Amends Schedule for Submittal of Detailed Control Room Design Review Program Plan Per Suppl 1 to NUREG-0737 to 841001 & Summary Rept to 850301,per Request.Summary Rept Schedule Tentative Based on NRC Review of Program Plan
ML20084J774
Person / Time
Site: Waterford Entergy icon.png
Issue date: 05/07/1984
From: Cook K
LOUISIANA POWER & LIGHT CO.
To: Knighton G
Office of Nuclear Reactor Regulation
References
RTR-NUREG-0737, RTR-NUREG-737 W3P84-1254, NUDOCS 8405100063
Download: ML20084J774 (2)


Text

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

o LOUISIANA 242 ouanONoe sineer POWER & LIGHT P O. BOX 6008

  • NEW OnLEANS. LOUISIANA 70174 + (504) 366-2345

$EONEsSEU May 7, 1984 W3P84-1254 3-A1.01.04 3-H1 Director of Nuclear Reactor Regulation Attention: Mr. G.W. Knighton, Chief Licensing Branch No. 3 Division of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

SUBJECT:

Waterford SES Unit 3 Docket No. 50-382 Detailed Control Room Design Review (DCRDR)

REFERENCE:

W3P84-1005 dated April 10, 1984

Dear Sir:

In the referenced letter LP&L committed to providing the DCRDR program plan and summary report in one submittal scheduled for January 31, 1985.

However, at the request of your staff, we are amending our schedule to allow for a two-fold submittal as follows:

Submittal Report Date Program Plan October 1, 1984 Summary Report March 1, 1985 1

Due to this change some qualifying remarks are in order. The Program Plan l will not necessarily be a listing of intended actions but rather a descrip- '

tion of what has been completed. As you know, most was completed prior to issuance of the NUREC 0737 Su(DCRDR pplement work at Waterford I requirement l for submittal of a Program Plan', Additionally, the Summary Report schedule is tentative, dependent upon the timely review by your staff of the Program Plan and the extent of comments received that must be addressed in the Summary Report.

8405100063 840507 PINT ADOCK 05000tM32 F pm 3

) ()

. =. --. _ _ _

o Should you require additional information on this matter please feel free l to contact Mike Meisner at (504) 363-8938.

Yours very truly, K.W. Cook Nuclear Support & Licensing Manager KWC/MJM/pco cc: E.L.-Blake, W.M. Stevenson, J.T. Collins, D.M. Crutchfield, J. Wilson, G.L. Constable, D. Tondi 4

1 4

+E- WP N M e