Issue date | From | Title | Project stage | |
---|---|---|---|---|
ML13063A183 | 28 February 2013 | Tennessee Valley Authority James Shea | Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) | Other |
ML13063A011 | 28 February 2013 | Tennessee Valley Authority James Shea | Overall Integrated Plan in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (EA-12-051) | Other |
ML13198A354 | 17 July 2013 | Farideh Saba Plant Licensing Branch II | Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order No. EA-12-051) | RAI |
ML13235A007 | 16 August 2013 | Tennessee Valley Authority James Shea | Response to NRC Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation | Response to RAI |
ML13247A286 | 28 August 2013 | Tennessee Valley Authority James Shea | First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | Other |
ML13247A291 | 28 August 2013 | Tennessee Valley Authority James Shea | First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant | Other |
ML13312A415 | 21 November 2013 | Siva Lingam Plant Licensing Branch II | Interim Staff Evaluation and Request for RAI Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation | RAI |
CNL-14-029, Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant | 28 February 2014 | Tennessee Valley Authority James Shea | Second Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant | Other |
CNL-14-033, Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | 5 March 2014 | Tennessee Valley Authority James Shea | Second Six-Month Status Report and Revised Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses Re Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | Other |
CNL-14-130, Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant | 28 August 2014 | Tennessee Valley Authority James Shea | Third Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Sequoyah Nuclear Plant | Other |
ML14302A197 | 6 November 2014 | Japan Lessons-Learned Division Tony Brown | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 | Acceptance Review |
CNL-15-038, Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 27 February 2015 | Tennessee Valley Authority James Shea | Fourth Six-Month Status Report in Response to March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | Other |
ML15033A430 | 3 March 2015 | Michael Brown Japan Lessons-Learned Division | Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 | Other |