WBL-24-008, Emergency Plan Implementing Procedure Revision
ML24060A087 | |
Person / Time | |
---|---|
Site: | Watts Bar |
Issue date: | 02/29/2024 |
From: | Anthony Williams Tennessee Valley Authority |
To: | Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Document Control Desk |
References | |
WBL-24-008 | |
Download: ML24060A087 (1) | |
Similar Documents at Watts Bar | |
---|---|
Category:Emergency Preparedness-Emergency Plan
MONTHYEARCNL-24-040, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2024-05-0808 May 2024
[Table view]Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revisions WBL-24-008, Emergency Plan Implementing Procedure Revision2024-02-29029 February 2024 Emergency Plan Implementing Procedure Revision WBL-24-004, Emergency Plan Implementing Procedure Revision2024-02-15015 February 2024 Emergency Plan Implementing Procedure Revision ML24038A3342024-02-0707 February 2024 Change to South Texas Project Electric Generating Station (Stepgs) Emergency Plan CNL-24-017, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions2024-01-17017 January 2024 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure and Emergency Preparedness Department Procedure Revisions CNL-23-053, Tennessee Valley Authority - Radiological Emergency Plan Revisions2023-07-18018 July 2023 Tennessee Valley Authority - Radiological Emergency Plan Revisions CNL-23-049, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan .2023-06-26026 June 2023 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan . WBL-23-025, Emergency Plan Implementing Procedure Revision2023-05-0505 May 2023 Emergency Plan Implementing Procedure Revision WBL-22-007, Unit 2 - Emergency Plan Implementing Procedure Revision2022-02-17017 February 2022 Unit 2 - Emergency Plan Implementing Procedure Revision CNL-22-016, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2022-02-11011 February 2022 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions CNL-21-067, Tennessee Valley Authority License Amendment Request to Revise Emergency Plan Implementing Procedure Regarding Seismic Event Emergency Action Level Change2022-01-27027 January 2022 Tennessee Valley Authority License Amendment Request to Revise Emergency Plan Implementing Procedure Regarding Seismic Event Emergency Action Level Change WBL-21-046, Unit 2 -Emergency Plan Implementing Procedure Revision2021-09-30030 September 2021 Unit 2 -Emergency Plan Implementing Procedure Revision WBL-21-042, Unit 2 - Emergency Plan Implementing Procedure Revision2021-09-0202 September 2021 Unit 2 - Emergency Plan Implementing Procedure Revision WBL-21-038, Unit 2 - Emergency Plan Implementing Procedure Revision2021-08-0505 August 2021 Unit 2 - Emergency Plan Implementing Procedure Revision ML20199M3802020-07-17017 July 2020 Tennessee Valley Authority - Radiological Emergency Plan Revision CNL-20-060, Tennessee Valley Authority - Radiological Emergency Plan Revision2020-07-17017 July 2020 Tennessee Valley Authority - Radiological Emergency Plan Revision CNL-20-025, Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision2020-03-0404 March 2020 Tennessee Valley Authority - Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-20-022, Emergency Preparedness Department Procedure Revision2020-02-24024 February 2020 Emergency Preparedness Department Procedure Revision L-20-006, Unit 2, Emergency Plan Implementing Procedure Revision2020-02-10010 February 2020 Unit 2, Emergency Plan Implementing Procedure Revision CNL-18-096, Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions2018-07-30030 July 2018 Tennessee Valley Authority - Radiological Emergency Plan and Central Emergency Control Center Emergency Plan Implementing Procedure Revisions ML18057A0432018-02-23023 February 2018 Unit 2 - Emergency Plan Implementing Procedures Revision CNL-16-099, Radiological Emergency Plan Revision2016-06-20020 June 2016 Radiological Emergency Plan Revision CNL-16-012, Radiological Emergency Revision and Central Emergency Control Center Emergency Plan Implementing Procedure Revision2016-01-14014 January 2016 Radiological Emergency Revision and Central Emergency Control Center Emergency Plan Implementing Procedure Revision CNL-15-104, Submittal of Revision 106, Appendix C to Central Emergency Control Center, Radiological Emergency Plan2015-06-15015 June 2015 Submittal of Revision 106, Appendix C to Central Emergency Control Center, Radiological Emergency Plan ML14357A3182014-04-16016 April 2014 Tennessee Valley Authority - Radiological Emergency Plan Revision ML0935006172009-12-14014 December 2009 Transmittal of Radiological Emergency Plan Additional Information ML14357A3192004-04-26026 April 2004 TVA Nuclear Radiological Emergency Plan (Rep), Revision 73 2024-05-08 Category:Letter type:WBL MONTHYEARWBL-24-047, Analysis of Capsule V from the Tennessee Valley Authority Watts Bar Unit 1 Reactor Vessel Radiation Surveillance Program2024-09-25025 September 2024
[Table view]Analysis of Capsule V from the Tennessee Valley Authority Watts Bar Unit 1 Reactor Vessel Radiation Surveillance Program WBL-24-043, Emergency Plan Implementing Procedure Revisions2024-09-16016 September 2024 Emergency Plan Implementing Procedure Revisions WBL-24-040, Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2)2024-08-13013 August 2024 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) WBL-24-034, NRC Regulatory Issue Summary (RIS) 2024-01 - Preparation and Scheduling of Operator Licensing Examinations2024-07-25025 July 2024 NRC Regulatory Issue Summary (RIS) 2024-01 - Preparation and Scheduling of Operator Licensing Examinations WBL-24-030, Emergency Plan Implementing Procedure Revisions2024-07-17017 July 2024 Emergency Plan Implementing Procedure Revisions WBL-24-028, Emergency Plan Implementing Procedure Revisions2024-07-0202 July 2024 Emergency Plan Implementing Procedure Revisions WBL-24-025, Emergency Plan Implementing Procedure Revisions. Includes EPIP-7, Revision 43, Activation and Operation of the Operations Support Center (OSC)2024-05-23023 May 2024 Emergency Plan Implementing Procedure Revisions. Includes EPIP-7, Revision 43, Activation and Operation of the Operations Support Center (OSC) WBL-24-022, Cycle 5 Steam Generator Tube Inspection Report2024-05-16016 May 2024 Cycle 5 Steam Generator Tube Inspection Report WBL-24-023, 2023 Annual Radiological Environmental Operating Report2024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report WBL-24-020, Unit 2 - Annual Non-Radiological Environmental Operating Report - 20232024-05-0707 May 2024 Unit 2 - Annual Non-Radiological Environmental Operating Report - 2023 WBL-24-019, Technical Specification (TS) 5.9.8 - Post Accident Monitoring System (Pams) Report2024-04-30030 April 2024 Technical Specification (TS) 5.9.8 - Post Accident Monitoring System (Pams) Report WBL-24-021, Unit 2, Annual Radioactive Effluent Release Report2024-04-29029 April 2024 Unit 2, Annual Radioactive Effluent Release Report WBL-24-016, Rev. 60 to Radiological Emergency Plan EPIP 1, Emergency Plan Classification Logic2024-04-11011 April 2024 Rev. 60 to Radiological Emergency Plan EPIP 1, Emergency Plan Classification Logic WBL-24-018, Rev. 30 to Radiological Emergency Plan EPIP 14, Radiological Control Response2024-04-11011 April 2024 Rev. 30 to Radiological Emergency Plan EPIP 14, Radiological Control Response WBL-24-011, CFR 50.46 - Annual Report2024-03-21021 March 2024 CFR 50.46 - Annual Report WBL-24-007, Technical Specification (TS) 5.7.2.15 - Explosive Gas and Storage Tank Radioactivity Monitoring Program2024-03-0505 March 2024 Technical Specification (TS) 5.7.2.15 - Explosive Gas and Storage Tank Radioactivity Monitoring Program WBL-24-008, Emergency Plan Implementing Procedure Revision2024-02-29029 February 2024 Emergency Plan Implementing Procedure Revision WBL-24-004, Emergency Plan Implementing Procedure Revision2024-02-15015 February 2024 Emergency Plan Implementing Procedure Revision WBL-24-005, American Society of Mechanical Engineers, Section XI, First 10-Year Inservice Inspection Interval, Inservice Inspection Owner’S Activity Report for Cycle 5 Operation2024-02-15015 February 2024 American Society of Mechanical Engineers, Section XI, First 10-Year Inservice Inspection Interval, Inservice Inspection Owner’S Activity Report for Cycle 5 Operation WBL-24-003, Emergency Plan Implementing Procedure Revision. Includes EPIP-6, Revision 58, Activation and Operation of the Technical Support Center (TSC)2024-01-30030 January 2024 Emergency Plan Implementing Procedure Revision. Includes EPIP-6, Revision 58, Activation and Operation of the Technical Support Center (TSC) WBL-23-058, Emergency Plan Implementing Procedure Revision. Includes EPIP-5, Revision 63, General Emergency2023-12-19019 December 2023 Emergency Plan Implementing Procedure Revision. Includes EPIP-5, Revision 63, General Emergency WBL-23-055, Of the Unit 2 Cycle 6 Core Operating Limits Report2023-11-22022 November 2023 Of the Unit 2 Cycle 6 Core Operating Limits Report WBL-23-051, Response to an Apparent Violation (EA-23-117); NRC Special Inspection Report 50-390, 391/2023440, Preliminary Greater than Green and Apparent Violation2023-11-22022 November 2023 Response to an Apparent Violation (EA-23-117); NRC Special Inspection Report 50-390, 391/2023440, Preliminary Greater than Green and Apparent Violation WBL-23-052, Periodic Submission for Changes Made to the Technical Specification Bases and Technical Requirements Manual2023-11-0808 November 2023 Periodic Submission for Changes Made to the Technical Specification Bases and Technical Requirements Manual WBL-23-045, 10 CFR 50.59 Summary Report2023-11-0707 November 2023 10 CFR 50.59 Summary Report WBL-23-048, LER 2023-S02-00 for Watts Bar Nuclear Plant, Units 1 and 2, Introduction of Contraband Into the Plant Protected Area2023-11-0202 November 2023 LER 2023-S02-00 for Watts Bar Nuclear Plant, Units 1 and 2, Introduction of Contraband Into the Plant Protected Area WBL-23-042, Update to Fire Protection Report2023-10-19019 October 2023 Update to Fire Protection Report WBL-23-038, American Society of Mechanical Engineers, Section XI, Third 10-Year Inservice Inspection Interval, Inservice Inspection Owner’S Activity Report for Cycle 18 Operation2023-08-0707 August 2023 American Society of Mechanical Engineers, Section XI, Third 10-Year Inservice Inspection Interval, Inservice Inspection Owner’S Activity Report for Cycle 18 Operation WBL-23-033, Emergency Plan Implementing Procedure Revision. Includes EPIP 1, Revision 59, Emergency Plan Classification Logic2023-07-13013 July 2023 Emergency Plan Implementing Procedure Revision. Includes EPIP 1, Revision 59, Emergency Plan Classification Logic WBL-23-026, Nuclear Regulatory Commission (NRC) Regulatory Issue Summary (RIS) 2023-01 - Preparation and Scheduling of Operator Licensing Examinations2023-05-18018 May 2023 Nuclear Regulatory Commission (NRC) Regulatory Issue Summary (RIS) 2023-01 - Preparation and Scheduling of Operator Licensing Examinations WBL-23-021, 2022 Annual Radiological Environmental Operating Report2023-05-11011 May 2023 2022 Annual Radiological Environmental Operating Report WBL-23-025, Emergency Plan Implementing Procedure Revision2023-05-0505 May 2023 Emergency Plan Implementing Procedure Revision WBL-23-020, Annual Non-Radiological Environmental Operating Report - 20222023-05-0404 May 2023 Annual Non-Radiological Environmental Operating Report - 2022 WBL-23-023, Of Cycle 19 Core Operating Limit Report2023-04-27027 April 2023 Of Cycle 19 Core Operating Limit Report WBL-23-019, Annual Radioactive Effluent Release Report2023-04-27027 April 2023 Annual Radioactive Effluent Release Report WBL-23-018, Revised Pressure and Temperature Limits Report (PTLR)2023-04-10010 April 2023 Revised Pressure and Temperature Limits Report (PTLR) WBL-23-013, 10 CFR 50.46 Annual Report for 20222023-03-29029 March 2023 10 CFR 50.46 Annual Report for 2022 WBL-23-015, Emergency Plan Implementing Procedure Revision2023-03-21021 March 2023 Emergency Plan Implementing Procedure Revision WBL-23-010, Emergency Plan Implementing Procedure Revisions2023-02-0909 February 2023 Emergency Plan Implementing Procedure Revisions WBL-23-008, Unit 1 Revision 1 of the Cycle 18 Core Operating Limits Report (COLR) and Units 2 Revision 1 of the Cycle 5 Core Operating Limits Report (COLR)2023-02-0707 February 2023 Unit 1 Revision 1 of the Cycle 18 Core Operating Limits Report (COLR) and Units 2 Revision 1 of the Cycle 5 Core Operating Limits Report (COLR) WBL-23-003, Emergency Plan Implementing Procedure Revision. Includes EPIP-16, Revision 25, Termination of the Emergency and Recovery2023-01-12012 January 2023 Emergency Plan Implementing Procedure Revision. Includes EPIP-16, Revision 25, Termination of the Emergency and Recovery WBL-23-001, Emergency Plan Implementing Procedure Revision. Includes EPIP-1, Revision 57, Emergency Plan Classification Logic2023-01-10010 January 2023 Emergency Plan Implementing Procedure Revision. Includes EPIP-1, Revision 57, Emergency Plan Classification Logic WBL-22-068, Submittal of Emergency Plan Implementing Procedure Revision2022-12-12012 December 2022 Submittal of Emergency Plan Implementing Procedure Revision WBL-22-062, Emergency Plan Implementing Procedure Revision. Includes EPIP-13, Revision 34, Initial Dose Assessment for Radiological Emeregencies2022-11-0101 November 2022 Emergency Plan Implementing Procedure Revision. Includes EPIP-13, Revision 34, Initial Dose Assessment for Radiological Emeregencies WBL-22-061, Unit 2 - Emergency Plan Implementing Procedure Revisions2022-10-17017 October 2022 Unit 2 - Emergency Plan Implementing Procedure Revisions WBL-22-060, Unit 2 - Emergency Plan Implementing Procedure Revisions. Includes EPIP-6, Revision 56, Activation and Operation of the Technical Support Center (TSC)2022-10-17017 October 2022 Unit 2 - Emergency Plan Implementing Procedure Revisions. Includes EPIP-6, Revision 56, Activation and Operation of the Technical Support Center (TSC) WBL-22-057, American Society of Mechanical Engineers, Section XI, First 10-Year Inservice Inspection Interval, Inservice Inspection Owners Activity Report for Cycle 4 Operation2022-09-26026 September 2022 American Society of Mechanical Engineers, Section XI, First 10-Year Inservice Inspection Interval, Inservice Inspection Owners Activity Report for Cycle 4 Operation WBL-22-046, Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2)2022-09-0808 September 2022 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) WBL-22-034, Update to Fire Protection Report Figures Redacted2022-08-0101 August 2022 Update to Fire Protection Report Figures Redacted WBL-22-037, Emergency Plan Implementing Procedure Revision. Including EPIP-13, Revision 33, Initial Dose Assessment for Radiological Emergencies2022-07-14014 July 2022 Emergency Plan Implementing Procedure Revision. Including EPIP-13, Revision 33, Initial Dose Assessment for Radiological Emergencies 2024-09-25 |
Text
Post Office Box 2000, Spring City, Tennessee 37381
WBL-24-008
February 29, 2024
10 CFR 50.54(q)(5) 10 CFR 72.44(f)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License Nos. NPF -90 and NPF-96 NRC Docket Nos. 50-390, 50-391, and 72 -1048
Subject:
Emergency Plan Implementing Procedure Revision
Pursuant to Title 10, Code of Federal Regulations (10 CFR) 50.54(q) (5), and 10 CFR 72.44(f),
Tennessee Valley Authority (TVA) is submitting a description of changes to the Watts Bar Nuclear Plant (WBN) Radiological Emergency Plan (REP). The affected document is the WBN Emergency Plan Implementing Procedure (EPIP) listed below:
EPIP Revision Title Effective Date
13 35 Initial Dose Assessment for Radiological 02/12/2024 Emergencies
Description of Changes
EPIP-13 Revision 35 enacted the following change:
- Corrected typographical errors in Section 2.2 (Developmental References).