Semantic search

Jump to navigation Jump to search
 Issue dateFromTitleProject stage
ML06080000321 March 2006Martin R
Plant Licensing Branch III-2
V.C. Summer - Request for Additional Information Regarding Instrumentation Test and Completion TimesRAI
RC-06-0067, LAR 05-2926 Implementation of WCAP-14333-P-A, Rev. 1, Probabilistic Risk Analysis of the RPS and ESFAS Test Times and Completion Times Response to Request for Additional Information31 May 2006South Carolina Electric & Gas Company
Archie J
LAR 05-2926 Implementation of WCAP-14333-P-A, Rev. 1, Probabilistic Risk Analysis of the RPS and ESFAS Test Times and Completion Times Response to Request for Additional InformationResponse to RAI
RC-06-0173, V. C. Summer - LAR 05-2926, Implementation of WCAP-14333-P-A, Rev. 1, Probabilistic Risk Analysis of RPS and ESFAS Test Times and Completion Times - Summarized List of Commitments29 September 2006South Carolina Electric & Gas Company
Archie J
V. C. Summer - LAR 05-2926, Implementation of WCAP-14333-P-A, Rev. 1, Probabilistic Risk Analysis of RPS and ESFAS Test Times and Completion Times - Summarized List of CommitmentsOther
ML06243068424 October 2006Martin R
NRC/NRR/ADRO/DORL/LPLII-1
V. C. Summer, License Amendment, WCAP-14333, Probabilistic Risk Analysis of the RPS and ESFAS Test Times and Completion Times.Acceptance Review
ML06300002624 October 2006NRC/NRR/ADRO/DORL/LPLII-1Technical Specifications, Implementing Approved Changes in Probabilistic Risk Analysis of the RPS and ESFAS Test Times and Completion Times.Request