ULNRC-04813, Ameren/Ue, Response to Order EA-03-009, Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors

From kanterella
(Redirected from ULNRC-04813)
Jump to navigation Jump to search
Ameren/Ue, Response to Order EA-03-009, Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors
ML030690496
Person / Time
Site: Callaway Ameren icon.png
Issue date: 02/26/2003
From: Blosser J
AmerenUE
To:
NRC/SECY/RAS
References
EA-03-009, ULNRC-04813
Download: ML030690496 (3)


Text

One Ameren Plaza 1901 Chouteau Avenue PO Box 66149 St. Louis, MO 63166-6149 314 621.3222 February 26, 2003 Secretary, Office of the Secretary of the Commission U.S. Nuclear Regulatory Commission ATTN: Rulemakings and Adjudications Staff Washington, DC 20555 Ladies and Gentlemen:

ULNRC-04813 DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO.

FACILITY OPERATING LICENSE NPF-30 RESPONSE TO ORDER EA-03-009, "ESTABLISHING INTERIM INSPECTION REQUIREMENTS FOR REACTOR PRESSURE VESSEL HEADS AT PRESSURIZED WATER REACTORS" AmerenUE has received the February 11, 2003, NRC Order Establishing Interim Inspection Requirements for Reactor Pressure Vessel Heads at Pressurized Water Reactors. The Order requires an answer within twenty days. AmerenUE files this answer consenting to the NRC Order for the Callaway Plant, and indicating its decision to not request a hearing.

This response is submitted in accordance with 10CFR2.202 and the specific requirements contained within the order. If you have any questions regarding this submittal, please contact me at (573) 676-8190 or Mr. Dave Shafer, Superintendent Licensing at (314) 554-3104.

Very truly yours, John D. Blosser Manager-Regulatory Affairs BFH/mlo

Attachment:

I - Affidavit a subsidiary ofArneren Corporation Union Electric wAmeren U1E

ULNRC-04813 February 26, 2003 Page 2 cc: U. S. Nuclear Regulatory Commission (Original and 1 copy)

Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 Mr. Samuel J. Collins Director, Office of Nuclear Reactor Regulations U. S. Nuclear Regulatory Commission Washington, DC 20555 Assistant General Counsel for Materials Litigation and Enforcement U. S. Nuclear Regulatory Commission Washington, DC 20555 Mr. Ellis W. Merschoff Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Jack N. Donohew (2 copies)

Licensing Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 7El Washington, DC 20555-2738 Manager, Electric Department Missouri Public Service Commission PO Box 360 Jefferson City, MO 65102

ULNRC-04813 Attachment I Page 1 of 1 STATE OF MISSOURI S S COUNTY OF CALLAWAY John D. Blosser, of lawful age, being first duly sworn upon oath says that he is Manager, Regulatory Affairs for Union Electric Company; that he has read the foregoing document and knows the content thereof; that he has executed the same for and on behalf of said company with full power and authority to do so; and that the facts therein stated are true and correct to the best of his knowledge, information and belief.

By J/ohn D. Blosser Manager, Regulatory Affairs SUBSCRIBED and sworn to before me this day of ___,

2003.

SEAL

  • NOTARlY
  • PUBliC
L c ~ ~ f 6Y' (e4.ct-7 C