ML20149M874: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(StriderTol Bot change)
 
Line 1: Line 1:
{{Adams
#REDIRECT [[AECM-88-0044, Forwards Util Response to Generic Ltr 88-02 Re Interest in Participating in Isap II Program.Expression of Interest Will Not Be Considered Commitment to Participate on Part of Util]]
| number = ML20149M874
| issue date = 02/22/1988
| title = Forwards Util Response to Generic Ltr 88-02 Re Interest in Participating in Isap II Program.Expression of Interest Will Not Be Considered Commitment to Participate on Part of Util
| author name = Kingsley O
| author affiliation = SYSTEM ENERGY RESOURCES, INC.
| addressee name =
| addressee affiliation = NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
| docket = 05000416
| license number =
| contact person =
| document report number = AECM-88-0044, AECM-88-44, GL-88-02, GL-88-2, NUDOCS 8802290194
| document type = CORRESPONDENCE-LETTERS, INCOMING CORRESPONDENCE, UTILITY TO NRC
| page count = 3
}}
 
=Text=
{{#Wiki_filter:.
O EEE                              February 22, 1988 ceta o Knw e wwna fuect CTay&Or4 U. S. Nuclear Regulatory Comission Washington, D. C. 20555 Attention: Document Control Desk Gentlemen:
 
==SUBJECT:==
Grand Gulf Nuclear Station Unit 1 Docket No. 50-416 License No. NPF-29 Response to Generic Letter 88-02 AECM-88/0044 Generic Letter 88-02 requested that each licensee respond to a survey indicating their interest in participating in the ISAP II Program.            System Energy Resources, Inc.'s (SERI) response to Generic Letter 88-02 is attached.
Should you have any questions concerning SERI's response, please contact me.
Yours truly, U
m t c ment                                                        I' cc: Mr. T. H. Cloninger (w/a)
Mr. R. B. McGehee (w/a)
Mr. N. S. Reynolds (w/a)
Mr. H. L. Themas (w/o)
Mr. R. C. Butcher (w/a)
Dr. J. Nelson Grace, Regional Administrator (w/a)
U. S. Nuclear Regulatory Connission Region II 101 Marietta St., N. W.,  Suite 2900 Atlanta, Georgia 30323 Mr. L. L. Kintner, Project Manager (w/a)
Office of Nuclear Reactor Regulation                              4 U. S. Nuclear Regulatory Comission Mail Stop 14820 Or h
Washington 0.C. 20555 l
1\
8002290194 esoppa PDR  ADOCK 05000416 P                    PDR        o w l mn .a.in    a r ~m n l ., , mm u n.e. w r,n c c w ,
J12AECM88021602 - 1
 
  ';    '. s Integrated Safety Assessment Program (ISAP)~II Response to Generic letter 88-02 Facility Name:          Grand Gulf Nuclear Station Utility:          System Energy Resources, Inc.
Individual Contact Name:                Matt Crawford                                                                                                Phone Number: (601) 969-2408 An expression of interest will not be considered a commitment to participate on the part of the utility.
I QUESTION                                                                                                                                                                                    !
: 1)      Would you be interested in participating in ISAP II? If so, in what time frame?
 
===RESPONSE===
: 1)      Possibly, based on consideration of additional information.
If the decision were made to participate in the ISAP 11 program.
SERI's participation would likely be in association with performing the Grand Gulf Nuclear Station's IPE, This is expected to begin in early 1989.
QUESTION
: 2)      Do you believe that an industry /NRC seminar consisting of a brief                                                                                                          i discussion by NRC followed by a question and answer period would be
'                          beneficial prior to making a decision?
 
===RESPONSE===
: 2)      Yes. A question / answer session would be especially beneficial to both the Industry and NRC. It would be very helpful to openly discuss with other utilities and the NRC both the positive and negative aspects of participating in the ISAP 11 program.
1 I
  ;          J14 MISC 88021203 - 1
 
6, J
i QUESTION f
,                    3)    Would you be interested in a one-on-one meeting with the NRC to discuss your particular facility or facilities?                        .
 
===RESPONSE===
: 3)    A one-on-one meeting with the NRC would probably only be beneficial    L if the decision was made to participate in the ISAP II program. In this event, a meeting would be beneficial in establishing a thorough    [
understanding of how the process will work and how the results will    t be used by both the utility and NRC.                                    i r
i QUESTION
: 4)    If you remain undecided regarding participation, what additional        l 4-                        infonnation do you need in order to make a decision?                    j t
RESPONSE                                                                          ,
!                    4)    Additional clarification as to how factors other than risk reduction    l estimates will be factored into prioritizing work items. Priorit-        '
ization and scheduling of modifications require consideration of many    i topics besides risk reduction estimates. Consideration of budget,        ,
.                          manpower loading, impact on plant availability, personnel exposure      (
and safety must all be considered.                                      ;
t L
:              QUESTION                                                                          j i
: 5)    Do you have any potential concerns about participating in ISAP II?      f l
I                                                                                                  F i              RESPONSE i
l                    5)    There is concern as to how factors other than risk reduction            !
i                          estimates will be factnred into the prioritizing and scheduling of
,                          both regulatory and non-regulatory issues (reference above response).  .
f~                                                                                                  }
4 QUESTION                                                                            7 l                    6)    Do you have any suggestions for program improvements or changes?
j              RESPONSE                                                                            .
: 6)    No suggestions at this time.                                              ,
I 1
t i
;              J14 MISC 88021203 - 2                                                              l
                                                                                                  't}}

Latest revision as of 02:36, 15 June 2022