Submits Schedule for Seismic Qualification Review Team Audit.Seismic Qualification Summary Will Be Submitted by 820716 W/Audit Commencing 820831 at Plant Site
ML20055B412
Person / Time
Site: Waterford Entergy icon.png
Issue date: 07/16/1982
From: Maurin L
LOUISIANA POWER & LIGHT CO.
To: Tedesco R
Office of Nuclear Reactor Regulation
References
W3P82-1918, NUDOCS 8207220176
Download: ML20055B412 (2)


Text

8 .

142 DELARONDE STREET P O W E R & L i G H T! P O BOX 6008

  • NEW ORLEANS. LOUIStANA 70174 . (504) 366 2345 U fillTIEb SYSTEM July 16, 1982 vice President Nuclear Operotions W3P82-1918 3-A20.18 Mr. R. L. Tedesco Assistant Director of Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

SUBJECT:

Waterford 3 SES Docket No. 50-382 Seismic Qualification Review Team (SQRT) Audit

Dear Mr. Tedesco:

The following schedule has been agreed to by members of the NRC staff for conducting the SQRT audit at the Waterford 3 site:

July 16 - LP6L submit seismic qualification summary sheets to NRC August 2 - NRC selects those components to be audited August 31 - SQRT audit commences at Waterford 3 site Accordingly, we are this date shipping, separately from this letter, two copies of our seismic qualification review forms directly to Mr. T. Y. Chang of the Equipment Qualification Branch, and one copy directly to Mr. J. N. Singh of EG6G, Idaho. This shipment consists of fifteen volumes. Volume I contains a Table of Contents and an Index of Seismic Qualification Review Forms by Discipline. This index is also further subdivided by system, and provides indication of each component's availability for audit. Volumes II through XV contain the actual Seismic Qualification Review Forms.

If you have any questions, please do not hesitate to call.

Yours very truly, l}YklathW QQ L. V. Maurin t @fchtf.o Vice President Nuclear Operations LVM/MGW/pco E207220176 820716 PDR ADOCK 05000382 A PDR

cc: Mr. W. M. Stevenson Mr. E. L. Blake Mr. L. Constable Mrs. S. Block Mr. T. Y. Chang