{{Adams
#REDIRECT [[TMI-13-093, Withdrawal of the Three Mile Island Nuclear Power Station, Unit 1, Technical Specification Change Request 352, Revise Technical Specification 3.14.2 and the Licensing Basis Flood Hazard Contained in the Updated Final Safety Analysis Repor]]
| number = ML13175A230
| issue date = 06/24/2013
| title = Withdrawal of the Three Mile Island Nuclear Power Station, Unit 1, Technical Specification Change Request 352, Revise Technical Specification 3.14.2 and the Licensing Basis Flood Hazard Contained in the Updated Final Safety Analysis Report
| author name = Barstow J
| author affiliation = Exelon Generation Co, LLC
| addressee name =
| addressee affiliation = NRC/Document Control Desk, NRC/NRR
| docket = 05000289
| license number = DPR-050
| contact person =
| case reference number = TMI-13-093
| document type = Letter
| page count = 1
| project =
| stage = Withdrawal
}}
 
=Text=
{{#Wiki_filter:TMI-13-093 June 24, 2013 U.S. Nuclear Regulatory Commission A TIN: Document Control Desk Washington, DC Three Mile Island Nuclear Station, Unit 1 Renewed Facility Operating License No. DPR-50 NRC Docket No. 50-289 10 CFR 50.90
 
==Subject:==
Withdrawal of the Three Mile Island Nuclear Power Station, Unit 1, Technical Specification Change Request 352, Revise Technical Specification 3.14.2 and the Licensing Basis Flood Hazard contained in the Updated Final Safety Analysis Report
 
==References:==
: 1. Letter from M. D. Jesse (Exelon Generation Company, LLC) to U.S. Nuclear Regulatory Commission, "Three Mile Island Nuclear Power Station, Unit 1, Technical Specification Change Request 352, Revise Technical Specification 3.14.2 and the Licensing Basis Flood Hazard contained in the Updated Final Safety Analysis Report," dated April 10, 2013 By letter to the Nuclear Regulatory Commission (NRC) dated April 10, 2013, Exelon Generation Company, LLC, (Exelon) submitted an amendment request to revise the Technical Specifications (TS) for Three Mile Island (TMI), Unit 1 (Reference 1). During a teleconference on June 10, 2013, the NRC provided results of the NRC's acceptance review of the Reference 1 amendment request. The NRC concluded that the Reference 1 amendment request cannot be reviewed until open issues are resolved with the ongoing TMI, Unit 1 Fukushima Near-Term Task Force Flooding Hazard submittals and associated design analyses.
As a result, Exelon is withdrawing this amendment request. If you have any questions or require additional information, please contact Wendy Croft at (610) 765-5726.
James Director, Licensing and Regulatory Affairs Exelon Generation Company, LLC cc: USNRC Region I, Regional Administrator USNRC Project Manager, TMI, Unit 1 USNRC Senior Resident Inspector, TMI, Unit 1 Director, Bureau of Radiation Protection, PA Department of Environmental Resources Chairman, Board of County Commissioners, Dauphin County, PA Chairman, Board of Supervisors, Londonderry Township, PA R. R. Janati, Commonwealth of Pennsylvania}}