TAC:57281
From kanterella
Jump to navigation
Jump to search
Request for: Open | |
Initiation
Questions Answers Results
Other: GO2-85-200, Confirms That Scheduled Testing of UHS Spray Ponds Has Begun,Satisfying License Condition 2.C.(6),per D Myers, GO2-85-649, Forwards Washington Nuclear Plant Unit 2 Spray Pond Drift Loss Rept, Per License Condition 2.C.(6) Re Uhs.License Condition 2.C.(6) Satisfied.Rev 1 to Operating & Engineering Test Procedure 8.2.92, UHS Performance, Also Encl, ML17278A428, ML17278A429, ML17279A693 | |
| From | |
MONTHYEARML17278A4291985-03-20020 March 1985
[table view]Rev 1 to Operating & Engineering Test Procedure 8.2.92, UHS Performance GO2-85-200, Confirms That Scheduled Testing of UHS Spray Ponds Has Begun,Satisfying License Condition 2.C.(6),per D Myers1985-04-11011 April 1985 Confirms That Scheduled Testing of UHS Spray Ponds Has Begun,Satisfying License Condition 2.C.(6),per D Myers ML17278A4281985-07-31031 July 1985 Washington Nuclear Plant Unit 2 Spray Pond Drift Loss Rept GO2-85-649, Forwards Washington Nuclear Plant Unit 2 Spray Pond Drift Loss Rept, Per License Condition 2.C.(6) Re Uhs.License Condition 2.C.(6) Satisfied.Rev 1 to Operating & Engineering Test Procedure 8.2.92, UHS Performance, Also Encl1985-09-27027 September 1985 Forwards Washington Nuclear Plant Unit 2 Spray Pond Drift Loss Rept, Per License Condition 2.C.(6) Re Uhs.License Condition 2.C.(6) Satisfied.Rev 1 to Operating & Engineering Test Procedure 8.2.92, UHS Performance, Also Encl ML17279A6931985-12-11011 December 1985 Discusses OL Granted to Util,Including License Condition 2.C.(6),that Required Util to Perform Operational Testing of UHS Spray Ponds to Verify Analyzed Parameters of Drift Loss, Seepage & Operational Capacity 1985-04-11 | |
Retrieved from "https://kanterella.com/w/index.php?title=TAC:57281&oldid=5097891"