Deficiency Rept SDAR-201 Re Installed Conduit to Equipment Interface Not Being Specified Per Design Documents.Initially Reported on 850918.Completion of Evaluation Expected by 860212
ML20136C422
Person / Time
Site: Comanche Peak Luminant icon.png
Issue date: 11/07/1985
From: Counsil W
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Denise R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
References
SDAR-201, TXX-4615, NUDOCS 8511210085
Download: ML20136C422 (1)


Text

.-l , ,

Log # TXX-4615 TEXAS UTILITIES GENERATING COMPANY File # 10110 SKYWAY TOWER = 400 NORTH 01JVE STREE"F. L.B. 51 e DAILAN. TEXAM 78201 WILLIAM 0, COUNSIL EZEcuTIVE VICE PREstOEse?

Mr. R. P. Denise, Director h D Q//{=+,, r, Division of Reactor Safety and Projects U.S. Nuclear Regulatory Commission j 'l:

Region IV gig / 2B85 /

611 Ryan Plaza Drive, Suite 1000 Arlington, TX 76012 x.s!) ';

SUBJECT:

COMANCHE PEAK STEAM ELECTRIC STATION DOCKET NO. 50-446 EQUIPMENT CONDUIT INTERFACE QA FILE: CP-85-39, SDAR-201 I

Dear Mr. Denise:

On September 18, 1985, we verbally notified your Mr. T. F. Westerman of a deficiency involving the installed conduit.to equipment interface which may not be as specified per design documents. We have submitted an interim report logged TX :~4589, dated October 10, 1985.

We are continuir:9 our evaluation and anticipate completion by February 12,

[ 1986.

Very taly yours,

[

W. G. Counsil JCH/grr c- NRC Region IV (0 + 1 copy)

Director, Inspection and Enforcement (i5 copids)

U. S. Nuclear Regulatory Commission Washington, D.C. 20555 0 s 999 Q2

)(o n n .. - . , - - . _ ,c _

. _. .. . .