Issue date | From | Title | Project stage | |
---|---|---|---|---|
L-07-017, License Amendment Requests Nos. 334 and 205 | 9 February 2007 | FirstEnergy Cosgrove T | License Amendment Requests Nos. 334 and 205 | Request |
ML071640121 | 3 July 2007 | Nadiyah Morgan NRC/NRR/ADRO/DORL/LPLI-1 | RAI, Recirculation Spray System Pump Start Signal License Amendment Request | RAI |
ML072250025 | 8 August 2007 | FirstEnergy Sena P | Responses to a Request for Additional Information (RAI) Dated July 3, 2007 in Support of License Amendment Request Nos. 334 and 205 | Request |
L-07-105, Supplemental Information for License Amendment Request Nos. 334 and 205 (TAC Nos. MD74290 and MD4291) | 23 August 2007 | FirstEnergy Sena P | Supplemental Information for License Amendment Request Nos. 334 and 205 (TAC Nos. MD74290 and MD4291) | Supplement |
L-07-126, Provides Supplemental Information in Support of License Amendment Request | 13 September 2007 | FirstEnergy Grada K | Provides Supplemental Information in Support of License Amendment Request | Supplement |
ML072820076 | 5 October 2007 | NRC/NRR/ADRO/DORL/LPLI-1 | Technical Specifications, Issuance of Amendment Changes to the Recirculation Spray System Pump Start Signal Due to the Containment Sump Screen Modification | Approval |
ML072680397 | 5 October 2007 | Nadiyah Morgan NRC/NRR/ADRO/DORL/LPLI-1 | License Amendment, Issuance of Amendment Changes to the Recirculation Spray System Pump Start Signal Due to the Containment Sump Screen Modification | Approval |
L-08-030, Supplemental Information in Support of License Amendment Request No. 205 | 25 January 2008 | FirstEnergy Sena P | Supplemental Information in Support of License Amendment Request No. 205 | Supplement |
ML080420549 | 11 March 2008 | Nadiyah Morgan NRC/NRR/ADRO/DORL/LPLI-1 | Issuance of Amendment Changes to the Recirculation Spray System Pump Start Signal Due to the Containment Sump Screen Modification | Approval |
ML080730027 | 11 March 2008 | NRC/NRR/ADRO/DORL/LPLI-1 | Technical Specifications to Amend 164 | Acceptance Review |
ML081570316 | 24 July 2008 | NRC/NRR/ADRO/DORL/LPLI-1 | Safety Evaluation by the Office of Nuclear Reactor Regulation for Beaver Valley Power Station, Unit No. 1 | Approval |
ML081570303 | 24 July 2008 | Nadiyah Morgan NRC/NRR/ADRO/DORL/LPLI-1 | Correction Letter the Recirculation Spray System Pump Start Signal Issued Amendment | Other |