W3P85-1237, Updates 840913 Response to Violations Noted in Insp Rept 50-382/84-25.Corrective Actions:Ongoing Program to Verify Adequate Documentation of Decisions Re Preventive Maint Implemented at Plant

From kanterella
(Redirected from W3P85-1237)
Jump to navigation Jump to search
Updates 840913 Response to Violations Noted in Insp Rept 50-382/84-25.Corrective Actions:Ongoing Program to Verify Adequate Documentation of Decisions Re Preventive Maint Implemented at Plant
ML20235U371
Person / Time
Site: Waterford Entergy icon.png
Issue date: 04/29/1985
From: Cook K
LOUISIANA POWER & LIGHT CO.
To: Martin R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
W3P85-1237, NUDOCS 8710140061
Download: ML20235U371 (2)


Text

.

LO UISI AN A / 44, oecAao~os vaser . an.ox.oo.

2OWER & LIGHT / New onLeANS LoulGIANA 70174-8000 9 (504)386-9345 MIDDLE SDUTH UTluTIES SYSTEM April 29, 1985 W3P85-1237 I A4.05 i Mr. Robert D. Martin Regional Administrator, Region IV ggggg)

U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 g

  • Ig Arlington, TX 76011

- N

Dear Mr. Martin:

Subject:

Waterford 3 SES Docket No. 50-382 License No. NPF-38 NRC Inspection Report 84-25 ,

Reference:

LP&L letter W3P84-2386 from K.W. Cook to J.T. Collins, NRC Region IV dated 9/13/84 regarding responses to Inspection '

Report 84-25.

l In the referenced letter, LP&L responded to Vin 1ation 8425-01 including the specifies identified in Section 4.0 of the subject Inspection Report. At this time, LP&L would like to clarify one commitment and extend the "Date Of Full Compliance" on another commitment contained in the referenced letter.

Under " Corrective Steps Which Will Be Taken" in Section 4.a.6 of the referenced response, LP&L stated:

"MI-5-113, Calibration of Crimpers, is being revised to reflect only crimpers presently on site and in the M&TE Program."

Our commitment is changed for clarification to read as follows: s "MI-5-118, Calibration of Crimpers, is being revised to reflect vendor  ;

technical manuals or bulletins applicable to crimpers used onsite and j in the M&TE Program." l l

Additionally, under "Date When Full Compliance Will Be Achieved" in Section 4.a.6 of the referenced response, LP&L stated:

i "The review of deviations from vendor recommendations, as prescribed l in vendor manuals for safety-related and environmentally qualified l equipment, is scheduled for completion by 4/30/85."  !

,ph b

.,- t -

l 8710140061 850429- '

g aq5/W $DR ADOCK 050 2

)-

/

' b o

, . . < =

Robert D. Martin W3P85-1237 Page 2 I

l I

l An ongoing program to verify adequate documentation of decisions concerning preventive maintenance with respect to any deviations from vendor  ;

recommendations, as prescribed-in vendor manuals, has been implemented at.

Waterford 3. To date, LP&L has performed a technical review of environmentally qualified / safety-related vendor technical manuals, extracted individual vendor recommendations applicable to Waterford 3 from )

those manuals, and is in the process of identifying deviations from those i vendor recommendations.

LP&L requires additional time to achieve full compliance regarding the 1 inspection item commitment. The initiation of corrective action or other j appropriate resolution for deviations identified during this initial effort j is rescheduled for August 1, 1985. {

If you have any questions, please contact Mr. G.E. Wuller, Onsite Licensing Unit Coordinator, at (504) 464-3499.

l Very truly yours.

s

( x \  ;

I .

K.W. Cook l Nuclear Support & Licensing Manager KWC:GEW:DWH:sms 1 i

cc: NRC, Director, Office of I&E G.W. Knighton, NRC-NRR D.M. Crutchfield, NRC-NRR j NRC Resident Inspectors Office INPO Records Center (J.T. Wheelock) l E.L. Blake W.M. Stevenson e- -