Interim Deficiencu Rept CP-86-69 Re Failure to Incorporate Specific Restraining/Support Requirements Defined by IEEE Std 420-1973, Class IE Control Switchboards, Into Project Specs & Procedures.Next Rept Will Be Submitted by 870312
ML20212J577
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 01/21/1987
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CP-86-69, TXX-6225, NUDOCS 8701280239
Download: ML20212J577 (1)


Text

Log # TXX-6225

  • File # 10110 909.1 ,

TEXAS UTILITIES GENERATING COMPANY SKYWAY TOWER . 488 NORTH OLIVE srTREET. I.B. St DALLAS. TEXA5 7Mel January 21, 1987

  • &$*.%h.2 %  ;

i Mr. Eric H. Johnson, Director l

j.

Division of Reactor Safety and Projects i U. S. Nuclear Regulatory Commission . ,

' JAN 2 3198/

611 Ryan Plaza Drive, Suite 1000 dh AjL Arlington, TX 76011

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 SUPPORT OF CLASS 1E WIRING SDAR: CP-86-69 (INTERIM REPORT)

Dear Mr. Johnson:

On October 32 1986, we verbally notified your Mr. I. Barnes of a deficiency regarding the failure to incorporate specific restraining / support requirements defined by IEEE Standard 420-1973, " Class 1E Control Switciiboards," into project specifications and procedures. This is an interim report of a potentially reportable item under the provisions of 10CFR50.55(e).

Preliminary evaluations indicate that in the event these conditions had remained uncorrected no condition adverse to the safety of plant operations should exist. Documentation supporting our position is currently in the final stages of review and is scheduled for completion on February 13, 1987.

Our next report will be submitted no later than March 13, 1987.

Very truly yours, V7k2t/

W. S. Counsil f I DAR:lw c - NRC Region IV (0 + 1 copy)

Director, Inspection and Enforcement (15 copies)

U. S. Nuclear Regulatory Commission Washington, D. C. 20555 K$5hohd4,3 PDR a omsuas or rexxs cruunts ru:crase wurm Mz7 ,