TXX-4863, Interim Deficiency Rept CP-85-54 Re Discrepancies in Supplier Provided HVAC Support Documents.Initially Reported on 851220.Engineering Evaluation Scheduled for Completion by Sept 1986.Next Rept Will Be Submitted by 860926

From kanterella
(Redirected from TXX-4863)
Jump to navigation Jump to search
Interim Deficiency Rept CP-85-54 Re Discrepancies in Supplier Provided HVAC Support Documents.Initially Reported on 851220.Engineering Evaluation Scheduled for Completion by Sept 1986.Next Rept Will Be Submitted by 860926
ML20211K935
Person / Time
Site: Comanche Peak  
Issue date: 06/18/1986
From: Counsil W, Keeley G
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Johnson E
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
CP-85-54, TXX-4863, NUDOCS 8606300374
Download: ML20211K935 (1)


Text

Log # TXX-4863 File # 10110 903.7 TEXAS UTILITIES GENERATING COMPANY 05KYWAY TOWER

  • 400 NORTH OflVE STREET. L B. 81
  • DALLAS. TEXAS 75301 June 18, 1986 M W"af,00fA Mr. Eric H. Johnson, Director Division of Reactor Safety and Projects U. S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76012

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION (CPSES)

DOCKET NOS. 50-445 AND 50-446 SEISMIC QUALIFICATION OF HVAC SUPPORTS SDAR: CP-85-54 (INTERIM REPORT)

Dear Mr. Johnson:

On December 20, 1985, we verbally notified your Mr. R. Hall of a deficiency involving discrepancies in supplier provided HVAC support documents which could invalidate the seismic qualification of the supports. This is an interim report of a potentially reportable item under the provisions of 10CFR50.55(e).

We have submitted interim reports logged TXX-4668 and TXX-4718, dated January 20, 1986, and February 28, 1986, respectively.

As built walkdowns started in April,1986, to obtain duct layout, support layout, and duct-to-support attachment information and details.

Engineering evaluations are in progress and are estimated to be completed in September, 1986. The scope of the work includes 415 of the approximately 3900 HVAC supports in Unit 1 and Common.

The supports comprise the Diesel Generator Train A and B Systems (65 supports) and the Control Room HVAC Safety-related Systems (350 supports). All duct-to-support attachments in Unit 1 and Common (1318 total) are included in the walkdown and engineering evaluation efforts.

We anticipate submitting our next report by September 26, 1986.

Very truly yours, hun W. G. Co i

'/

8606300374 e6061s By:

PDR ADOCK 05000445 G. S. Keeley 6

PDR Manager, Nuclea' icensing JCH/arh c - NRC Region IV (0 + 1 Copy)

Director, Inspection & Enforcement (15 copies)

U. S. Nuclear Regulatory Commission Washington, D.C.

20555 n