 Issue dateTitle
ML23143A39123 May 2023Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements
ML22090A09831 March 2022Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Design Requirements
IR 05000528/20210029 August 2021Integrated Inspection Report 05000528/2021002, 05000529/2021002, and 05000530/2021002 and Exercise of Enforcement Discretion
ML16365A24030 December 2016Emergency License Amendment Request to Extend Diesel Generator 3B Completion Time
ML16356A68921 December 2016Emergency License Amendment Request for a One-Time Extension of Diesel Generator Completion Time
ML16054A01212 February 2016FOIA/PA-2015-0294 - Resp 2 - Final, Agency Records Subject to the Request Are Enclosed. Part 4 of 8
ML16054A00812 February 2016FOIA/PA-2015-0294 - Resp 2 - Final, Agency Records Subject to the Request Are Enclosed. Part 1 of 8
ML16054A01412 February 2016FOIA/PA-2015-0294 - Resp 2 - Final, Agency Records Subject to the Request Are Enclosed. Part 6 of 8
ML15364A03424 December 2015Final Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)
ML15218A30031 July 2015License Amendment Request to Revise Technical Specifications to Adopt TSTF-505-A, Revision 1, Risk-Informed Completion Times
ML14177A64527 June 2014Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations
ML13136A02228 February 2013APS Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events
ML13025A28329 January 2013NRC Comments on Draft Integrated Plans, Palo Verde
ML13015A25617 December 2012Draft Submittal February 2013 FLEX Integrated Plan - Palo Verde
ML13081A09630 June 2011Updated Final Safety Analysis Report, Revision 16. Chapter 7, Instrumentation & Controls.
ML10236033512 August 2010Response to July 21, 2010, Request for Additional Information Regarding Metal Fatigue for the Review of the License Renewal Application, and License Renewal Application Amendment No. 22
ML06069048623 February 2006Supplement to Emergency Amendment to Technical Specifications 3.7.8, Essential Spray Pond System (Esps) and 3.8.1, AC Sources - Operating.
ML17300B30731 March 1999Seismic Portion of Submittal-Only Screening Review of Palo Verde Nuclear Generating Station Units Ipeee.
ML17305A53914 February 1990LER 89-018-01:on 891026,discovered That Containment Purge Valves Did Not Meet Local Leak Rate Testing Acceptance Criteria.Caused by Intergranular Stress Fracture.Spiral Pins Replaced.Reportable Per Part 21.W/900214 Ltr
ML20206B21331 March 1987Technical Specifications for Palo Verde Nuclear Generating Station,Unit 3.Docket No. 50-530.(Arizona Public Service Company)
ML17303A1811 December 1986Reactor Containment Bldg Integrated Leak Rate Test Summary Technical Rept. W/861208 Ltr
ML20129J77819 February 1985Forwards Std Accident Monitoring Instrumentation Tech Specs, Incorporating Heated Junction Thermocouple Sys & C-E Design for Reactor Vessel Level Monitoring Sys.Tech Specs Based on Tech Specs Approved by NRC for Palo Verde Unit 1
ML20039G84331 December 1981Palo Verde Nuclear Generating Station Units 1,2 and 3 Auxiliary Feedwater System Reliability Study Evaluation
ML17296B13125 September 1980Vol II of III of Transcript of 800925 & 26 Sys Review of Palo Verde Nuclear Generating Station Equipment Qualification,Before Equipment Qualification Review Board. Pp 214-389
ML18192B8303 February 1975Environmental Report Construction Permit Stage, Volume IV for Palo Verde Nuclear Generating Station, Units 1, 2, & 3.