{{#Wiki_filter:Northwest Medical Isotopes, LLC (NWMI)Construction Permit Review Processand Environmental Scoping MeetingDecember 8, 2015 Purpose of Today's MeetingProvide overview of construction permit review process  
{{#Wiki_filter:Northwest Medical Isotopes, LLC (NWMI)
-Safety review
Construction Permit Review Process and Environmental Scoping Meeting December 8, 2015
-Environmental reviewReceive public input on environmental review 2 NRC's Governing Statutes
 
-Atomic Energy Act of 1954, as Amended
Purpose of Todays Meeting Provide overview of construction permit review process
-National Environmental Policy Act (NEPA)NRC's Mission
  - Safety review
-Protect Public Health and Safety
  - Environmental review Receive public input on environmental review 2
-Promote Common Defense and SecurityNRC Regulatory Oversight 3
 
Construction permit application
NRC Regulatory Oversight NRCs Governing Statutes
-Environmental report
- Atomic Energy Act of 1954, as Amended
-Preliminary safety analysis report (PSAR)Concurrent reviews
- National Environmental Policy Act (NEPA)
-Each take approximately 18
NRCs Mission
-24 monthsApplication available at: http://adams.nrc.gov/wba/  
- Protect Public Health and Safety
-ADAMS Accession No.: ML15086A261 and ML15210A182Construction Permit Application 4
- Promote Common Defense and Security 3
Construction Permit Review ProcessEnvironmentalReviewNRC Construction Permit DecisionConstruction PermitApplication submitted to NRCSafetyReviewReview byACRSHearing 5 Acceptance/Sufficiency reviewReview contents of application
 
-Summary description of the facility
Construction Permit Application Construction permit application
-Preliminary design of the facility
  - Environmental report
-Preliminary analysis and evaluation of design
  - Preliminary safety analysis report (PSAR)
-Environmental Report Decision to docketDocketing and Sufficiency of Application 6
Concurrent reviews
Manufacture low enriched uranium targetsTransport targets to research reactors
  - Each take approximately 18-24 months Application available at: http://adams.nrc.gov/wba/
-University of Missouri  
  - ADAMS Accession No.: ML15086A261 and ML15210A182 4
-Columbia-Oregon State UniversityTransport irradiated targets back to NWMI 99Mo recovered through processing of irradiated targetsFacility Technology 7
 
Facility Technology 8Facility OperationsSlide from Public Meeting on April 2, 2015(ML15090A710)
Construction Permit Review Process Safety Review Review by ACRS Construction Permit NRC Construction Application        Hearing Permit Decision submitted to NRC Environmental Review 5
Initial NRC staff review of the applicationRequest(s) for additional information (RAI)Safety Evaluation Report (SER) and Environmental Impact Statement (EIS)Advisory Committee on Reactor Safeguards (ACRS) SER reviewMandatory hearingDecision to grant or deny construction permitSafety and Environmental Review Process 9
 
National Environmental Policy Act (NEPA)-Informs Federal decision making
Docketing and Sufficiency of Application Acceptance/Sufficiency review Review contents of application
-Public disclosure of environmental impacts and other considerationsNRC's Environmental Regulations10 CFR Part 51Staff prepares an Environmental Impact Statement (EIS)Environmental Review(10 CFR Part 51) 10 Environmental Review(10 CFR Part 51) 11Staff conducts environmental site auditNRC issues draft EIS*Scoping Process*Draft EIS ProcessNRC issues final EIS* Opportunityfor PublicInvolvement Proposed Site LocationDiscovery Ridge, Columbia, MO Approximately 3.0 hectares (7.4 acres)Agricultural land 12 Proposed Site LocationDiscovery Ridge, Columbia, MO Approximately 3.0 hectares (7.4 acres)Agricultural land 13 Staff Evaluates Impacts to Resources
  - Summary description of the facility
-Fish and Wildlife
  - Preliminary design of the facility
-Water and Air Resources
  - Preliminary analysis and evaluation of design
-Historical or Cultural Resources-Taxes, Community Development, Environmental Justice
  - Environmental Report Decision to docket 6
-Human Health
 
-Land Use Environmental Impact Statement 14 Scoping and Public InvolvementWhat is unique about your community?What local environmental issues should the NRC examine?What reasonable alternatives are appropriate for the area?
Facility Technology Manufacture low enriched uranium targets Transport targets to research reactors
15 Role of Public Comments on the Environmental ReviewLicensing DecisionEnvironmental Impact StatementSafety Evaluation ReportHearingAdvisory Committee on Reactor Safeguards Independent ReviewPublic Comments on Environmental ReviewConstruction PermitApplication 16 How to Submit Comments on the Environmental ReviewOnline at http://www.regulations.govEnter ID :Comments will not be edited to remove identifying informationComments must be submitted by January 4, 2016 NRC-2013-0235 17 How to Submit Comments on the Environmental Reviewhttp://www.regulations.gov 18 By mail (please reference NWMI construction permit):Ms. Cindy BladeyChief, Rules, Announcements, and Directives BranchOffice of Administration, Mail stop: OWFN H08US Nuclear Regulatory Commission Washington, DC 20555-0001Comments will not be edited to remove identifying informationComments must be submitted by January 4, 2016How to Submit Comments on the Environmental Review 19 Where to view documentsEnvironmental Report located at:Daniel Boone Regional Library 100 W BroadwayColumbia, MO 65203Environmental Report can also be viewed on NRC's Web site: http://adams.nrc.gov/wba
  - University of Missouri - Columbia
/Accession Number: ML15086A261 20 Project Manager InformationNancy Martinez (Environmental)(800) 368-5642 ext. 2719Nancy.Martinez@nrc.govMichael Balazik (Safety)
  - Oregon State University Transport irradiated targets back to NWMI 99Mo recovered through processing of irradiated targets 7
(800) 368-5642 ext. 2856Michael.Balazik@nrc.gov 21 Northwest Medical Isotopes, LLC (NWMI)Construction Permit Review Processand Environmental Scoping MeetingDecember 8, 2015 Purpose of Today's MeetingProvide overview of construction permit review process  
 
-Safety review
Facility Technology Slide from Public Meeting on April 2, 2015 Facility Operations (ML15090A710) 8
-Environmental reviewReceive public input on environmental review 2 NRC's Governing Statutes
 
-Atomic Energy Act of 1954, as Amended
Safety and Environmental Review Process Initial NRC staff review of the application Request(s) for additional information (RAI)
-National Environmental Policy Act (NEPA)NRC's Mission
Safety Evaluation Report (SER) and Environmental Impact Statement (EIS)
-Protect Public Health and Safety
Advisory Committee on Reactor Safeguards (ACRS) SER review Mandatory hearing Decision to grant or deny construction permit                                    9
-Promote Common Defense and SecurityNRC Regulatory Oversight 3
 
Construction permit application
Environmental Review (10 CFR Part 51)
-Environmental report
National Environmental Policy Act (NEPA)
-Preliminary safety analysis report (PSAR)Concurrent reviews
  - Informs Federal decision making
-Each take approximately 18
  - Public disclosure of environmental impacts and other considerations NRCs Environmental Regulations 10 CFR Part 51 Staff prepares an Environmental Impact Statement (EIS) 10
-24 monthsApplication available at: http://adams.nrc.gov/wba/  
 
-ADAMS Accession No.: ML15086A261 and ML15210A182Construction Permit Application 4
Environmental Review (10 CFR Part 51)
Construction Permit Review ProcessEnvironmentalReviewNRC Construction Permit DecisionConstruction PermitApplication submitted to NRCSafetyReviewReview byACRSHearing 5 Acceptance/Sufficiency reviewReview contents of application
Staff conducts environmental site audit                                *Draft NRC issues                       NRC issues EIS draft EIS                       final EIS Process
-Summary description of the facility
    *Scoping Process
-Preliminary design of the facility
* Opportunity for Public Involvement                11
-Preliminary analysis and evaluation of design
 
-Environmental Report Decision to docketDocketing and Sufficiency of Application 6
Proposed Site Location
Manufacture low enriched uranium targetsTransport targets to research reactors
* Discovery Ridge, Columbia, MO
-University of Missouri  
* Approximately 3.0 hectares (7.4 acres)
-Columbia-Oregon State UniversityTransport irradiated targets back to NWMI 99Mo recovered through processing of irradiated targetsFacility Technology 7
* Agricultural land 12
Facility Technology 8Facility OperationsSlide from Public Meeting on April 2, 2015(ML15090A710)
 
Initial NRC staff review of the applicationRequest(s) for additional information (RAI)Safety Evaluation Report (SER) and Environmental Impact Statement (EIS)Advisory Committee on Reactor Safeguards (ACRS) SER reviewMandatory hearingDecision to grant or deny construction permitSafety and Environmental Review Process 9
Proposed Site Location
National Environmental Policy Act (NEPA)-Informs Federal decision making
* Discovery Ridge, Columbia, MO
-Public disclosure of environmental impacts and other considerationsNRC's Environmental Regulations10 CFR Part 51Staff prepares an Environmental Impact Statement (EIS)Environmental Review(10 CFR Part 51) 10 Environmental Review(10 CFR Part 51) 11Staff conducts environmental site auditNRC issues draft EIS*Scoping Process*Draft EIS ProcessNRC issues final EIS* Opportunityfor PublicInvolvement Proposed Site LocationDiscovery Ridge, Columbia, MO Approximately 3.0 hectares (7.4 acres)Agricultural land 12 Proposed Site LocationDiscovery Ridge, Columbia, MO Approximately 3.0 hectares (7.4 acres)Agricultural land 13 Staff Evaluates Impacts to Resources
* Approximately 3.0 hectares (7.4 acres)
-Fish and Wildlife
* Agricultural land 13
-Water and Air Resources
 
-Historical or Cultural Resources-Taxes, Community Development, Environmental Justice
Environmental Impact Statement Staff Evaluates Impacts to Resources
-Human Health
- Fish and Wildlife
-Land Use Environmental Impact Statement 14 Scoping and Public InvolvementWhat is unique about your community?What local environmental issues should the NRC examine?What reasonable alternatives are appropriate for the area?
- Water and Air Resources
15 Role of Public Comments on the Environmental ReviewLicensing DecisionEnvironmental Impact StatementSafety Evaluation ReportHearingAdvisory Committee on Reactor Safeguards Independent ReviewPublic Comments on Environmental ReviewConstruction PermitApplication 16 How to Submit Comments on the Environmental ReviewOnline at http://www.regulations.govEnter ID :Comments will not be edited to remove identifying informationComments must be submitted by January 4, 2016 NRC-2013-0235 17 How to Submit Comments on the Environmental Reviewhttp://www.regulations.gov 18 By mail (please reference NWMI construction permit):Ms. Cindy BladeyChief, Rules, Announcements, and Directives BranchOffice of Administration, Mail stop: OWFN H08US Nuclear Regulatory Commission Washington, DC 20555-0001Comments will not be edited to remove identifying informationComments must be submitted by January 4, 2016How to Submit Comments on the Environmental Review 19 Where to view documentsEnvironmental Report located at:Daniel Boone Regional Library 100 W BroadwayColumbia, MO 65203Environmental Report can also be viewed on NRC's Web site: http://adams.nrc.gov/wba
- Historical or Cultural Resources
/Accession Number: ML15086A261 20 Project Manager InformationNancy Martinez (Environmental)(800) 368-5642 ext. 2719Nancy.Martinez@nrc.govMichael Balazik (Safety)
- Taxes, Community Development, Environmental Justice
(800) 368-5642 ext. 2856Michael.Balazik@nrc.gov 21}}
- Human Health
- Land Use 14
 
Scoping and Public Involvement What is unique about your community?
What local environmental issues should the NRC examine?
What reasonable alternatives are appropriate for the area?
15
 
Role of Public Comments on the Environmental Review Public Comments on Environmental Review Environmental Impact Statement Safety                              Advisory Committee on Evaluation                              Reactor Safeguards Report                                Independent Review Licensing Decision Construction Permit                            Hearing Application 16
 
How to Submit Comments on the Environmental Review Online at http://www.regulations.gov Enter ID :     NRC-2013-0235 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 17
 
How to Submit Comments on the Environmental Review http://www.regulations.gov 18
 
How to Submit Comments on the Environmental Review By mail (please reference NWMI construction permit):
Ms. Cindy Bladey Chief, Rules, Announcements, and Directives Branch Office of Administration, Mail stop: OWFN-12-H08 US Nuclear Regulatory Commission Washington, DC 20555-0001 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 19
 
Where to view documents Environmental Report located at:
* Daniel Boone Regional Library 100 W Broadway Columbia, MO 65203 Environmental Report can also be viewed on NRCs Web site: http://adams.nrc.gov/wba/
Accession Number: ML15086A261 20
 
Project Manager Information Nancy Martinez (Environmental)
(800) 368-5642 ext. 2719 Nancy.Martinez@nrc.gov Michael Balazik (Safety)
(800) 368-5642 ext. 2856 Michael.Balazik@nrc.gov 21
 
Northwest Medical Isotopes, LLC (NWMI)
Construction Permit Review Process and Environmental Scoping Meeting December 8, 2015
 
Purpose of Todays Meeting Provide overview of construction permit review process
  - Safety review
  - Environmental review Receive public input on environmental review 2
 
NRC Regulatory Oversight NRCs Governing Statutes
- Atomic Energy Act of 1954, as Amended
- National Environmental Policy Act (NEPA)
NRCs Mission
- Protect Public Health and Safety
- Promote Common Defense and Security 3
 
Construction Permit Application Construction permit application
  - Environmental report
  - Preliminary safety analysis report (PSAR)
Concurrent reviews
  - Each take approximately 18-24 months Application available at: http://adams.nrc.gov/wba/
  - ADAMS Accession No.: ML15086A261 and ML15210A182 4
 
Construction Permit Review Process Safety Review Review by ACRS Construction Permit NRC Construction Application        Hearing Permit Decision submitted to NRC Environmental Review 5
 
Docketing and Sufficiency of Application Acceptance/Sufficiency review Review contents of application
  - Summary description of the facility
  - Preliminary design of the facility
  - Preliminary analysis and evaluation of design
  - Environmental Report Decision to docket 6
 
Facility Technology Manufacture low enriched uranium targets Transport targets to research reactors
  - University of Missouri - Columbia
  - Oregon State University Transport irradiated targets back to NWMI 99Mo recovered through processing of irradiated targets 7
 
Facility Technology Slide from Public Meeting on April 2, 2015 Facility Operations (ML15090A710) 8
 
Safety and Environmental Review Process Initial NRC staff review of the application Request(s) for additional information (RAI)
Safety Evaluation Report (SER) and Environmental Impact Statement (EIS)
Advisory Committee on Reactor Safeguards (ACRS) SER review Mandatory hearing Decision to grant or deny construction permit                                    9
 
Environmental Review (10 CFR Part 51)
National Environmental Policy Act (NEPA)
  - Informs Federal decision making
  - Public disclosure of environmental impacts and other considerations NRCs Environmental Regulations 10 CFR Part 51 Staff prepares an Environmental Impact Statement (EIS) 10
 
Environmental Review (10 CFR Part 51)
Staff conducts environmental site audit                                *Draft NRC issues                       NRC issues EIS draft EIS                       final EIS Process
    *Scoping Process
* Opportunity for Public Involvement                11
 
Proposed Site Location
* Discovery Ridge, Columbia, MO
* Approximately 3.0 hectares (7.4 acres)
* Agricultural land 12
 
Proposed Site Location
* Discovery Ridge, Columbia, MO
* Approximately 3.0 hectares (7.4 acres)
* Agricultural land 13
 
Environmental Impact Statement Staff Evaluates Impacts to Resources
- Fish and Wildlife
- Water and Air Resources
- Historical or Cultural Resources
- Taxes, Community Development, Environmental Justice
- Human Health
- Land Use 14
 
Scoping and Public Involvement What is unique about your community?
What local environmental issues should the NRC examine?
What reasonable alternatives are appropriate for the area?
15
 
Role of Public Comments on the Environmental Review Public Comments on Environmental Review Environmental Impact Statement Safety                              Advisory Committee on Evaluation                              Reactor Safeguards Report                                Independent Review Licensing Decision Construction Permit                            Hearing Application 16
 
How to Submit Comments on the Environmental Review Online at http://www.regulations.gov Enter ID :     NRC-2013-0235 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 17
 
How to Submit Comments on the Environmental Review http://www.regulations.gov 18
 
How to Submit Comments on the Environmental Review By mail (please reference NWMI construction permit):
Ms. Cindy Bladey Chief, Rules, Announcements, and Directives Branch Office of Administration, Mail stop: OWFN-12-H08 US Nuclear Regulatory Commission Washington, DC 20555-0001 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 19
 
Where to view documents Environmental Report located at:
* Daniel Boone Regional Library 100 W Broadway Columbia, MO 65203 Environmental Report can also be viewed on NRCs Web site: http://adams.nrc.gov/wba/
Accession Number: ML15086A261 20
 
Project Manager Information Nancy Martinez (Environmental)
(800) 368-5642 ext. 2719 Nancy.Martinez@nrc.gov Michael Balazik (Safety)
(800) 368-5642 ext. 2856 Michael.Balazik@nrc.gov 21}}

Revision as of 03:47, 31 October 2019

Nwmi Scoping Meeting Slides
ML15337A172
Person / Time
Site: Northwest Medical Isotopes
Issue date: 12/08/2015
From: Martinez N
Division of License Renewal
To:
References
Download: ML15337A172 (21)


Text

Northwest Medical Isotopes, LLC (NWMI)

Construction Permit Review Process and Environmental Scoping Meeting December 8, 2015

Purpose of Todays Meeting Provide overview of construction permit review process

- Safety review

- Environmental review Receive public input on environmental review 2

NRC Regulatory Oversight NRCs Governing Statutes

- Atomic Energy Act of 1954, as Amended

- National Environmental Policy Act (NEPA)

NRCs Mission

- Protect Public Health and Safety

- Promote Common Defense and Security 3

Construction Permit Application Construction permit application

- Environmental report

- Preliminary safety analysis report (PSAR)

Concurrent reviews

- Each take approximately 18-24 months Application available at: http://adams.nrc.gov/wba/

- ADAMS Accession No.: ML15086A261 and ML15210A182 4

Construction Permit Review Process Safety Review Review by ACRS Construction Permit NRC Construction Application Hearing Permit Decision submitted to NRC Environmental Review 5

Docketing and Sufficiency of Application Acceptance/Sufficiency review Review contents of application

- Summary description of the facility

- Preliminary design of the facility

- Preliminary analysis and evaluation of design

- Environmental Report Decision to docket 6

Facility Technology Manufacture low enriched uranium targets Transport targets to research reactors

- University of Missouri - Columbia

- Oregon State University Transport irradiated targets back to NWMI 99Mo recovered through processing of irradiated targets 7

Facility Technology Slide from Public Meeting on April 2, 2015 Facility Operations (ML15090A710) 8

Safety and Environmental Review Process Initial NRC staff review of the application Request(s) for additional information (RAI)

Safety Evaluation Report (SER) and Environmental Impact Statement (EIS)

Advisory Committee on Reactor Safeguards (ACRS) SER review Mandatory hearing Decision to grant or deny construction permit 9

Environmental Review (10 CFR Part 51)

National Environmental Policy Act (NEPA)

- Informs Federal decision making

- Public disclosure of environmental impacts and other considerations NRCs Environmental Regulations 10 CFR Part 51 Staff prepares an Environmental Impact Statement (EIS) 10

Environmental Review (10 CFR Part 51)

Staff conducts environmental site audit *Draft NRC issues NRC issues EIS draft EIS final EIS Process

  • Scoping Process
  • Opportunity for Public Involvement 11

Proposed Site Location

  • Discovery Ridge, Columbia, MO
  • Approximately 3.0 hectares (7.4 acres)
  • Agricultural land 12

Proposed Site Location

  • Discovery Ridge, Columbia, MO
  • Approximately 3.0 hectares (7.4 acres)
  • Agricultural land 13

Environmental Impact Statement Staff Evaluates Impacts to Resources

- Fish and Wildlife

- Water and Air Resources

- Historical or Cultural Resources

- Taxes, Community Development, Environmental Justice

- Human Health

- Land Use 14

Scoping and Public Involvement What is unique about your community?

What local environmental issues should the NRC examine?

What reasonable alternatives are appropriate for the area?

15

Role of Public Comments on the Environmental Review Public Comments on Environmental Review Environmental Impact Statement Safety Advisory Committee on Evaluation Reactor Safeguards Report Independent Review Licensing Decision Construction Permit Hearing Application 16

How to Submit Comments on the Environmental Review Online at http://www.regulations.gov Enter ID : NRC-2013-0235 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 17

How to Submit Comments on the Environmental Review http://www.regulations.gov 18

How to Submit Comments on the Environmental Review By mail (please reference NWMI construction permit):

Ms. Cindy Bladey Chief, Rules, Announcements, and Directives Branch Office of Administration, Mail stop: OWFN-12-H08 US Nuclear Regulatory Commission Washington, DC 20555-0001 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 19

Where to view documents Environmental Report located at:

  • Daniel Boone Regional Library 100 W Broadway Columbia, MO 65203 Environmental Report can also be viewed on NRCs Web site: http://adams.nrc.gov/wba/

Accession Number: ML15086A261 20

Project Manager Information Nancy Martinez (Environmental)

(800) 368-5642 ext. 2719 Nancy.Martinez@nrc.gov Michael Balazik (Safety)

(800) 368-5642 ext. 2856 Michael.Balazik@nrc.gov 21

Northwest Medical Isotopes, LLC (NWMI)

Construction Permit Review Process and Environmental Scoping Meeting December 8, 2015

Purpose of Todays Meeting Provide overview of construction permit review process

- Safety review

- Environmental review Receive public input on environmental review 2

NRC Regulatory Oversight NRCs Governing Statutes

- Atomic Energy Act of 1954, as Amended

- National Environmental Policy Act (NEPA)

NRCs Mission

- Protect Public Health and Safety

- Promote Common Defense and Security 3

Construction Permit Application Construction permit application

- Environmental report

- Preliminary safety analysis report (PSAR)

Concurrent reviews

- Each take approximately 18-24 months Application available at: http://adams.nrc.gov/wba/

- ADAMS Accession No.: ML15086A261 and ML15210A182 4

Construction Permit Review Process Safety Review Review by ACRS Construction Permit NRC Construction Application Hearing Permit Decision submitted to NRC Environmental Review 5

Docketing and Sufficiency of Application Acceptance/Sufficiency review Review contents of application

- Summary description of the facility

- Preliminary design of the facility

- Preliminary analysis and evaluation of design

- Environmental Report Decision to docket 6

Facility Technology Manufacture low enriched uranium targets Transport targets to research reactors

- University of Missouri - Columbia

- Oregon State University Transport irradiated targets back to NWMI 99Mo recovered through processing of irradiated targets 7

Facility Technology Slide from Public Meeting on April 2, 2015 Facility Operations (ML15090A710) 8

Safety and Environmental Review Process Initial NRC staff review of the application Request(s) for additional information (RAI)

Safety Evaluation Report (SER) and Environmental Impact Statement (EIS)

Advisory Committee on Reactor Safeguards (ACRS) SER review Mandatory hearing Decision to grant or deny construction permit 9

Environmental Review (10 CFR Part 51)

National Environmental Policy Act (NEPA)

- Informs Federal decision making

- Public disclosure of environmental impacts and other considerations NRCs Environmental Regulations 10 CFR Part 51 Staff prepares an Environmental Impact Statement (EIS) 10

Environmental Review (10 CFR Part 51)

Staff conducts environmental site audit *Draft NRC issues NRC issues EIS draft EIS final EIS Process

  • Scoping Process
  • Opportunity for Public Involvement 11

Proposed Site Location

  • Discovery Ridge, Columbia, MO
  • Approximately 3.0 hectares (7.4 acres)
  • Agricultural land 12

Proposed Site Location

  • Discovery Ridge, Columbia, MO
  • Approximately 3.0 hectares (7.4 acres)
  • Agricultural land 13

Environmental Impact Statement Staff Evaluates Impacts to Resources

- Fish and Wildlife

- Water and Air Resources

- Historical or Cultural Resources

- Taxes, Community Development, Environmental Justice

- Human Health

- Land Use 14

Scoping and Public Involvement What is unique about your community?

What local environmental issues should the NRC examine?

What reasonable alternatives are appropriate for the area?

15

Role of Public Comments on the Environmental Review Public Comments on Environmental Review Environmental Impact Statement Safety Advisory Committee on Evaluation Reactor Safeguards Report Independent Review Licensing Decision Construction Permit Hearing Application 16

How to Submit Comments on the Environmental Review Online at http://www.regulations.gov Enter ID : NRC-2013-0235 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 17

How to Submit Comments on the Environmental Review http://www.regulations.gov 18

How to Submit Comments on the Environmental Review By mail (please reference NWMI construction permit):

Ms. Cindy Bladey Chief, Rules, Announcements, and Directives Branch Office of Administration, Mail stop: OWFN-12-H08 US Nuclear Regulatory Commission Washington, DC 20555-0001 Comments will not be edited to remove identifying information Comments must be submitted by January 4, 2016 19

Where to view documents Environmental Report located at:

  • Daniel Boone Regional Library 100 W Broadway Columbia, MO 65203 Environmental Report can also be viewed on NRCs Web site: http://adams.nrc.gov/wba/

Accession Number: ML15086A261 20

Project Manager Information Nancy Martinez (Environmental)

(800) 368-5642 ext. 2719 Nancy.Martinez@nrc.gov Michael Balazik (Safety)