Text
~~
WAmeren MISSOURI September 24, 2013 ULNRC-06031 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Ladies and Gentlemen:
10 CFR 50.90 DOCKET NUMBER 50-483 CALLA WAY PLANT UNIT 1 UNION ELECTRIC CO.
FACILITY OPERATING LICENSE NPF-30 RESPONSES TO RAI SET #4 REGARDING ADOPTION OF NATIONAL FIRE PROTECTION ASSOCIATION STANDARD NFPA 805 Callaway Plant Reference 1): Ameren Missouri Letter ULNRC-05781, "Request for License Amendment to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)," August 29, 2011 Reference 2): NRC Letter, "Request for Additional Information License Amendment Request to Adopt National Fire Protection Association Standard 805 Performance Based Standard for Fire Protection for Light Water Reactor Generating Plants Callaway Plant (TAC No. ME7046)"
By the Reference 1 letter, Union Electric Company (Ameren Missouri) submitted a license amendment request (LAR) for Callaway Plant Unit 1 to adopt National Fire Protection Association Standard 805 (NFPA 805). Per Reference 2 the NRC electronically transmitted its fourth Request for Additional Information (RAI) related to our application. contains Ameren Missouri's response to the single request contained in the RAI. contains LAR Attachments to reflect changes made to the LAR as a result of the RAI response and NRC requested changes to the license condition.
This letter does not contain new commitments.
PO Box 620 Fulton, MD 65251 AmerenMissouri.com
ULNRC-06031 September 24, 2013 Page 2 If there are any questions with regard to these RAI responses, please contact me at (573) 676-8719 or Mr. Justin Hiller at (314) 225-1141.
I declare under penalty of perjury that the foregoing is true and correct Sincerely, Executed on: ----------------
~~r{v Scott Maglio Manager, Regulatory Affairs EMP/nls Enclosure I, Request for Additional Information (RAI) Set #4 Responses, Summary of LAR Changes
ULNRC-06031 September 24, 2013 Page 3 cc:
U.S. Nuclear Regulatory Commission (Original and 1 copy)
Attn: Document Control Desk Washington, DC 20555-0001 Mr. Steven A. Reynolds Acting Regional Administrator U.S. Nuclear Regulatory Commission Region IV 1600 East Lamar Boulevard Arlington, TX 76011-4511 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Fred Lyon Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-8B 1 Washington, DC 20555-2738
ULNRC-06031 September 24, 2013 Page4 Index and send hardcopy to QA File Al60.0761 Hardcopy:
Certrec Corporation 4150 International Plaza Suite 820 Fort Worth, TX 76109 (Certrec receives ALL attachments as long as they are non-safeguards and may be publicly disclosed.)
Electronic distribution for the following can be made via Responses and Reports ULNRC Distribution:
A. C. Heflin F. M. Diya C. 0. Reasoner III L. H. Graessle S. A. Maglio T. B. Elwood R. C. Wink J. W. Hiller G. A. Harris M. K. Fletcher L. E. Eitel S. G. Cantrell Corporate Communications NSRB Secretary STARS Regulatory Affairs Mr. John O'Neill (Pillsbury Winthrop Shaw Pittman LLP)
Missouri Public Service Commission Ms. Leanne Tippett Mosby (DNR)