U-601116, Monthly Operating Rept for Dec 1987

From kanterella
(Redirected from U-601116)
Jump to navigation Jump to search
Monthly Operating Rept for Dec 1987
ML20147C180
Person / Time
Site: Clinton Constellation icon.png
Issue date: 12/31/1987
From: Spangenberg F
ILLINOIS POWER CO.
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
U-601116, NUDOCS 8801190104
Download: ML20147C180 (6)


Text

.

Pags 1 of 5 Attachmint to U-601116 CHALLENGES TO MAIN STEAM SAFETY / RELIEF VALVES Month December 1987 None l

[

I l

l

)

td b /

8801190104 871231

[3 'l l l

DR ADOCK 05000461 DCD

Paga 2 of 5 Attachment to U-601116 MONTHLY OPERATING REPORT FORMAT AND INSTRUCTIONS AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-461 UNIT Clinton 1 DATE 12/31/87 COMPLETED BY F. A. Spangenberg TELEPHONE (217) 935-8881 X3400 MONTH December, 1987 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1 943 17 935 2 945 18 948 3 940 19 848 4 947 20 468 5 935 21 865 6 918 27 949 7 896 23 945 8 928 24 924 9 944 25 941 10 902 26 857 11 393 27 444 12 378 28 447 13 387 29 451 14 386 30 444 15 747 31 446 16 923 INSTRUCTIONS On this form, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month. Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100% line (or the restricted power level line). In such cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

[ Page 3 of 5 Attachment to' ,

U-601116:

OPERATING Da u REPORT DOCKET NO. 50-461

' UNIT Clinton 1 DATE 12/31/87 COMPLETED BY F. A. Spangenberg -

TELEPHONE (217) 935-8881 X3400 OPERATING STATUS

1. REPORTING PERIOD: December, 1987 GROSS HOURS IN REPORTING PERIOD: 744
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 2894 MAX. DEPEND. CAPACITY (MWe-Net): 916 DESIGN ELECTRICAL RATING (MWe-Net): 933
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR WAS CRITICAL... 744 _

898.3 898.3

6. REACTOR RESERVE SHUTDOWN HOURS......... 0 0 0
7. HOURS GENERATOR ON LINE..............., 744 898.3 898.3
8. UNIT RESERVE SHUTDOWN HOURS............ 0 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH)... 1,766,704 2,145,500 2,145,500
10. GROSS ELECTRICAL ENERGY GENERATED (MWH) 589,043 716,650 716,650
11. NET ELECTRICAL ENERGY GENERATED (MWH).. 562.135 684,103 684,103
12. REACTOR SERVICE FACTOR................. 100% 100% 100%
13. REACTOR AVAILABILITY FACTOR............ 100% 100% 100%
14. UNIT SERVICE FACT 0R.................... 100% 100% 100%
15. UNIT AVAILABILITY FACTOR............... 100% 100% 100%

16 UNIT CAPACITY FACTOR (Using MDC) . . . . . . . 82.5% 83.1% 83.1%

17. UNIT CAPACITY FACTOR (Using Design MWe) 81.0% 81.6% 81.6%
18. UNIT FORCED OUTAGE RATE................ 0.0% 0.0% 0.0%
19. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE. AND DURATION OF EACH): Maintenance shutdown, March 19, 1986, 11 months estimated.

Actual duration to be determined.

20. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): FORECAST ACHIEVED INITIAL CRITICALITY 2/27/87 INITIAL ELECTRICITY (Synchronization) 4/24/87 COMPLETION OF WARRANTY RUN 10/09/87 r

, c Pcgi 4 of 5.

Attachment to . .-

U-601116 UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-461 UNIT Clinton 1 DATE 12/31/87 COMPLETED BY F. A. Spangenberg TELEPHONE (217) 935-8881' X3400 REPORT MONTH December, 1987 METHOD OF TY.'E SHUTTING DOWN F: FORCED DURATION THE REACTOR OR NO. DATE S: SCHEDULED (HOURS) REASON (1) REDUCING POWER (2) CORRECTIVE ACTIONS / COMMENTS 1 12/10/87 F 0 A: Power reduced to 1: Manual insertion approximately 42% of control Reason to allow repair rods and of steam leaks. reduction of A-Equipment Failure recirculation (explain) flow. B-Maintenance or Test C-Refueling 2 12/19/87 F 0 A: Power reduced to 1: Manual D-Regulatory Restriction approximately 50% insertion of E-Operator Training &

to allow repair of control rods License Examination condenser water box and reduction F-Administrative tubes. of recirc- G-Operational Error ulation flow. (explain)

H-Other 3 12/26/87 F 0 A: Power reduced to 1: Manual approximately 48% insertion of Method to allow repair of control rods condensor water box and reduction 1-Manual tubes, and repair of recirc- 2-Manual Scram of the 4B Feedwater ulation flow. 3 ,. e.o Scram Heat Exchanger. 4-Continued 5-Reduced Load 9-Other-i

Pega 5 of 5 Attachmint to U-601116 REFUELING INFORMATION

1) Name of facility Clinton Power Station

.- 2) Scheduled date for next refueling shutdown January 1989

3) Scheduled date for restart following refuel To be determined in January 1988 1
4) Will refueling or resumption of operation thereafter require a Technical Specification change or other license amendment? Yes If Yes, list in general what these will be:

An Operating License and Technical Specification change in response to the Reduced Feedwater Temperature Analysis if it is performed for CPS. ,

i- If No, has the reload fuel design and core configuration been reviewed by the Facility Review Group (FRG) to determine whether any unreviewed I safety questions are associated with the core reload? No If no such review has taken place, when it is scheduled? July, 1988

5) Scheduled date(s) for submitting proposed licensing action and supporting information:

i The reload license cmendment is scheduled to be submitted on October 3, 1988.

6) List any important licensing considerations associated with refueling e.g., new or different fuel design or supplier, unreviewed design or performance analysis methods, significant changes in fuel design, new operating procedures.

The new core design is not yet finalized.

7) Number of fuel assemblies 1

a) in the core 624 b) in the spent fuel storage pool 0_

8) The present licensed spent fuel pool storage capacity 2,672

' The size of any requested or planned increase in licensed storage capacity 0 (number of fuel assemblies)  ;

E

9) The projected date of the last refueling that can be discharged to the spent fuel pool, assuming the present licensed capacity ,2010 .

l l

l 0

~

. U-601116 L . L30-88 ( 01- 11)-LP 1A.120 ILLINDIS DOWER COMPANY IP CUNTON POMR ST ATION P.O. Box 678. CLLNTON, (UJNOt$ 61727 January 11, 1988 10CFR50.36 RG 1.16 Docket No. 50-461 2

Document Control Desk U.S. Naclear Regulatory Commission Washington, D.C. 20555

Subject:

Clinton Povet Station, Unit 1 December 1987 Monthly Operating Report NPF-62

Dear Sir:

Please find enclosed the Monthly Operating Report for Clinton Power Station, Unit 1, for the period ending December 31, 1987.

Sincarely yours, 0.{ u w, ,0 F. A. S > erg II Manager {ange Li insing a 4 Safety GSL/ktn Enclosure cc: Regional Administrator, Region III, USNRC 1