{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 July 10, 2018 Administrative Judge                                    Administrative Judge Paul S. Ryerson, Chair                                   Dr. Sue H. Abreu Atomic Safety and Licensing Board Panel                  Atomic Safety and Licensing Board Panel Mail Stop T-3 F23                                        Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission                       U.S. Nuclear Regulatory Commission Washington, DC 20555-0001                                Washington, DC 20555-0001 Administrative Judge Dr. Gary S. Arnold Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 In the Matter of TENNESSEE VALLEY AUTHORITY (Clinch River Nuclear Site Early Site Permit Application)
- 0001       July 10 , 2018   Administrative Judge Paul S. Ryerson, Chair Atomic Safety and Licensing Board Panel Mail Stop T
Docket No. 52-047-ESP
-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555
-0001  Administrative Judge Dr. Gary S. Arnold Atomic Safety and Licensing Board Panel Mail Stop T
-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555
-0001 Administrative Judge Dr. Sue H. Abreu Atomic Safety and Licensing Board Panel Mail Stop T
-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001   In the Matter of TENNESSEE VALLEY AUTHORITY (Clinch River Nuclear Site Early Site Permit Application) Docket No. 52
-047-ESP  


==Dear Administrative Judges:==
==Dear Administrative Judges:==


Pursuant to the Atomic Safety and Licensing Board's "Initial Scheduling Order," dated December 7, 2017, the staff of the U.S. Nuclear Regulatory Commission ("Staff") herein notifies the Licensing Board and the parties that the hearing file has been provided for this proceeding
Pursuant to the Atomic Safety and Licensing Boards Initial Scheduling Order, dated December 7, 2017, the staff of the U.S. Nuclear Regulatory Commission (Staff) herein notifies the Licensing Board and the parties that the hearing file has been provided for this proceeding.
. This is the NRC staff's eighth hearing file and mandatory disclosures update. Materials in the hearing file may be accessed through the Agencywide Documents Access and Management System ("ADAMS").
This is the NRC staffs eighth hearing file and mandatory disclosures update. Materials in the hearing file may be accessed through the Agencywide Documents Access and Management System (ADAMS). An index containing the ADAMS accession number, date, and title or description of each item in the initial disclosure is appended hereto as Attachment 1.
An index containing the ADAMS accession number, date, and title or description of each item in the initial disclosure is appended hereto as Attachment 1.
On or about July 20, 2018, the documents identified in the hearing file may be accessed through ADAMS or through the Electronic Hearing Docket (EHD), which may be accessed at https://adams.nrc.gov/ehd/. The hearing file will be contained in the Staff Discovery Materials tab of the EHD, in a sub-folder entitled, Clinch River Hearing File, Update 8 in the Clinch River Nuclear Site ESP" folder. Any party who seeks access to a document listed in the NRC staff hearing file index prior to it populating the publicly available folder may contact NRC staff counsel.
On or about July 20, 2018, the documents identified in the hearing file may be accessed through ADAMS or through the Electronic Hearing Docket ("EHD"), which may be accessed at https://adams.nrc.gov/ehd/. The hearing file will be contained in the "Staff Discovery Materials" tab of the EHD, in a sub
 
-folder entitled, "Clinch River Hearing Fil e, Update 8" in the "Clinch River Nuclear Site ESP" folder. Any party who seeks access to a document listed in the NRC staff hearing file index prior to it populating the publicly available folder may contact NRC staff counsel.
Judge Ryerson                                                               July 10, 2018 Judge Arnold Judge Abreu Further, pursuant to 10 C.F.R. § 2.336(c), attached is the Affidavit of Allen Fetter, certifying that all relevant materials required by this section have been disclosed, and that the disclosures are accurate and complete as to documents identified by July 3, 2018.
Judge Ryerson July 1 0 , 2018 Judge Arnold Judge Abreu Further, pursuant to 10 C.F.R. § 2.336(c), attached is the Affidavit of Allen Fetter, certifying that all relevant materials required by this section have been disclosed, and that the disclosures are accurate and complete as to document s i dentified by July 3 , 2018. Finally, the NRC Staff notes that it has made a good faith effort to identify and characterize all documents meeting the criteria of 10 C.F.R. § 2.336(b), as modified by the "Agreement of the Parties Regarding Mandatory Discovery Disclosures," dated November 8, 2017, and 10 C.F.R.
Finally, the NRC Staff notes that it has made a good faith effort to identify and characterize all documents meeting the criteria of 10 C.F.R. § 2.336(b), as modified by the Agreement of the Parties Regarding Mandatory Discovery Disclosures, dated November 8, 2017, and 10 C.F.R.
§ 2.1203 in this proceeding. In identifying these documents, the Staff does not concede their relevance to the issues to be decided in this proceeding.
§ 2.1203 in this proceeding. In identifying these documents, the Staff does not concede their relevance to the issues to be decided in this proceeding.
Sincerely, /Signed (electronically) by/
Sincerely,
                                                            /Signed (electronically) by/
Ann Hove Counsel for NRC Staff
Ann Hove Counsel for NRC Staff


==Enclosures:==
==Enclosures:==
Attachment 1 - Hearing File Index, Update 8 Affidavit of Allen Fetter cc w/Encls.:    Service List


Attachment 1  
Attachment 1 - Clinch River Nuclear Site ESP Hearing File Index Update 8 - July 10, 2018 Accession  Document ID#                             Title Number     Date 08-001 ML18183A604 06/19/2018   2018/06/19 Clinch River ESP - [External_Sender] Aug 17 Recurring Meeting 08-002 ML18183A605 06/25/2018   2018/06/25 Clinch River ESP - reading room access request 08-003 ML18183A603 06/28/2018   2018/06/28 Clinch River ESP - [External_Sender] Programatic Consultation Discsuion Meeting Request 08-004 ML18180A386 06/29/2018   2018/06/29 - Comment (7) E-mail regarding Clinch River ESP Draft EIS
- Hearing File Index, Update 8 Affidavit of Allen Fetter  cc w/Encls.: Service List   
- Clinch River Nuclear Site ESP Hearing File Index Update 8  
- July 10 , 2018   ID# Accession Number Document Date Title 08-001 ML18183A604 06/19/2018 2018/06/19 Clinch River ESP  
- [External_Sender] Aug 17 Recurring Meeting 08-002 ML18183A605 06/25/2018 2018/06/25 Clinch River ESP  
- reading room access request 08-003 ML18183A603 06/28/2018 2018/06/28 Clinch River ESP  
- [External_Sender] Programatic Consultation Discsuion Meeting Request 08-004 ML18180A386 06/29/2018 2018/06/29  
- Comment (7) E
-mail regarding Clinch River ESP Draft EIS


July 10 , 2018 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of ) ) TENNESSEE VALLEY AUTHORITY ) Docket Nos.
July 10, 2018 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of                                       )
52-047-ESP ) (Clinch River Nuclear Site) ) AFFIDAVIT OF ALLEN FETTER CONCERNING MANDATORY DISCLOSURE REQUIREMENT OF 10 C.F.R. § 2.336(b)
                                                        )
TENNESSEE VALLEY AUTHORITY                             )       Docket Nos. 52-047-ESP
                                                        )
(Clinch River Nuclear Site)                             )
AFFIDAVIT OF ALLEN FETTER CONCERNING MANDATORY DISCLOSURE REQUIREMENT OF 10 C.F.R. § 2.336(b)
I, Allen Fetter, do hereby state as follows:
I, Allen Fetter, do hereby state as follows:
: 1. I am employed as a Senior Project Manager in the U.S. Nuclear Regulatory Commission's (NRC) Office of New Reactors. I currently serve as a project manager for the Clinch River Nuclear Site Early Site Permit ("ESP") Application review. 2. I hereby certify that all relevant materials required to be disclosed pursuant to 10 C.F.R. §§ 2.336 (b) and (c) and 2.1203(a)(1) in the captioned proceeding have been disclosed, and that the disclosures are accurate and complete for documents identified as of July 3, 2018. 3. I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information and belief. Executed in Accord with 10 CFR 2.304(d)
: 1.       I am employed as a Senior Project Manager in the U.S. Nuclear Regulatory Commissions (NRC) Office of New Reactors. I currently serve as a project manager for the Clinch River Nuclear Site Early Site Permit (ESP) Application review.
Allen Fetter U.S. Nuclear Regulatory Commission Senior Project Manager, Office of New Reactors (301) 415-8556 Allen.Fetter@nrc.gov Washington, DC 20555
: 2.       I hereby certify that all relevant materials required to be disclosed pursuant to 10 C.F.R. §§ 2.336 (b) and (c) and 2.1203(a)(1) in the captioned proceeding have been disclosed, and that the disclosures are accurate and complete for documents identified as of July 3, 2018.
-0001 Date signed: July 10, 2018 Executed in Rockville, Maryland this 10 th d ay of July 10 , 2018 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of ) ) TENNESSEE VALLEY AUTHORITY ) Docket Nos.
: 3.       I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information and belief.
52-047-ESP ) (Clinch River Nuclear Site) )   CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Letter to the Atomic Safety and Licensing Board regarding the Clinch River Nuclear Site Hearing File Update Seven, including: Attachment 1  
Executed in Accord with 10 CFR 2.304(d)
- Clinch River Nuclear Site ESP Hearing File Index, NRC Staff Disclosure  
Allen Fetter U.S. Nuclear Regulatory Commission Senior Project Manager, Office of New Reactors (301) 415-8556 Allen.Fetter@nrc.gov Washington, DC 20555-0001 Date signed: July 10, 2018 Executed in Rockville, Maryland this 10th day of July 10, 2018
- Update 8; and Affida v it of Allen Fetter, dated July 10, 2018, in the above
 
-captioned proceeding have been served upon the Electronic Information Exchange, the NRC's E-Filing System, this 10th day of July , 2018.   /Signed (electronically) by/
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of                                       )
Ann Hove Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop  
                                                        )
- O-14 A44 Washington, DC 20555 Telephone:
TENNESSEE VALLEY AUTHORITY                             )       Docket Nos. 52-047-ESP
(301) 415-0963 E-mail: Ann.Hove@nrc.gov Date of signature: July 10 , 2018}}
                                                        )
(Clinch River Nuclear Site)                             )
CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Letter to the Atomic Safety and Licensing Board regarding the Clinch River Nuclear Site Hearing File Update Seven, including: Attachment 1 -
Clinch River Nuclear Site ESP Hearing File Index, NRC Staff Disclosure - Update 8; and Affidavit of Allen Fetter, dated July 10, 2018, in the above-captioned proceeding have been served upon the Electronic Information Exchange, the NRCs E-Filing System, this 10th day of July, 2018.
                                                        /Signed (electronically) by/
Ann Hove Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-14 A44 Washington, DC 20555 Telephone: (301) 415-0963 E-mail: Ann.Hove@nrc.gov Date of signature: July 10, 2018}}

Latest revision as of 21:49, 20 October 2019

NRC Staff Hearing File Update 8
ML18191B233
Person / Time
Site: Clinch River
Issue date: 07/10/2018
From: Hove A
NRC/OGC
To: Sue Abreu, Gary Arnold, Paul Ryerson
Atomic Safety and Licensing Board Panel
SECY RAS
References
52-047-ESP, ASLBP 17-954-01-ESP-BD01, RAS 54362
Download: ML18191B233 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, DC 20555 - 0001 July 10, 2018 Administrative Judge Administrative Judge Paul S. Ryerson, Chair Dr. Sue H. Abreu Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 Administrative Judge Dr. Gary S. Arnold Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 In the Matter of TENNESSEE VALLEY AUTHORITY (Clinch River Nuclear Site Early Site Permit Application)

Docket No. 52-047-ESP

Dear Administrative Judges:

Pursuant to the Atomic Safety and Licensing Boards Initial Scheduling Order, dated December 7, 2017, the staff of the U.S. Nuclear Regulatory Commission (Staff) herein notifies the Licensing Board and the parties that the hearing file has been provided for this proceeding.

This is the NRC staffs eighth hearing file and mandatory disclosures update. Materials in the hearing file may be accessed through the Agencywide Documents Access and Management System (ADAMS). An index containing the ADAMS accession number, date, and title or description of each item in the initial disclosure is appended hereto as Attachment 1.

On or about July 20, 2018, the documents identified in the hearing file may be accessed through ADAMS or through the Electronic Hearing Docket (EHD), which may be accessed at https://adams.nrc.gov/ehd/. The hearing file will be contained in the Staff Discovery Materials tab of the EHD, in a sub-folder entitled, Clinch River Hearing File, Update 8 in the Clinch River Nuclear Site ESP" folder. Any party who seeks access to a document listed in the NRC staff hearing file index prior to it populating the publicly available folder may contact NRC staff counsel.

Judge Ryerson July 10, 2018 Judge Arnold Judge Abreu Further, pursuant to 10 C.F.R. § 2.336(c), attached is the Affidavit of Allen Fetter, certifying that all relevant materials required by this section have been disclosed, and that the disclosures are accurate and complete as to documents identified by July 3, 2018.

Finally, the NRC Staff notes that it has made a good faith effort to identify and characterize all documents meeting the criteria of 10 C.F.R. § 2.336(b), as modified by the Agreement of the Parties Regarding Mandatory Discovery Disclosures, dated November 8, 2017, and 10 C.F.R.

§ 2.1203 in this proceeding. In identifying these documents, the Staff does not concede their relevance to the issues to be decided in this proceeding.

Sincerely,

/Signed (electronically) by/

Ann Hove Counsel for NRC Staff

Enclosures:

Attachment 1 - Hearing File Index, Update 8 Affidavit of Allen Fetter cc w/Encls.: Service List

Attachment 1 - Clinch River Nuclear Site ESP Hearing File Index Update 8 - July 10, 2018 Accession Document ID# Title Number Date 08-001 ML18183A604 06/19/2018 2018/06/19 Clinch River ESP - [External_Sender] Aug 17 Recurring Meeting 08-002 ML18183A605 06/25/2018 2018/06/25 Clinch River ESP - reading room access request 08-003 ML18183A603 06/28/2018 2018/06/28 Clinch River ESP - [External_Sender] Programatic Consultation Discsuion Meeting Request 08-004 ML18180A386 06/29/2018 2018/06/29 - Comment (7) E-mail regarding Clinch River ESP Draft EIS

July 10, 2018 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 52-047-ESP

)

(Clinch River Nuclear Site) )

AFFIDAVIT OF ALLEN FETTER CONCERNING MANDATORY DISCLOSURE REQUIREMENT OF 10 C.F.R. § 2.336(b)

I, Allen Fetter, do hereby state as follows:

1. I am employed as a Senior Project Manager in the U.S. Nuclear Regulatory Commissions (NRC) Office of New Reactors. I currently serve as a project manager for the Clinch River Nuclear Site Early Site Permit (ESP) Application review.
2. I hereby certify that all relevant materials required to be disclosed pursuant to 10 C.F.R. §§ 2.336 (b) and (c) and 2.1203(a)(1) in the captioned proceeding have been disclosed, and that the disclosures are accurate and complete for documents identified as of July 3, 2018.
3. I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information and belief.

Executed in Accord with 10 CFR 2.304(d)

Allen Fetter U.S. Nuclear Regulatory Commission Senior Project Manager, Office of New Reactors (301) 415-8556 Allen.Fetter@nrc.gov Washington, DC 20555-0001 Date signed: July 10, 2018 Executed in Rockville, Maryland this 10th day of July 10, 2018

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

TENNESSEE VALLEY AUTHORITY ) Docket Nos. 52-047-ESP

)

(Clinch River Nuclear Site) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing Letter to the Atomic Safety and Licensing Board regarding the Clinch River Nuclear Site Hearing File Update Seven, including: Attachment 1 -

Clinch River Nuclear Site ESP Hearing File Index, NRC Staff Disclosure - Update 8; and Affidavit of Allen Fetter, dated July 10, 2018, in the above-captioned proceeding have been served upon the Electronic Information Exchange, the NRCs E-Filing System, this 10th day of July, 2018.

/Signed (electronically) by/

Ann Hove Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-14 A44 Washington, DC 20555 Telephone: (301) 415-0963 E-mail: Ann.Hove@nrc.gov Date of signature: July 10, 2018