 Issue dateTitle
ML21105A4861 April 2021Technical Specifications Bases, Manual
ML21105A4871 April 2021Technical Requirements Manual
ML20309A61330 September 20206 to Updated Final Safety Analysis Report, Chapter 7, Instrumentation and Control
ML19305D24831 December 2019Issuance of Amendments Adoption of Emergency Action Level Schemes Per NEI 99-01, Rev. 6
ML17033B53129 September 2016Redacted Updated Final Safety Analysis Report Chapter 7
IR 05000338/201300430 October 2013IR 05000338-13-004, 05000339-13-004; on 07/01/2013 09/30/2013; North Anna Power Station, Units 1 and 2, Problem Identification and Resolution
ML13204A29223 July 2013IR 05000338-13-003, 05000339-13-003; IR 05000338-13-501, 05000339-13-501; 04/01/2013 06/30/2013; North Anna Power Station, Units 1 and 2. Routine Integrated Inspection Report
IR 05000338/201200331 July 2012IR 05000338-12-003, 05000339-12-003; 04/01/2012 - 06/30/2012; North Anna Power Station, Units 1 and 2; Inservice Inspection Activities
IR 05000338/201200210 May 2012IR 05000338-12-002, 05000339-12-002, on 01/01/2012 - 03/31/2012; North Anna Power Station, Units 1 and 2; Other Activities
IR 05000338/201000528 January 2011IR 05000338-10-005, 05000339-10-005, 07200056-10-002, on 10/01/2010 - 12/31/2010, North Anna Power Station, Units 1 & 2, and Independent Spent Fuel Storage Installation
IR 05000338/201000429 October 2010IR 05000338-10-004, 05000339-10-004, 07200056-10-001; 07/01/2010 - 09/30/2010; North Anna Power Station, Units 1 & 2, and North Anna Independent Spent Fuel Storage Installation: Plant Modifications; Identification and Resolution of Problems
IR 05000338/201000329 July 2010IR 05000338-10-003, 05000339-10-003, 07200056-10-001, on 04/01/2010 - 06/30/2010, North Anna Power Station, Units 1 & 2 and the North Anna Independent Spent Fuel Storage Installation: Maintenance Effectiveness, Identification and Resolution
ML10210055129 July 2010IR 05000338-10-003, 05000339-10-003, 07200056-10-001, on 04/01/2010 - 06/30/2010, North Anna Power Station, Units 1 & 2 and the North Anna Independent Spent Fuel Storage Installation: Maintenance Effectiveness, Identification and Resolution
IR 05000338/20100027 May 2010IR 05000338-10-002, 05000339-10-002, on 01/01/2010 - 03/31/2010, North Anna Power Station, Units 1 and 2. Routine Integrated Inspection Report, Fire Protection, Event Followup, and Other Activities
ML09282015630 September 2009Updated Final Safety Analysis Report, Revision 45, Chapter 7, Instrumentation and Control
IR 05000338/200900229 April 2009IR 05000338-09-002, 05000339-09-002, on 01/01/2009 - 03/31/2009, North Anna Power Station, Units 1 and 2, Routine Integrated Inspection Report
IR 05000338/200800528 January 2009IR 05000338-08-005, 05000339-08-005, on 10/01/2008 - 12/31/2008, North Anna Power Station, Units 1 and 2; Routine Integrated Report, Fire Protection
IR 05000338/200800428 October 2008IR 05000338-08-004, 05000339-08-004; 07/01/2008 - 09/30/2008; North Anna Power Station, Units 1 and 2; Routine Integrated Report, Other Activities
IR 05000338/200700531 January 2008IR 05000338-07-005, 05000339-07-005 on 10/01/2007 - 12/31/2007 for North Anna, Units 1 & 2, Refueling and Outage Activities
IR 05000338/200700430 October 2007IR 05000338-07-004 and 05000339-07-004; on 07/01/2007 - 09/30/2007; North Anna Power Station, Units 1 & 2, Routine Integrated Resident and Regional Report. Inservice Inspection
IR 05000338/200700331 July 2007IR 05000338-07-003, IR 05000339-07-003; 04/01- 06/30/2007; North Anna Power Station, Units 1 & 2; Other Activities
IR 05000338/200700226 April 2007IR 05000338-07-002, 05000339-07-002 and 07200056-07-001, on 03/31/2007, North Anna, Units 1 and 2
IR 05000338/200600529 January 2007IR 05000338-06-005, 05000339-06-005 and 07200016-06-003 on 12/31/2006 for North Anna, Units 1 and 2
IR 05000338/200600328 July 2006IR 05000338-06-003, IR 05000339-06-003, IR 07200016-06-001, on 04/01/2006 - 06/30/2006, for North Anna, Units 1 & 2, and Independent Spent Fuel Storage Installation. Routine Integrated Resident and Regional Report
IR 05000338/200600226 April 2006IR 05000338-06-002, IR 05000339-06-002, IR 07200016-06-001; 01/01/2006 - 03/31/2006; North Anna Units 1 & 2, & North Anna Independent Spent Fuel Storage Installation. Routine Integrated Resident and Regional Inspector Report. Event Follow-u
ML06117000826 April 2006IR 05000338-06-002, IR 05000339-06-002, IR 07200016-06-001; 01/01/2006 - 03/31/2006; North Anna Units 1 & 2, & North Anna Independent Spent Fuel Storage Installation. Routine Integrated Resident and Regional Inspector Report. Event Follow-u
IR 05000338/200500530 January 2006IR 05000338-05-005, IR 05000339-05-005; 10/01/2005 - 12/31/2005; North Anna Power Station Units 1 & 2. Routine Integrated Resident and Regional Report. Inservice Inspection
ML19331D78627 August 1980LER 80-043/03L-0:on 800814,during Mode 5 Operation, Pressurizer Power Relief Valve Declared Inoperable When Nitrogen Gas Supply Required for Overpressure Protection Dropped Below 1,775 Psig.Caused by Low Nitrogen Pressure