously

posted, and a flashing light shall be activated as a waming device.

Contrary to the above, on February 1,1999, NRC inspectors identified that an area

with dose rates greater than 1000 millirems per hour was not provided with locked or

continuously guarded doors to prevent unauthorized entry. Specifically, the area

around the spe,)t fuel pool cooling and cleanup heat exchangers, an area which is

l

. accessible to personnel and in which an enclosure reasonably could be constructed,

was not provided with locked or continuously guarded doors to prevent unauthorized

!

entry.

l

,

4

l

l

!

i

i

.-

..

.

Attachm:nt to GNRO-99/00028

.

+

P ge 2 cf 3

.

"

l

I.

Admission or Denial of the Allemed Violation

'

Entergy Operations, Inc. admits to the violation, as outlined in NRC Inspection Report

No: 50-416/99-01, which stated that we had violated GGNS TS (Technical

Specification) 5.7.3.

GGNS reviewed the section of GGNS TS listed in the violation, it is important to note

that the area in question (185 foot elevation of Auxiliary Building in the area around the

fuel pool heat exchangers) had TS 5.7.3 allowed measures (flashing light, barricade,

and posting) in place for preventing unauthorized entry. Per TS 5.7.3, individual areas

shall be barricaded and conspicuously posted, and a flashing light shall be activated as

a waming device for areas that are not enclosed or guarded and where no enclosure

can be reasonably constructed. The area in question fully complied with these

requirements to prevent unauthorized entry.

However, GGNS could not produce clear documentation of our decision that

.

construction of an enclosure around the fuel pool heat exchanger was not considered

" reasonable". GGNS believes that the use of a flashing light, barricade, and posting

was appropriate and in accordance with the requirements of TS 5.7.3. Nevertheless,

GGNS also understands that the implied TS requirement on deciding whether

L

enclosure is reasonable or not should be formally documented. Therefore, Grand Gulf

Nuclear Station will not contest the violation.

. H.

'Ibe Reason for the Violation, if Admitted

No formai program exists to document evaluations conducted to determine whether it is

" reasonable" to erect an enclosure when radiation levels, in areas without an enclosure,

are 11000 mrom/hr.

IH.

Corrective Steps Which Have Been Taken and Results Achieved

g

i

r>ntact permanent lead shielding has been applied to the area in question and

,

accessible area doserates are now <1000 mrem /hr. This has allowed exiting from TS

j

5.7.3.

IV.

Corrective Steps to be Taken to Preclude Further Violations

!

An evaluation program is being established to aid in the determination of enclosing of

areas which have long term (>90 days) doserates 21000 mrem /hr. The evaluation will

be documented and available for review. The essential elements of the evaluation

program willinclude:

Impact on operator and maintenance access to plant equipment.

.

A requirement to address ALARA concems prior to installing enclosures.

.

Engineering controls that should be applied prior to enclosing.

.

Cost benefit analysis versus dose for installation of enclosures or other options as

.

outlined in the evaluation,

,

i

\\

l

'

.

r:.

8-

. .

Attachment to CNRO-99/00028

-

',; *

P ge 3 ef 3

.

V.

Date When Full Compliance Will be Achieved

1. Permanent shielding was installed and accessible area doserates were confirmed

t

to be <1000 mrem /hr. Completed 3/2/1999

2. Development of an evaluation program as outlined in Section IV - 7/31/1999

l

i

l

,