W3F1-2003-0012, January 2003 Monthly Operating Report for Waterford 3 Ses

From kanterella
Jump to navigation Jump to search
January 2003 Monthly Operating Report for Waterford 3 Ses
ML030550591
Person / Time
Site: Waterford Entergy icon.png
Issue date: 02/13/2003
From: Ridgel J
Entergy Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
W3F1-2003-0012
Download: ML030550591 (6)


Text

Entergy Operations, Inc.

17265 River Road KilIona, LA 70066 Tel 504 739 6650 W3F1-2003-0012 A4.05 PR February 13, 2003 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555

Subject:

Waterford 3 SES Docket No. 50-382 License No. NPF-38 Monthly Operating Report Gentlemen:

Attached is the subject report which covers the operating statistics for the month of January, 2003. This report is submitted per Section 6.9.1.6 of the Waterford 3 Technical Specifications for Facility Operating License No. NPF-38.

There are no commitments associated with this submittal. Should you have any questions regarding the above, please contact T.M. Manzella at (504) 739-6882.

Very truly yours, (Ridgel Acting Licensing Manager JAR/TMM/cbh Attachment cc:

E.W. Merschoff (NRC Region IV), N. Kalyanam (NRC-NRR),

J. Smith, N.S. Reynolds, B. Lewis (Utility Data Institute, Inc.),

lerevents@inpo.org - INPO Records Center, NRC Resident Inspectors Office

NRC MONTHLY OPERATING REPORT WATERFORD 3 for January, 2003

SUMMARY

OF OPERATIONS The unit operated at an average reactor power level of 99.9% and experienced no shutdowns or significant power reductions during the period.

PRESSURIZER SAFETY VALVE FAILURES AND CHALLENGES There were no pressurizer safety valve failures or challenges experienced during the month.

Page I of 5 2/12/2003

OPERATING DATA REPORT DOCKET NUMBER:

UNIT NAME:

DATE OF REPORT:

COMPLETED BY:

TELEPHONE:

50-382 WATERFORD 3 February 12, 2003 Bruce Meyers (504) 739-6426 OPERATING STATUS

1. Reporting Period Gross Hours in Reporting Period
2. Currently Authorized Power Level (MWt)

Maximum Dependable Capacity (Net MWe)

Design Electrical Rating (Net MWe)

3. Power Level to which Restricted (if any) (Net
4. Reason for Restriction (if any)

January, 2003 744 3,441 1,075 1,104 MWe)

NIA N/A Number of Hours Reactor was Critical Reactor Reserve Shutdown Hours Hours Generator was On-line Unit Reserve Shutdown Hours Gross Thermal Energy Generated (MWH)

Gross Electrical Energy Generated (MWH)

Net Electrical Energy Generated (MWH)

Reactor Service Factor Reactor Availability Factor Unit Service Factor Unit Availability Factor Unit Capacity Factor (using MDC)

Unit Capacity Factor (using DER)

Unit Forced Outage Rate THIS MONTH 744.0 0.0 744.0 0.0 2,556,532 858,406 824,209 100.0 100.0 100.0 100.0 103.1 100.3 0.0 YEAR TO DATE 744.0 0.0 744.0 0.0 2,556,532 858,406 824,209 100.0 100.0 100.0 100.0 103.1 100.3 0.0 CUMULATIVE 130,993.2 0.0 129,706.5 0.0 432,290,483 144,888,517 138,404,443 86.1 86.1 85.3 85.3 84.6 82.4 3.6 Page 2 of 5

5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.

18.

211212003

OPERATING DATA REPORT DOCKET NUMBER:

UNIT NAME:

DATE OF REPORT:

COMPLETED BY:

TELEPHONE:

50-382 WATERFORD 3 February 12, 2003 Bruce Meyers (504) 739-6426 OPERATING STATUS (Cont.)

19. Shutdowns Scheduled over next 6 months (type, date and duration of each):

NONE

20. If Shutdown at end of report period, estimated date of startup:
21. Unit is in Commercial Operation.

THIS

22. Hours in Reporting Period
23. Unit Forced Outage Hours
24. Nameplate Rating (Gross MWe)

Max. Dependable Capacity (Gross MWe)

NIA rEAR TO MONTH DATE CUMULATIVE 744 744 152,137 0.0 0.0 4,897.9 1,200 1,120

25. If changes occur in capacity ratings (Items 2 and 24) since the last report, give the reasons:

NIA Page 3 of 5 211212003

r-.

AVERAGE DAILY UNIT POWER LEVEL DOCKET NUMBER:

UNIT NAME:

DATE OF REPORT:

COMPLETED BY:

TELEPHONE:

50-382 WATERFORD 3 February 12, 2003 Bruce Meyers (504) 739-6426 Reporting Period:

January, 2003 DAY Avg. Power Level 1

1,109 2

1,108 3

1,108 4

1,109 5

1,109 6

1,109 7

1,108 8

1,109 9

1,109 10 1,110 11 1,109 12 1,110 13 1,108 14 1,108 15 1,108 (NET MWe)

DAY Avg. Power Level 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1,108 1,107 1,107 1,108 1,110 1,106 1,088 1,106 1,107 1,109 1,109 1,109 1,108 1,110 1,110 1,109 INSTRUCTIONS:

On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

Reflects On-Line Net Generation.

Page 4 of 5 2112/2003

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NUMBER:

UNIT NAME:

DATE OF REPORT:

COMPLETED BY:

TELEPHONE:

REPORTING PERIOD:

January, 2003 Outage Date Duration Number (yymmdd)

Type (Hours)

Reason NA Shutdown Method 50-382 WATERFORD 3 February 12, 2003 Bruce Meyers (504) 739-6426 Cause, Comments and Corrective Actions TYPE F - Forced S - Scheduled METHOD 1 - Manual 2 - Manual Scram 3 - Automatic Scram 4 - Continuation from Previol 5 - Power Reduction 6 - Other (explain) 2/12/2003 REASON A - Equipment Failure (explain)

B - Maintenance or Test C - Refueling D - Regulatory Restriction E - Operator Training and License Examination F - Administrative G - Operational Error (explain)

H - Other (explain) is Period Page 5 of 5