ML21098A126: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
Line 16: | Line 16: | ||
=Text= | =Text= | ||
{{#Wiki_filter:}} | {{#Wiki_filter:Working Group Nicholas Melly, P.E. | ||
Office of Nuclear Regulatory Research | |||
NRC/EPRI Working Group | |||
* EPRI & NRC cooperative research agreement | |||
* Mission | |||
- Advance state of knowledge and develop understanding of risk from HEAF | |||
* Goals | |||
- Parameters that influence frequency and severity | |||
- Develop more realistic risk models | |||
- Analyze plant impact and ensure plant safety HEAF Research Working Group Update - April 6th, 2021 | |||
NRC/EPRI Working Group Team Members | |||
* Ken Fleischer (Fleischer Consultants) | |||
* JS Hyslop (NRC) | |||
* Dane Lovelace (Jensen Hughes) | |||
* Nicholas Melly (NRC) | |||
* Shannon Lovvern (TVA) | |||
* Kenn Miller (NRC) | |||
* Tom Short (EPRI) | |||
* Gabriel Taylor (NRC) | |||
* Marko Randelovic/Ashley Lindeman (EPRI) | |||
* Chris LaFleur (SNL) | |||
* Jason Floyd (Jensen Hughes) | |||
* Kenneth Hamburger (NRC) | |||
Project Management | |||
* Kelli Voelsing (EPRI) | |||
* Mark Henry Salley (NRC) | |||
HEAF Research Working Group Update - April 6th, 2021 | |||
NRC/EPRI Working Group Method Improvements | |||
* Updated frequency values to comport with working group definitions of HEAF events (Arc blast vs. HEAF events) | |||
* The use of plant specific electrical design to focus HEAF scenario creation and frequency | |||
* NRC/EPRI working group is in the process of developing CDF modeling tools along with fragility test data, OpEx and expert judgment to define target vulnerability | |||
* Development of multiple consequence end states HEAF Research Working Group Update - April 6th, 2021 | |||
NRC Project Plan | |||
* Project Plan | |||
- Requested by EPRI to improve project management | |||
- Addresses objectives, assumptions, risks, and schedule | |||
- Developed in close coordination with NRC/EPRI WG Members | |||
- The project plan has been recently added to the NRC HEAF website | |||
* https://www.nrc.gov/about-nrc/regulatory/research/fire-research/heaf-research.html HEAF Research Working Group Update - April 6th, 2021 | |||
Project Schedule HEAF Research Working Group Update - April 6th, 2021 6}} |
Latest revision as of 17:54, 19 January 2022
ML21098A126 | |
Person / Time | |
---|---|
Issue date: | 04/06/2021 |
From: | Nick Melly Office of Nuclear Regulatory Research |
To: | |
Kenneth Hamburger | |
Shared Package | |
ML21098A124 | List: |
References | |
Download: ML21098A126 (6) | |
Text
Working Group Nicholas Melly, P.E.
Office of Nuclear Regulatory Research
NRC/EPRI Working Group
- EPRI & NRC cooperative research agreement
- Mission
- Advance state of knowledge and develop understanding of risk from HEAF
- Goals
- Parameters that influence frequency and severity
- Develop more realistic risk models
- Analyze plant impact and ensure plant safety HEAF Research Working Group Update - April 6th, 2021
NRC/EPRI Working Group Team Members
- Ken Fleischer (Fleischer Consultants)
- JS Hyslop (NRC)
- Dane Lovelace (Jensen Hughes)
- Nicholas Melly (NRC)
- Shannon Lovvern (TVA)
- Kenn Miller (NRC)
- Tom Short (EPRI)
- Gabriel Taylor (NRC)
- Marko Randelovic/Ashley Lindeman (EPRI)
- Chris LaFleur (SNL)
- Jason Floyd (Jensen Hughes)
- Kenneth Hamburger (NRC)
Project Management
- Kelli Voelsing (EPRI)
- Mark Henry Salley (NRC)
HEAF Research Working Group Update - April 6th, 2021
NRC/EPRI Working Group Method Improvements
- Updated frequency values to comport with working group definitions of HEAF events (Arc blast vs. HEAF events)
- The use of plant specific electrical design to focus HEAF scenario creation and frequency
- NRC/EPRI working group is in the process of developing CDF modeling tools along with fragility test data, OpEx and expert judgment to define target vulnerability
- Development of multiple consequence end states HEAF Research Working Group Update - April 6th, 2021
NRC Project Plan
- Project Plan
- Requested by EPRI to improve project management
- Addresses objectives, assumptions, risks, and schedule
- Developed in close coordination with NRC/EPRI WG Members
- The project plan has been recently added to the NRC HEAF website
- https://www.nrc.gov/about-nrc/regulatory/research/fire-research/heaf-research.html HEAF Research Working Group Update - April 6th, 2021
Project Schedule HEAF Research Working Group Update - April 6th, 2021 6