Beaver Valley Unit 1 License Condition 2.CBeaver Valley Unit 1 License Condition 2.C.5 requires that FENOC shall implement and maintain in effect all provisions of the approved fire protection program as described in the Updated Final Safety Analysis Report. BVPS Unit 1 UFSAR Rev. 24 Section 9.10.1 states that the fire protection plan that satisfies General Design Criterion 3 of Appendix A to 10 CFR 50 is described in BVPS Administrative Procedures. 1/2 ADM-1900, Fire Protection Program, Rev. 19 step 7.17.4 requires operating procedures be maintained to implement the actions required to achieve safe shutdown. Contrary to the above, on July 29, 2009, the NRC identified that FENOC did not meet this requirement and failed to maintain safe shutdown procedure 1OM-56B.4.I, Safe Shutdown Following a Serious Fire in the Service Building, Rev. 11, and ensure that the RCPs were tripped and remain tripped prior to securing RCP seal cooling. FENOC is in transition to NFPA 805 and therefore the NRC-identified violation was evaluated in accordance with the criteria established by Section A of the NRCs Interim Enforcement Policy Regarding Enforcement Discretion for Certain Fire Protection Issues (10 CFR Part 50.48) for a licensee in NFPA 805 transition. Specifically, although the NRC identified the violation, it is likely that FENOC would have identified and corrected this issue as part of the transition to NFPA 805, FENOC entered the issue into the corrective action program, FENOC implemented compensatory measures in a reasonable time commensurate with the risk significance, the issue was not likely to have been previously identified by routine FENOC efforts, and the violation was not willful. Because all the criteria were met, the NRC is exercising enforcement discretion for this issue.ing enforcement discretion for this issue.  +
23:59:59, 30 September 2009  +
05000334  +  and 05000412  +
23:59:59, 30 September 2009  +
Has query"Has query" is a predefined property that represents meta information (in form of a <a rel="nofollow" class="external text" href="https://www.semantic-mediawiki.org/wiki/Subobject">subobject</a>) about individual queries and is provided by <a rel="nofollow" class="external text" href="https://www.semantic-mediawiki.org/wiki/Help:Special_properties">Semantic MediaWiki</a>.
Modification date"Modification date" is a predefined property that corresponds to the date of the last modification of a subject and is provided by <a rel="nofollow" class="external text" href="https://www.semantic-mediawiki.org/wiki/Help:Special_properties">Semantic MediaWiki</a>.
00:40:36, 29 October 2017  +
23:59:59, 30 September 2009  +
Failure to Ensure RCPs were Tripped and Remain Tripped Prior to Securing Reactor Coolant Pump Seal Cooling  +