TXX-6587, Interim Deficiency Rept CP-87-24 Re Engineering Approval Allowing Bending of Nelson Stud Anchors on Containment Liners in Excess of FSAR Requirements.Initially Reported on 870629.Evaluation Continuing.Next Rept Expected by 870828
| ML20236E566 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 07/29/1987 |
| From: | Counsil W, Keeley G TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| To: | NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
| References | |
| CP-87-24, TXX-6587, NUDOCS 8708030009 | |
| Download: ML20236E566 (1) | |
Text
- _ - _ _ - _ _ _ _ _ _ _ - _ _ _ - _ _
M Log #.TXX-6587
==
File # 10110 3.
3 906.2 r.
==
Ref: 10CFR50.55(e)'
1UELECTRIC i
wmiam c. counsii July 29, 1987-l Executne Vice President U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445 AND f0-446 CONTAINMENT LINER NELSON STUD BENDING SDAR:
CP-87-24 (INTERIM REPORT)
Gentlemen:
On June 29, 1987, we verbally notified your Mr. H. S. Phillips of a deficiency involving engineering ' approval provided to allow bending of Nelson stud anchors on the containment liner in excess of FSAR requirements. This is an interim report of a potentially reportable item under the provisions of 10CFR50.55(e).
We are continuing our evaluation and anticipate submitting our next report on this issue.no later than August 28, 1987.
Very truly yours, W. G. Counsil t/
By:
G. S. Keeley JDS/mlh Manager, Nud censing c - Mr. R. D. Martin, Region IV Re;,ident Inspectors, CPSES (3) i p;P RB88K 8?8?Er f