TXX-5017, Interim Deficiency Rept CP-86-54 Re Design & Installation of Control Room Ceiling.Initially Reported on 860806.Evaluation Continuing.Next Rept Expected by 861003

From kanterella
(Redirected from TXX-5017)
Jump to navigation Jump to search
Interim Deficiency Rept CP-86-54 Re Design & Installation of Control Room Ceiling.Initially Reported on 860806.Evaluation Continuing.Next Rept Expected by 861003
ML20203N169
Person / Time
Site: Comanche Peak  Luminant icon.png
Issue date: 09/17/1986
From: Counsil W, Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CP-86-54, TXX-5017, NUDOCS 8609230180
Download: ML20203N169 (1)


Text

._

I Log # TXX-5017 File # 10110 903.7 TEXAS UTILITIES GENERATING COMPANY SKYWAY TOWER . 400 NORTH OLIVE KI'REET. L.B. 51. DALLA 8, TEXAS 75301 September 17, 1986 i

= .w.=, S}g@3DV1M SEP 181986 q j Mr. Eric H. Johnson, Director g/

Division of Reactor Safety and Projects ,_

U.S. Nuclear Regulatory Commission J 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76012

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 ORIGINAL DESIGN OF CONTROL ROOM CEILING

. SDAR: CP-86-54 (INTERIM REPORT)

Dear Mr. Johnson:

On August 6,1986, we verbally notified your Mr. I. Barnes of a deficiency in the original design and installation of the control room ceiling. This is an interim report of a potentially reportable item under the provisions of 10CFR50.55(e). On September 5, 1986, we received an extension in submitting this report from your Mr. I. Barnes until September 17, 1986.

We are continuing our evaluation and anticipate submitting our next report by October 3, 1986.

Very truly yours, b

W. G. Co sil By: .

G. S. Keele Manager, Licensi JCH/amb c - NRC Region IV (0 + 1 copy)