{{#Wiki_filter:June 5, 1998 MEMORANDUM TO:                   Thomas T. Martin, Chairman Committee to Review Generic Requirements (original signed by Brian W. Sheron for:]
{{#Wiki_filter:June 5, 1998 MEMORANDUM TO:
FROM:                           Frank J. Miraglia, Jr., Deputy Director Office of Nuclear Reactor Regulation
Thomas T. Martin, Chairman Committee to Review Generic Requirements (original signed by Brian W. Sheron for:]
FROM:
Frank J. Miraglia, Jr., Deputy Director Office of Nuclear Reactor Regulation


==SUBJECT:==
==SUBJECT:==
Line 23: Line 25:
Specifically, these reviews are of the BWRVIP-03,-14, and -18 reports.
Specifically, these reviews are of the BWRVIP-03,-14, and -18 reports.
The subject SEs are not complete, in as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.
The subject SEs are not complete, in as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.
CONTACT:           C. E. Carpenter, DE:NRR 415-2169 Distribution:
CONTACT:
SJCollins                     EMCB R/F               ! File Center;if     PUBLIC DOCUMENT NAME: G:\BWRVIP\CRGR-MEM.A
C. E. Carpenter, DE:NRR 415-2169 Distribution:
* see previous concurrence INDIC ATE IN BOX: *C"= COPY, "N"nNO COPY OFFICE       LPM:EMCB               SLS:EMCB             SC:EMCB         (A)BC:EMCB NAME         CECarpenter* A         RAHermann*           KRWichman*     EJSullivan*
SJCollins EMCB R/F
DATE         06/04/98               06/04/98             06/04/98       06/ /98 mm                        .-:    ;
! File Center;if PUBLIC DOCUMENT NAME: G:\\BWRVIP\\CRGR-MEM.A
                                                      .m                 m OFFICE       (A)DD:DE               (A)D:DE             ( AC     RR       D:1 R d b NAME         JRStrosnider*         GClainas*           BWSd     n     FJM     lia DATE         06/04/98               06/04/98             06/ 5 /98       06/ J/98 OFFICIAL RECORD COP' f                                           'a lo ,
* see previous concurrence INDIC ATE IN BOX: *C"= COPY, "N"nNO COPY OFFICE LPM:EMCB SLS:EMCB SC:EMCB (A)BC:EMCB NAME CECarpenter* A RAHermann*
98M10 S C Wif 6H@ @ O N                                     gO 9006100478 990605 kN ~q cgW PDR     REVQP ERONUPRC                                                                                 i PDR                                                                   ,\O ,
KRWichman*
EJSullivan*
DATE 06/04/98 06/04/98 06/04/98 06/ /98
.m m
mm b
OFFICE (A)DD:DE (A)D:DE
( AC RR D:1 R d NAME JRStrosnider*
GClainas*
BWSd n
FJM lia DATE 06/04/98 06/04/98 06/ 5 /98 06/ J/98 OFFICIAL RECORD COP' f
'a lo,
98M10 S C Wif 6H@ @ O N gO kN ~q cgW 9006100478 990605 PDR REVQP ERONUPRC i
PDR
,\\O,


r MEMORANDUM TO:               Thomas T. Martin, Chairman Committee to Review Generic Requirements FROM:                         Frank J. Miraglia, Jr., Deputy Director Office of Nuclear Reactor Regulation
r MEMORANDUM TO:
Thomas T. Martin, Chairman Committee to Review Generic Requirements FROM:
Frank J. Miraglia, Jr., Deputy Director Office of Nuclear Reactor Regulation


==SUBJECT:==
==SUBJECT:==
WITHDAWAL OF REQUEST FOR CRGR TO REVIEW THE STAFF'S SAFETY EVALUATIONS FOR THE BWR VESSEL AND INTERNALS
WITHDAWAL OF REQUEST FOR CRGR TO REVIEW THE STAFF'S SAFETY EVALUATIONS FOR THE BWR VESSEL AND INTERNALS PROJECT SUBMITTALS Subsequent to the discussions held by you with Jack R. Strosnider, Acting Deputy Director of the Division of Engineering, the Office of Nuclear Reactor Regulation (NRR)is withdrawing its request to have the Committee to Review Generic Requirements (CRGR) waive review of the staff's safety evaluation (SEs) for the Electric Power Research Institute (EPRI) proprietary guidance reports that have been submitted by the BWR Vessel and Internals Project (BWRVIP).
!                                          PROJECT SUBMITTALS Subsequent to the discussions held by you with Jack R. Strosnider, Acting Deputy Director of the Division of Engineering, the Office of Nuclear Reactor Regulation (NRR)is withdrawing its request to have the Committee to Review Generic Requirements (CRGR) waive review of the staff's safety evaluation (SEs) for the Electric Power Research Institute (EPRI) proprietary guidance reports that have been submitted by the BWR Vessel and Internals Project (BWRVIP).
Specifically, these reviews are of the BWRVIP-03, -14, and -18 reports.
Specifically, these reviews are of the BWRVIP-03, -14, and -18 reports.
The subject SEs are not complete, in as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.
The subject SEs are not complete, in as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.
1 CONTACT:           C. E. Carpenter, DE:NRR 415 2169 I
1 CONTACT:
C. E. Carpenter, DE:NRR 415 2169 I
Distribution:
Distribution:
SJCollins                   EMCB R/F                 File Center           PUBLIC DOCUMENT NAME: G:\BWRVIP\CRGR-MEM.A                                               4N IND6CATE IN BOX:"C"= COPY W/O ATTACHMENT / ENCLOSURE "E"= COPY W/ATT$NCL,"N"sNO COPY >14C OFFICE     LPM MCS             SLS:EMC9         h     SC;E   Of)       (A)BC:EMCB NAME                 r         RAHerman                         n       EJSullivan k umu                   uma               immi               umm OFFICE     (A)DD:DE             (A)D:DE               (A)ADT:NRR         DD:NRR NAME       JRStrosnider         GClaina                 BWSheron         FJMiraglia DATE           / O /98                 /98                 / /98           /   /98 giu\*                        OFFICIAL RECORD COPY
SJCollins EMCB R/F File Center PUBLIC DOCUMENT NAME: G:\\BWRVIP\\CRGR-MEM.A 4N IND6CATE IN BOX:"C"= COPY W/O ATTACHMENT / ENCLOSURE "E"= COPY W/ATT$NCL,"N"sNO COPY >14C OFFICE LPM MCS SLS:EMC9 h
SC;E Of)
(A)BC:EMCB NAME r
RAHerman n
EJSullivan k umu uma immi umm OFFICE (A)DD:DE (A)D:DE (A)ADT:NRR DD:NRR NAME JRStrosnider GClaina BWSheron FJMiraglia DATE
/ O /98
/98
/
/98
/
/98 OFFICIAL RECORD COPY gi
* u\\


f
f
  ,          ** u9 p             t,                               UNITED STATES y
** u9 p
  /    *              }
t, UNITED STATES y
t NUCLEAR REC!ULATORY COMMISSION WASHINGTON. D.C. 30086-4001
}
        %        .                                  June 5, 1998 MEMORANDUM TO: Thomas T. Martin, Chairman Committee to Review Generic Requirements FROM:               <          . Miraglia, Jr., Deputy Director
NUCLEAR REC!ULATORY COMMISSION
                                  >    ice of Nuclear Reactor Regulation
/
t WASHINGTON. D.C. 30086-4001 June 5, 1998 MEMORANDUM TO: Thomas T. Martin, Chairman Committee to Review Generic Requirements FROM:
. Miraglia, Jr., Deputy Director ice of Nuclear Reactor Regulation


==SUBJECT:==
==SUBJECT:==
THDRAWAL OF REQUEST FOR CRGR TO REVIEW THE STAFF'S SAFETY EVALUATIONS FOR THE BWR VESSEL AND INTERNALS PROJECT SUBMITTALS I
THDRAWAL OF REQUEST FOR CRGR TO REVIEW THE STAFF'S SAFETY EVALUATIONS FOR THE BWR VESSEL AND INTERNALS PROJECT SUBMITTALS I
Subsequent to the discussions held by you with Jack R. Strosnider, Acting Deputy Director of the ;
Subsequent to the discussions held by you with Jack R. Strosnider, Acting Deputy Director of the Division of Engineering, the Office of Nuclear Reactor Regulation (NRR) is withdrawing its request to have the Committee to Review Generic Requirements (CRGR) waive review of the staff's safety evaluation (SEs) for the Electric Power Research Institute (EPRI) proprietary guidance reports that have been submitted by the BWR Vessel and intemals Project (BWRVIP).
Division of Engineering, the Office of Nuclear Reactor Regulation (NRR) is withdrawing its request to have the Committee to Review Generic Requirements (CRGR) waive review of the staff's safety evaluation (SEs) for the Electric Power Research Institute (EPRI) proprietary guidance reports that have been submitted by the BWR Vessel and intemals Project (BWRVIP).
Specifically, these reviews are of the BWRVIP-03,-14, and -18 reports.
Specifically, these reviews are of the BWRVIP-03,-14, and -18 reports.
The subject SEs are not complete, as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.
The subject SEs are not complete, as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.
CONTACT:       C. E. Carpenter, DE:NRR 415-2169 I
CONTACT:
                                                                                                            ,}}
C. E. Carpenter, DE:NRR 415-2169 I
,}}

Latest revision as of 02:17, 3 December 2024

Withdraws Request to Have Committee to Review Generic Requirements Waive Review of Staff SER for Electric Power Research Institute Proprietary Guidance Repts Submitted by BWR Vessel & Internals Project (BWRVIP)
ML20236E829
Person / Time
Issue date: 06/05/1998
From: Miraglia F
NRC (Affiliation Not Assigned)
To: Martin T
Committee To Review Generic Requirements
References
NUDOCS 9806100478
Download: ML20236E829 (3)


Text

June 5, 1998 MEMORANDUM TO:

Thomas T. Martin, Chairman Committee to Review Generic Requirements (original signed by Brian W. Sheron for:]

FROM:

Frank J. Miraglia, Jr., Deputy Director Office of Nuclear Reactor Regulation

SUBJECT:

WITHDRAWAL OF REQUEST FOR CRGR TO REVIEW THE STAFF'S SAFETY EVALUATIONS FOR THE BWR VESSEL AND INTERNALS PROJECT SUBMiTTALS Subsequent to the discussions held by you with Jack R. Strosnider, Acting Deputy Director of the Division of Engineering, the Office of Nuclear Reactor Regulation (NRR) is withdrawing its request to have the Committee to Review Generic Requirements (CRGR) waive review of the staff's safety evaluation (SEs) for the Electric Power Research Institute (EPRI) proprietary guidance reports that have been submitted by the BWR Vessel and Internals Project (BWRVIP).

Specifically, these reviews are of the BWRVIP-03,-14, and -18 reports.

The subject SEs are not complete, in as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.

CONTACT:

C. E. Carpenter, DE:NRR 415-2169 Distribution:

SJCollins EMCB R/F

! File Center;if PUBLIC DOCUMENT NAME: G:\\BWRVIP\\CRGR-MEM.A

  • see previous concurrence INDIC ATE IN BOX: *C"= COPY, "N"nNO COPY OFFICE LPM:EMCB SLS:EMCB SC:EMCB (A)BC:EMCB NAME CECarpenter* A RAHermann*

KRWichman*

EJSullivan*

DATE 06/04/98 06/04/98 06/04/98 06/ /98

.m m

mm b

OFFICE (A)DD:DE (A)D:DE

( AC RR D:1 R d NAME JRStrosnider*

GClainas*

BWSd n

FJM lia DATE 06/04/98 06/04/98 06/ 5 /98 06/ J/98 OFFICIAL RECORD COP' f

'a lo,

98M10 S C Wif 6H@ @ O N gO kN ~q cgW 9006100478 990605 PDR REVQP ERONUPRC i

PDR

,\\O,

r MEMORANDUM TO:

Thomas T. Martin, Chairman Committee to Review Generic Requirements FROM:

Frank J. Miraglia, Jr., Deputy Director Office of Nuclear Reactor Regulation

SUBJECT:

WITHDAWAL OF REQUEST FOR CRGR TO REVIEW THE STAFF'S SAFETY EVALUATIONS FOR THE BWR VESSEL AND INTERNALS PROJECT SUBMITTALS Subsequent to the discussions held by you with Jack R. Strosnider, Acting Deputy Director of the Division of Engineering, the Office of Nuclear Reactor Regulation (NRR)is withdrawing its request to have the Committee to Review Generic Requirements (CRGR) waive review of the staff's safety evaluation (SEs) for the Electric Power Research Institute (EPRI) proprietary guidance reports that have been submitted by the BWR Vessel and Internals Project (BWRVIP).

Specifically, these reviews are of the BWRVIP-03, -14, and -18 reports.

The subject SEs are not complete, in as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.

1 CONTACT:

C. E. Carpenter, DE:NRR 415 2169 I

Distribution:

SJCollins EMCB R/F File Center PUBLIC DOCUMENT NAME: G:\\BWRVIP\\CRGR-MEM.A 4N IND6CATE IN BOX:"C"= COPY W/O ATTACHMENT / ENCLOSURE "E"= COPY W/ATT$NCL,"N"sNO COPY >14C OFFICE LPM MCS SLS:EMC9 h

SC;E Of)

(A)BC:EMCB NAME r

RAHerman n

EJSullivan k umu uma immi umm OFFICE (A)DD:DE (A)D:DE (A)ADT:NRR DD:NRR NAME JRStrosnider GClaina BWSheron FJMiraglia DATE

/ O /98

/98

/

/98

/

/98 OFFICIAL RECORD COPY gi

  • u\\

f

    • u9 p

t, UNITED STATES y

}

NUCLEAR REC!ULATORY COMMISSION

/

t WASHINGTON. D.C. 30086-4001 June 5, 1998 MEMORANDUM TO: Thomas T. Martin, Chairman Committee to Review Generic Requirements FROM:

. Miraglia, Jr., Deputy Director ice of Nuclear Reactor Regulation

SUBJECT:

THDRAWAL OF REQUEST FOR CRGR TO REVIEW THE STAFF'S SAFETY EVALUATIONS FOR THE BWR VESSEL AND INTERNALS PROJECT SUBMITTALS I

Subsequent to the discussions held by you with Jack R. Strosnider, Acting Deputy Director of the Division of Engineering, the Office of Nuclear Reactor Regulation (NRR) is withdrawing its request to have the Committee to Review Generic Requirements (CRGR) waive review of the staff's safety evaluation (SEs) for the Electric Power Research Institute (EPRI) proprietary guidance reports that have been submitted by the BWR Vessel and intemals Project (BWRVIP).

Specifically, these reviews are of the BWRVIP-03,-14, and -18 reports.

The subject SEs are not complete, as they contain open issues which require further review before a final SE can be issued. As such, CRGR review at this time is not required. When the open issues have been resolved, the staff will provide the CRGR with the final SEs for review, if required.

CONTACT:

C. E. Carpenter, DE:NRR 415-2169 I

,