TXX-6556, Interim Deficiency Rept CP-85-36 Re Installation of nonsafety-related Conduits on nonsafety-related Supports. Initially Reported on 860906.Unit 1 Field Verification Continuing.Unit 2 to Be Addressed.Next Rept Due by 880210

From kanterella
(Redirected from TXX-6556)
Jump to navigation Jump to search
Interim Deficiency Rept CP-85-36 Re Installation of nonsafety-related Conduits on nonsafety-related Supports. Initially Reported on 860906.Unit 1 Field Verification Continuing.Unit 2 to Be Addressed.Next Rept Due by 880210
ML20235H254
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 07/07/1987
From: Counsil W, Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM)
References
CP-85-36, TXX-6556, NUDOCS 8707150070
Download: ML20235H254 (1)


Text

.- -- _

6 Log # TXX-6556

==

File # 10110 i

5 903.9

)

=

=

Ref # 10CFR50.55(e) 1UELECTRIC y

i William G. Counsil Executive Vice hesident U. S. Nuclear Regulatory Commission i

Attn: Document Control Desk Washington, D. C.

20555

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 TRAIN "C" CONDUIT SUPPORTS SDAR:

CP-85-36 (INTERIM REPORT)

{

l Gentlemen:

On September 6,1986, we verbally notified your Mr. C. Gould of a deficiency i

involving the installation of non-safety related conduit (two-inch diameter q

I and smaller) on non-safety related dead weight supports in Category 1 areas.

4 This is an interim report of a potentially reportable item under the

{

provisions of 10CFR50.55(e).

Our latest interim report was logged TXX-6221, j

dated January 21, 1987.

As previously reported, the evaluation program developed to address this issue j

(CPRT Program Plan ISAP I.c) is still in process.

Currently, our field verification is continuing in the Unit 1 and Common Area to determine the adequacy of the Train C conduit supports.

To date, the I

evaluation of conduit supports in 180 rooms has been completed. These efforts I

represent approximately 63 percent of the rooms and 72 percent of the supports in the Unit 1 and Common Area.

Evaluation and verification activities for Unit 2 will be addressed after the completion of the Unit 1 and Common Area activities i

Our evaluation of the Unit 1 and Common Area is currently scheduled for completion by late December,1987.

We anticipate submitting our next report on this issue no later than February 10, 1988.

l Very truly yours, r

hbk3OOck$Ob445 W. G. Counsil S

PDR-7 By:

G. S. Keeley

& /

Manager,NuclearLicen/ing DAR/gj c - R. D. Martin, Region IV Resident Inspectors, CPSES (3)