l l
M Log # TXX-6256
=M File # 10110 d
908.3
.=
=
Ref # 10CFR50.55(e) 1UELECTRIC wu c;
February 4, 1987 g
U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)
DOCKET NOS. 50-445 AND 50-446 TRACEABILITY OF 1E PIGTAIL EXTENSIONS SDAR: CP-86-38 (INTERIM REPORT)
Gentlemen:
On May 27, 1986, we verbally notified your Mr. T. F. Westerman of a deficiency involving the failure of project procedures to adequately address the installation _and_ inspection criteria forJ:able-runsi used as device pigtail extensions. This is an interim report of a potentially reporrabTe-item under the provisions of 10CFR50.55(e). Our latest interim report, logged TXX-6166, was submitted on December 16, 1986.
The field verification effort to obtain cable and splice data is continuing.
As-built data obtained from this effort is under evaluation in preparation of our assessment of the impact of this issue on the safety of plant operations.
Our next report on this issue will be submitted no later than May 21, 1987.
Very truly yours, A
W. G. Counsil
/
By:
G. S. Keeley Manager, Nucha Licensing RSB:lw c - Mr. E. H. Johnson, Region IV Mr. D. L. Kelley, RI - Region IV Mr. H. S. Phillips, RI - Region IV B7021 g { M "45
?"
ZG2.1 gg 400 North Olive Street l_ B. 8 I Dallas, Texas 75201