Issue date | Title | |
---|---|---|
ML23318A208 | 13 September 2023 | Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations, July I, 2022 - June 30, 2023 - Volume 2 (Exhibits) |
ML23318A209 | 13 September 2023 | Thirty-Third Annual Report on the Safety of Diablo Canyon Nuclear Power Plant Operations, July I, 2022 - June 30, 2023 - Volume 1 (Main Report) |
IR 05000275/2022010 | 27 January 2023 | Biennial Problem Identification and Resolution Inspection Report 05000275/2022010 and 05000323/2022010 |
ML17011A204 | 28 February 2017 | SRM-M150521A - Proposed Director'S Decision Friends of Earth 2.206 Petition Based on Commission Memorandum and Order CLI-15-14 |
IR 05000275/2016004 | 8 February 2017 | NRC Integrated Inspection Report 05000275/2016004 and 05000323/2016004 and Exercise of Enforcement Discretion |
DCL-16-124, Implementation of Alternative Source Term Summary of Dose Analyses and Results Revision 5 | 9 November 2016 | Implementation of Alternative Source Term Summary of Dose Analyses and Results Revision 5 |
ML16336A573 | 20 October 2016 | Diablo-2016-10 Draft Written Examination |
ML16321A243 | 20 October 2016 | 2016-10 Final Written Exam |
ML16287A755 | 6 October 2016 | Technical Assessment Implementation of Alternative Source Terms Summary of Dose Analyses and Results Revision 4 |
IR 05000275/2016009 | 26 August 2016 | NRC Problem Identification and Resolution Inspection Report 05000275/2016009; 05000323/2016009 |
ML16169A265 | 18 May 2016 | Technical Report, Implementation of Alternative Source Terms Summary of Dose Analysis and Results, Revision 3 |
ML16004A354 | 11 December 2015 | Response to NRC Request for Additional Information Regarding License Amendment Request 15-03, Application of Alternative Source Terms Summary of Dose Analysis & Results, Revision 1 |
IR 05000275/2015003 | 13 November 2015 | IR05000275/2015003, 05000323/2015003, and 07200026/2015001 July 1, 2015 Through September 30, 2015, Diablo Canyon Power Plant - NRC Integrated Inspection Report |
ML15170A453 | 19 June 2015 | Exhibit 2 - Letter from Dr. Michael Peck to Senator Barbara Boxer (January 22, 2015) |
ML15176A527 | 17 June 2015 | License Amendment Request 15-03 Application of Alternative Source Term. Part 1 of 8 |
DCL-15-069, Diablo Canyon, Units 1 and 2 - License Amendment Request 15-03 Application of Alternative Source Term. Part 1 of 8 | 17 June 2015 | Diablo Canyon, Units 1 and 2 - License Amendment Request 15-03 Application of Alternative Source Term. Part 1 of 8 |
ML15156B521 | 5 June 2015 | Petitioner Friends of the Earth'S Motion to Allow Supplemental Briefing |
IR 05000275/2015001 | 5 May 2015 | IR 05000275/2015001 and 05000323/2015001, January 1, 2015 Through March 31, 2015, Diablo Canyon, Units 1 and 2, Integrated Inspection |
ML15092A937 | 2 April 2015 | NRC Staff Answer to Friends of the Earth'S Appeal of Memorandum and Order LBP-15-6 (Denying Petition to Intervene and Petition for Waiver) |
DCL-15-023, License Amendment Request 15-01 - Incorporation Into Licensing Basis of Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident | 25 February 2015 | License Amendment Request 15-01 - Incorporation Into Licensing Basis of Pressurizer Filling Analysis for Major Rupture of a Main Feedwater Pipe Accident |
IR 05000275/2014005 | 29 January 2015 | NRC Integrated Inspection Report 05000275/2014005 and 05000323/2014005 |
ML15014A504 | 29 December 2014 | 14-1213(D.C.Cir.)PG&E Response to Motion to Dismiss |
ML15012A536 | 10 December 2014 | 14-1213(D.C.Cir.)Respondents Motion to Dismiss (Filed) |
IR 05000275/2014004 | 27 October 2014 | IR 05000275/2014004, 05000323/2014004; on 07/01/2014 - 09/19/2014; Diablo Canyon Power Plant; Operability Determinations and Functionality Assessments, Problem Identification and Resolution, Follow-up of Events and Notices of Enforcement Di |
IR 05000275/2014007 | 22 October 2014 | IR 05000275/2014007 and 05000323/2014007; 03/23/2012 - 09/11/2014; Diablo Canyon Power Plant; Problem Identification and Resolution (Biennial) |
ML14252A743 | 9 September 2014 | DPO Case File-DPO-2013-002 (Public) |
IR 05000275/2014002 | 23 April 2014 | IR 05000275-14-002, 05000323-14-002; on 01/01/2014 - 03/21/2014; Diablo Canyon Power Plant; Operability Determinations and Functionality Assessments, Refueling and Other Outage Activities |
DCL-14-030, Diablo, Units 1 and 2 - Report of 10 CFR 50.59, Changes, Tests and Experiments, for the Period of January 1, 2012 Through December 31, 2013 | 17 April 2014 | Diablo, Units 1 and 2 - Report of 10 CFR 50.59, Changes, Tests and Experiments, for the Period of January 1, 2012 Through December 31, 2013 |
IR 05000275/2013003 | 12 August 2013 | IR 05000275-13-003, 05000323-13-003, 05000323-13-003; 03/24/2013 - 06/30/2013; Diablo Canyon Power Plant, Integrated Resident and Regional Report; Licensed Operator Requalification, and Fire Protection |
IR 05000275/2013002 | 3 May 2013 | IR 0500275-13-002, 05000323-13-002; 01/01/2013 - 03/23/2013; Diablo Canyon Power Plant, Integrated Resident and Regional Report; Inservice Inspection Activities, Problem Identification and Resolution |
DCL-12-104, Ninety-Day Response to NRC Bulletin 2012-01: Design Vulnerability in Electric Power System. | 25 October 2012 | Ninety-Day Response to NRC Bulletin 2012-01: Design Vulnerability in Electric Power System. |
IR 05000275/2012003 | 3 August 2012 | IR 05000275-12-003, IR 05000323-12-003; 3/24/2012 6/22/2012; Diablo Canyon Power Plant, Integrated Resident and Regional Report; Adverse Weather Protection, Inservice Inspection Activities, Refueling and Other Outage Activities, Radiologica |
IR 05000275/2012007 | 4 May 2012 | IR 05000275-12-007, 05000323-12-007; 03/05/2012 - 03/22/2012; Diablo Canyon Power Plant Biennial Baseline Inspection of the Identification and Resolution of Problems |
DCL-12-035, Report for 10 CFR 50.59, Changes, Test, and Experiments, for the Period January 1, 2010, Through December 31, 2011 | 18 April 2012 | Report for 10 CFR 50.59, Changes, Test, and Experiments, for the Period January 1, 2010, Through December 31, 2011 |
IR 05000275/2011005 | 14 February 2012 | IR 05000275-11-005, 05000323-11-005; 9/26/2011 12/31/2011; Diablo Canyon Power Plant, Integrated Resident and Regional Report; Operability Evaluations |
IR 05000275/2011003 | 10 August 2011 | IR 05000275-11-003, 05000323-11-003; 3/28/2011 6/26/2011; Diablo Canyon Power Plant, Integrated Resident and Regional Report; Fire Protection, Plant Modifications, Identification and Resolution of Problems, and Radiological Hazard Assessmen |
IR 05000275/2011002 | 11 May 2011 | IR 05000275-11-002, 05000323-11-002; 1/1/2011 3/27/2011; Diablo Canyon Power Plant, Integrated Resident and Regional Report; Adverse Weather Protection; Heat Sink Performance and Permanent Plant Modifications |
DCL-11-018, License Amendment Request 11-02, Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) | 17 February 2011 | License Amendment Request 11-02, Revision to Technical Specification 3.7.1, Main Steam Safety Valves (Mssvs) |
IR 05000275/2010005 | 7 February 2011 | IR 05000275-10-005 & 05000323-10-005, on 09/26/2010 - 12/31/2010, Diablo Canyon Power Plant, Integrated Resident and Regional Report; Fire Protection; Operability Evaluations; Plant Modifications, Post Maintenance Testing, and Other Activit |
IR 05000275/2010006 | 9 September 2010 | IR 05000275-10-006, 05000323-10-006, on 03/29/10 - 07/27/10; Diablo Canyon Power Plant, Biennial Baseline Inspection of the Identification and Resolution of Problems |
IR 05000275/2010003 | 10 August 2010 | IR 05000275-10-003, 05000323-10-003, on 3/28/2010 - 6/26/2010; Diablo Canyon Power Plant, Integrated Resident and Regional Report; Identification and Resolution of Problems and Event Followup |
IR 05000275/2010007 | 23 July 2010 | IR 05000275-10-007, 05000323-10-007, on 02/08/2010 Through 06/10/2010, Diablo Canyon Power Plant: Baseline Inspection, NRC Inspection Procedure 71111.21, Component Design Basis Inspection. |
IR 05000323/2009009 | 9 March 2010 | IR 05000323-09-009 on 11/30/2009 - 01/25/2010 for Diablo Canyon, Special Inspection Report |
IR 05000275/2009003 | 5 August 2009 | IR 05000275-09-003 and 5000323-09-003; Pacific Gas Power Plant, Units 1 and 2; 03/28- 06/26/2009; Diablo Canyon Power Plant - NRC Integrated Inspection |
IR 05000275/2008004 | 3 November 2008 | IR 05000275-08-004, 05000323-08-004; 7/1/08 - 9/30/08; Diablo Canyon Power Plant Units 1 and 2; Equipment Alignment, Fire Protection, and Operability Evaluations |
IR 05000275/2008003 | 5 August 2008 | IR 05000275-08-003, 05000323-08-003 on 04/01/2008 - 06/30/2008 for Diablo Canyon, Units 1 and 2, Maintenance Effectiveness, Operability Evaluations, and Identification and Resolution of Problems |
IR 05000275/2006004 | 31 October 2006 | IR 05000275-06-004, 05000323-06-004; Pacific Gas and Electric Company; 07/02/06 - 9/30/06; Diablo Canyon Power Plant Units 1 and 2; Fire Protection, and Flood Protection |
IR 05000275/2006012 | 8 September 2006 | Second Errata for Diablo Canyon Power Plant - NRC Problem Identification and Resolution Inspection Report 05000275-06-012 and 05000323-06-012 |
IR 05000275/2004005 | 25 January 2006 | Errata of IR 05000275/2004-005 and 05000323/2004-005, 10/01/04 - 12/31/04, Pacific Gas and Electric Company, Operability Evaluations, Event Followup, Personnel Performance Related to Nonroutine Plant Evolutions and Events, Equipment Alignme |
IR 05000275/2005002 | 12 January 2006 | IR 05000275-05-002 and 05000323-05-002, Diablo Canyon Power Plant Replacement Pages |