Issue date | From | Title | Project stage | |
---|---|---|---|---|
ML20108E123 | 6 December 1984 | Southern Nuclear Gucwa L | Forwards NEDO-30825, Core Spray Sparger Crack Analysis for Ei Hatch Nuclear Power Station,Unit 1, in Response to IE Bulletin 80-13, Cracking in Core Spray Spargers | Other |
ML20134L704 | 22 August 1985 | Southern Nuclear Gucwa L | Submits Justification for Continued Operation for Unlimited Number of Cycles W/One or More Cracked Core Spray Spargers, Per IE Bulletin 80-13, Cracking in Core Spray Spargers & NRC .Ge NEDO-30825 Cited | Other |
IR 05000321/1985033 | 6 January 1986 | NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) Cline W Stoddart P | Insp Repts 50-321/85-33 & 50-366/85-33 on 851028-29,1118-22 & 1216.No Violation or Deviation Noted.Major Areas Inspected:Allegation Involving post-accident Sampling Sys & Plant Liquid & Gaseous Radioactive Effluents | Request |
ML20137B270 | 6 January 1986 | Southern Nuclear Gucwa L | Submits Results of Visual Insp of Core Spray Spargers, Associated Piping & Installed Clamping Device,Per IE Bulletin 80-13 & NRC .Approval for Continued Facility Operation Requested | Other |
ML20137D968 | 9 January 1986 | Muller D Office of Nuclear Reactor Regulation | Discusses 850822 Submittal Re Insp of Cracked Core Spray Spargers Per IE Bulletin 80-13.Requested Relief Will Be Granted After Insps Performed & Results Transmitted to NRC | Other |
ML20154J159 | 28 February 1986 | Southern Nuclear Gucwa L | Provides Addl Info Re Results of Recent Core Spray Sparger Exam Reported Per IE Bulletin 80-13 in .Extent of Insp Performed on Crack Discovered During Last Refueling Outage & Air Bubble Testing Discussed | Other |