ENS 53767: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
Line 20: | Line 20: | ||
No emergency diesel generators started as per design. Train A and B motor driven and the turbine driven AFW pumps have been returned to automatic. All other safety systems functioned per design. | No emergency diesel generators started as per design. Train A and B motor driven and the turbine driven AFW pumps have been returned to automatic. All other safety systems functioned per design. | ||
The loss of power to 138 KV transformer XST1 resulted in loss of power to both safeguards busses on Unit 2. The busses performed a load-shed and slow transfer to power supplied from 345 KV transformer XST2A as designed and were re-energized and loads sequenced back onto the busses. The emergency diesel generators are not required to start unless the busses are not re-energized by the alternate offsite transformer. All electrical power related actuations functioned as designed. There was no impact on Unit 1. | The loss of power to 138 KV transformer XST1 resulted in loss of power to both safeguards busses on Unit 2. The busses performed a load-shed and slow transfer to power supplied from 345 KV transformer XST2A as designed and were re-energized and loads sequenced back onto the busses. The emergency diesel generators are not required to start unless the busses are not re-energized by the alternate offsite transformer. All electrical power related actuations functioned as designed. There was no impact on Unit 1. | ||
The licensee has notified the NRC Resident Inspector. | The licensee has notified the NRC Resident Inspector. | ||
| URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2018/20181204en.html#en53767 | | URL = https://www.nrc.gov/reading-rm/doc-collections/event-status/event/2018/20181204en.html#en53767 | ||
}}{{unit info | }}{{unit info |
Latest revision as of 23:58, 23 February 2020
Where | |
---|---|
Comanche Peak Texas (NRC Region 4) | |
Reporting | |
10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+5.25 h0.219 days <br />0.0312 weeks <br />0.00719 months <br />) | |
Opened: | Brian Mitchell 11:15 Dec 3, 2018 |
NRC Officer: | Karen Cotton |
Last Updated: | Dec 3, 2018 |
53767 - NRC Website
| |