IR 05000483/202000229 July 2020Integrated Inspection Report 05000483/2020002
IR 05000483/201700428 January 2018NRC Integrated Inspection Report 05000483/2017004 and Exercise of Enforcement Discretion
IR 05000483/201600212 August 2016NRC Integrated Inspection Report 05000483/2016002 and Notice of Violation
IR 05000483/20160085 May 2016NRC Problem Identification and Resolution Inspection Report 05000483/2016008
IR 05000483/201500913 January 2016IR 05000483/2015009, September 21, 2015 Through December 9, 2015, Callaway Plant - Special Report
IR 05000483/20140086 November 2014IR 05000483/2014008; on 08/11/2014 - 09/23/2014; Callaway Plant; Problem Identification and Resolution (Biennial)
IR 05000483/20140025 May 2014IR 05000483-14-002; on 01/01/2014 - 03/21/2014; Callaway Plant, Integrated Resident and Regional Report; Operability Determinations and Functionality Assessments, Follow-up of Events and Notices of Enforcement Discretion
IR 05000483/201300313 August 2013IR 05000483-13-003; 03/28/2013-6/30/2013; Callaway Plant, Integrated Resident and Regional Report; Maintenance Effectiveness, Maintenance Risk Assessments and Emergent Work Control, Problem Identification and Resolution, and Followup of Eve
IR 05000483/201200811 September 2012IR 05000483-12-008, 06/25/2012 - 07/13/2012, Callaway Plant, NRC Problem Identification and Resolution
IR 05000483/20120032 August 2012IR 05000483-12-003; 03/28-06/26/2012; Callaway Plant Integrated Resident and Regional Report; Flood Protection Measures and Operability Evaluations and Functionality Assessments
IR 05000483/201100318 July 2011IR 05000483-11-003, on 03/25/2011 - 06/23/2011 Callaway Plant, Integrated Resident and Regional Report, Flood Protection Measures, Operability Evaluations, Surveillance Testing, Radioactive Solid Waste Processing, Radioactive Material Handl
IR 05000483/201000329 July 2010IR 05000483-10-003, 03/25/2010 - 06/23/2010, Callaway Plant, Integrated Resident and Regional Report; Equipment Alignments, Refueling and Other Outage Activities and Event Follow-up
IR 05000483/200900328 July 2009IR 05000483-09-003, on 3/25-6/23/2009, Integrated Resident and Regional Report, Maintenance Risk Assessments and Emergent Work Control and Access Control to Radiologically Significant Areas
IR 05000483/20080085 December 2008IR 05000483-08-008; July 28 Through August 22, 2008; Callaway Plant: Baseline Inspection, NRC Inspection Procedure 71111.21, Component Design Basis Inspection
IR 05000483/200601226 December 2006IR 05000483/2006012, on 10/16/2006 - 11/30/2006, Callaway, Biennial Inspection of the Identification and Resolution of Problems