ML13337A6255 December 2013Thadani M
Plant Licensing Branch I
Constellation Energy Nuclear Group, R.E. Ginna Nuclear Power Plant, Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool InstruRAI
ML14037A2779 February 2014NRC/NRR/DPR/MSD
Mega-Tech Services
Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for R.E. Ginna Nuclear Power Plant, TAC No.: MF1152Other
ML14007A70419 February 2014Jeremy Bowen
NRC/NRR/DPR/MSD/MSPB
R. E. Ginna Nuclear Power Plant - Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies)Acceptance Review
ML14245A05126 August 2014Exelon
Korsnick M G
August 2014 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Other
L-14-032, August 2014 Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)26 August 2014Exelon
Constellation
Korsnick M
August 2014 Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051)Other
RS-15-061, February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)20 February 2015Exelon
Constellation
Korsnick M
February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order No. EA-12-049)Other
RS-15-062, R. E. Ginna - February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051)20 February 2015Exelon
Constellation
Korsnick M
R. E. Ginna - February 2015 Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (EA-12-051)Other
ML15082A13131 March 2015Boska J
Japan Lessons-Learned Division
Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051Other
ML15154B33218 June 2015Boska J
Japan Lessons-Learned Division
Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051Other
RS-16-006, Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)4 January 2016Exelon
James Barstow
Report of Full Compliance with March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)Other