TXX-4511, Interim Deficiency Rept SDAR-171 Re Reliance Control Board Differing from Equipment Qualification Rept.Initially Reported on 850226.Evaluation Continuing.Completion Expected by 850731
| ML20128N919 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 07/11/1985 |
| From: | Wells J TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC) |
| To: | Hunter D NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| SDAR-171, TXX-4511, NUDOCS 8507260298 | |
| Download: ML20128N919 (1) | |
Text
I' L
TEXAS UTILITIES GENERATING COMPANY N K Y WAY 14 sWEN
- 4089 NONTH H, ITE seTHEET,8,.H. ses
- tsALLAN, TEX AM 73208 l
3dlb.u July 11, 1985 TXX-4511
@S0EQ %
JLi5IllE Mr. D.R. Hunter, Chief Reactor Project Branch 2 U.S. Nuclear Regulatory Commission Office of Inspection & Enforcement 611 Ryan Plaza Drive, Suite 1000 Docket Nos.: 50-445 Arlington, TX 76012 50-446 COMANCHE PEAK STEAM ELECTRIC STATION RELIANCE CONTROL BOARDS QA FILE: CP-85-10, SDAR-171 FILE N0.:
10110
Dear Mr. Hunter:
On February 26, 1985 we verbally notified your Mr. D. Hunnicutt of a deficiency
[
regarding a Reliance supplied control board that differs from the EQ report.
We have submitted interim reports logged TXX-4445, TXX-4464 and TXX-4482 dated March 25, 1985, April 19, 1985 and May 29, 1985.
We are continuing our evaluation and anticipate completion by July 31, 1985.
I Very truly yours, JRW:tig cc: NRC Region IV - (0 + 1 copy)
Director, Inspection & Enforcement (15 copies)
U.S. Nuclear Regulatory Commission Washington, DC 20555 8507260298 850711 PDR ADOCK 05000445 S
./