{{#Wiki_filter:Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar-18Acceptance Review - Action: Issuance of acceptance letter.4-May-18 FRN (Opportunity to request a hearing (30 d))
{{#Wiki_filter:From:             Diaz Maldonado, Marilyn To:               weave1dw@westinghouse.com; Spalding, Amanda J Cc:               Johnson, Robert; Erlanger, Craig; Smith, Brian
11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 From: Diaz Maldonado, Marilyn To: weave1dw@westinghouse.com
; Spalding, Amanda J Cc: Johnson, Robert
; Erlanger, Craig
; Smith, Brian


==Subject:==
==Subject:==
Westinghouse Transfer of Control Application/Review - Schedule Date: Monday, May 07, 2018 11:16:00 AM Hi Doug, During our last conference call, you requested an understanding of the NRC staff's milestones going forward regarding the Transfer of Control review.
Westinghouse Transfer of Control Application/Review - Schedule Date:             Monday, May 07, 2018 11:16:00 AM Hi Doug, During our last conference call, you requested an understanding of the NRC staffs milestones going forward regarding the Transfer of Control review. Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule.
Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule.                   If you have any questions, please let me know.
Westinghouse License Transfer Application Review Schedule Major Milestones                                      Completion Date Application Date                                                      21-Mar-18 Application received and docketed                                      27-Mar-18 Acceptance Review - Action: Issuance of acceptance                    4-May-18 letter.
Thanks, Marilyn Diaz
FRN (Opportunity to request a hearing (30 d))                          11-May-18 Issue RAIs (if any)                                                    31-May-18 Start concurrence process of the SER                                  13-Jun-18 FCSE Division Director Review and Concurrence                          9-Jul-18 NMSS Office concurrence and signature                                  18-Jul-18 If you have any questions, please let me know.
, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110}}
: Thanks, Marilyn Diaz, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110}}

Revision as of 01:50, 21 October 2019

W05/07/2018 E-mail Westinghouse Transfer of Control Application/Review - Schedule
ML18141A642
Person / Time
Issue date: 05/07/2018
From: Diaz-Maldonado M
Fuel Manufacturing Branch
To: Weaver D
Westinghouse
Diaz M
References
Download: ML18141A642 (1)


Text

From: Diaz Maldonado, Marilyn To: weave1dw@westinghouse.com; Spalding, Amanda J Cc: Johnson, Robert; Erlanger, Craig; Smith, Brian

Subject:

Westinghouse Transfer of Control Application/Review - Schedule Date: Monday, May 07, 2018 11:16:00 AM Hi Doug, During our last conference call, you requested an understanding of the NRC staffs milestones going forward regarding the Transfer of Control review. Below is a detailed schedule of the major milestones. Please note that these are target dates and are subject to change depending on many factors. We will promptly communicate any significant changes to this schedule.

Westinghouse License Transfer Application Review Schedule Major Milestones Completion Date Application Date 21-Mar-18 Application received and docketed 27-Mar-18 Acceptance Review - Action: Issuance of acceptance 4-May-18 letter.

FRN (Opportunity to request a hearing (30 d)) 11-May-18 Issue RAIs (if any) 31-May-18 Start concurrence process of the SER 13-Jun-18 FCSE Division Director Review and Concurrence 9-Jul-18 NMSS Office concurrence and signature 18-Jul-18 If you have any questions, please let me know.

Thanks, Marilyn Diaz, Project Manager/Chemical Engineer U.S Nuclear Regulatory Commission NMSS/FCSE/FMB Washington, DC 20555 (301)415-7110